Attachment 17 RFP Questions and Answers 2.pdf

PDF 240 KB Posted

Attached to
Request for Proposal U. S. Army Garrison Miami - UESC
Solicitation number
W912DY24R0047
Issued by

About this file

This is a Questions and Answers document addressing four inquiries related to RFP W912DY24R0047 for the U.S. Army Garrison Miami UESC project. The document clarifies that Amendment 0004, which suspended the acquisition on September 9, 2024, was not posted on SAM.gov due to the solicitation being cancelled.

The document addresses page limit requirements, confirming that Past Performance Questionnaires (PPQs) must be included within the 25-page limit with no increase to accommodate these forms. It specifies that PPQs should be provided for the same projects listed in Tab 2a (Previous Experience) and Tab 2b (Past Performance). Regarding evaluation criteria, offerors are directed to Factor II Previous Experience/Past Performance on page 47 of the solicitation for information on how proposals limiting PPQs will be evaluated.

View the file

Other files

File Type Posted
UESC Solicitation Amend 0007_USAG Miami_4Mar2025.pdf PDF
Attachment 16 Site Access Instructions.pdf PDF
UESC Solicitation Amend 0006_USAG Miami_12Feb2025.pdf PDF
Attachment 13 (LightingPlan-Bldg2-CCA).pdf PDF
UESC Solicitation Amend 0005_USAG Miami_6Feb2025.pdf PDF
Attachment 11 (SitePowerMap-wOneLine).pdf PDF
Attachment 15 (USAG-MiamiUsageFY20-24).pdf PDF
Attachment 14 (LightingPlan-Bldg3-AGB).pdf PDF
Attachment 10 RFP Questions and Answers.pdf PDF
Attachment 12 (LightingPlan-Bldg1-HQ).pdf PDF
UESC Solicitation Amend_0002_USAG_Miami_9Aug2024.pdf PDF
UESC Solicitation Amend 0003_USAG Miami_5Sep2024.pdf PDF
UESC Solicitation Amendment 0002 W912DY-24-R-0047_9Aug2024.pdf PDF
Solicitation_W912DY-24-R-0047_Amend_0001_USAG_Miami_17Jul2024.pdf PDF
Attachment 4a - DBA Wage Determination - Building.pdf PDF
Attachment 9 - BAA Certification for Contractors Signature.docx DOCX document
Attachment 4c - SCA Wage Determination.pdf PDF
Attachment 5 - Letter of Commitment of Key Subcontractor.docx DOCX document
Attachment 3 - UESC Data Item Descriptions.pdf PDF
Attachment 8 - Small Business Participation Plan.pdf PDF
Attachment 4b - DBA Wage Determination - Heavy.pdf PDF
Attachment 7 - Price Worksheet.xlsx XLSX spreadsheet
Attachment 2 - UESC Financial Schedules 1-5a.xlsx XLSX spreadsheet
Attachment 6 - Past Performance Questionnaire.docx DOCX document
Attachment 1 - PWS for USAG Miami.docx DOCX document
Solicitation_W912DY-24-R-0047_USAG_Miami_12Jul2024.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. We are not able to locate Amendment 04 on SAM.gov. Please confirm if this Amendment was issued and if a signed form should be returned with the proposal submission. Amendment 0004 was when the Government Suspended the acquisition until further notice, on 9 Sep 2024. The actual amendment was not posted due to the solicitation being cancelled.

2. Q&A item #8 indicates that completed PPQs are included in the 25-page limit. Please advise if the total page count for this section will be increased to accommodate for these forms or confirm that PPQs are not included in the page limit. The page count will not be increased and the PPQs are to be included in the page count.

3. Will the government provide a precise number of PPQs required, so that each o eror has the same number of pages available within the prescribed page count to address solicitation requirements other than past performance? PPQs should be provided for the same projects the O eror listed in Tab 2a - Previous Experience and Tab 2b – Past Performance

4. If not, will the government evaluate proposals more or less favorably if an offeror chooses to limit the number of PPQs in order to maximize page count focused on solicitation requirements other than past performance? Please see Factor II Previous Experience/Past Performance (Pg47) on how it will be evaluated.