This document is an amendment to a Request for Proposals (RFP) for the Howard A. Hanson Dam Additional Water Storage Project - Fish Passage Facility (Solicitation W912DW24R0004). The key changes in this amendment include:

  1. Revisions to the page limitations for the technical proposal factors related to construction management approach, past performance, and pre-construction services.
  2. Revision to extend the duration of CLIN 0001 for pre-construction services from 365 days to 518 days.
  3. Updates to the Statement of Work, including changes to preconstruction services, key personnel, design milestones, cost estimates, and construction specifications.
  4. Issuance of an editable Past Performance Questionnaire (PPQ) form.

The solicitation is an unrestricted full and open competition using the FAR 15 best value tradeoff process to award an Integrated Design and Construction (IDaC) contract. The North American Industry Classification System (NAICS) code is 237990 - Other Heavy and Civil Engineering Construction, with a small business size standard of $45 million.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment R0004 is to issue: revised page limitations for proposals, revised CLIN 0001 duration, revised 01 11 00-A - STATEMENT OF WORK, revised construction specifications, and an editable PPQ form. See the Continuation Sheet for additional details.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-May-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW24R0004

X 9B. DATED (SEE ITEM 11)

29-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-May-2024

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW24R0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

R0004

Summary of Changes in Amendment No. R0004

Note: Track changes used in the updated documents.

1. Revisions to the page limits for Factor 1 (GANT Chart), Factor 2 (CPARS / PPQs), and Factor 3

(resumes). See revised details in PROPOSAL SUBMISSIONS (SECTION 00 21 16).

2. This amendment revises and clarifies the duration for CLIN 0001 – Pre-Construction Services (Base

Item). The duration for this CLIN is 518 days. See revision to 52.211-10 – Commencement, Prosecution, and Completion of Work.

3. 01 11 00-A - STATEMENT OF WORK

Changes: 1.1.1 Preconstruction Services updated to replace the term “value engineering” with more specific language. 3.1 Key Personnel updated to include information regarding office space to be provided to the contractor. 3.3.9 Design Milestones updated to clarify deliverables language. 3.3.11 Other Interim Reviews updated PDT Review Period to seven days & BCOES Review Period to twenty-two days. 3.3.13.1 Cost Estimate corrected to indicate that cost estimates are to be provided at 65% and 80% design milestones. 3.3.13.4 Estimate Proposal for Construction Option Negotiations updated to remove language regarding final construction price or cost information, added reference to 00 73 00 Supplementary Conditions – IDAC Clause.

4. ATTACHMENT – CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS

Changes: Updated cover page to indicate that technical details are to be provided during design phase.

Removed 21 13 13 – WET PIPE SPRINKLER SYSTEMS, 21 13 16 – DRY PIPE SPRIKLER SYSTEMS & 21 30 00 – FIRE PUMPS from Division 21, added 21 11 00 – STANDPIPES.

5. Editable Past Performance Questionnaire (PPQ) form is issued with this amendment.

SUMMARY OF CHANGES

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

PROPOSAL SUBMISSION

A. PROPOSAL SUBMISSIONS (SECTION 00 21 16)

For clarity, the addressed section shall reference the Solicitation. The identified sections are in accordance with (IAW) the Construction Specifications Institute (CSI) pursuant to the U.S.

Army Corps of Engineers Desk Guide (UDG) 5114.201-1.

Section 00 21 16 of the Solicitation (Request for Proposal (RFP)) contains the proposal submission instructions. Section 00 21 16 includes specific information on what must be furnished with the offer and identifies evaluation criteria that will be used in evaluating proposals received. Section 00 22 16 contains the basis of award and evaluation methods/ratings.

1. INTRODUCTION

1.1. The Solicitation is an unrestricted full and open competitive acquisition using the

Federal Acquisition Regulation (FAR) Part 36, Construction and Architect- Engineer Contracts, and FAR 15.101-1, Tradeoff Source Selection Process (i.e., Best Value Tradeoff). One solicitation will be issued for the acquisition consisting of a Request for Proposal (RFP) pursuant to FAR 15.101-2 best-value tradeoff (BVTO) source selection process to award an Integrated Design and Construction (IDaC) contract.

1.2. Pursuant to Defense Federal Acquisition Regulation Supplement (DFARS)

236.204, the magnitude of construction is over $500 million.

1.3. The primary North American Industry Classification System (NAICS) code for the acquisition is 237990 – Other Heavy and Civil Engineering Construction.

Small Business Size Standard of $45 million.

1.4. Selection will be made based on the responsible Offeror whose proposal conforms to the Solicitation requirements, demonstrating high technical capability and low risk, presenting the most advantageous offer to the Government. The Government reserves the right to accept other than the lowest-priced offer or to reject all proposals.

1.5. The Government shall not reimburse any cost incurred or associated with preparing and submitting any responses to the Solicitation. Oral explanations or instructions to Offerors are not binding. Any information given to an Offeror which impacts the Solicitation and/or offers will be provided in the form of a written amendment to the Solicitation. It is the Offeror’s responsibility to acknowledge all amendments in its proposal submission.

1.6. The Offeror shall not modify the terms and conditions of the Solicitation in their technical proposals or add conditions or qualifications to their offers. If an Offeror include terms and conditions that conflict with the terms and conditions of the Solicitation, the Offeror may be determined ineligible for award. Any questions related to specific terms and conditions contained within the Solicitation should be resolved prior to the submission of an offer.

1.7. All proposals received will be considered complete and final. The evaluation board will not consider any information or data incorporated by reference or referred to other sources outside the respective proposal volumes and factors responses. The successful Offeror will be selected solely based on the stated evaluation factors. Accordingly, proposals submitted in response to the Solicitation should provide clear, complete, concise, and straightforward responses to the evaluation factors. Elaborate proposals, color brochures, and other excesses are discouraged.

1.8. Proposals that reiterate “Parroting” the contents of the Solicitation, or contain only superficial responses, may be considered unacceptable. Evidence of experience, capability, and qualifications demonstrating and supporting the Offeror’s claims is essential. The absence of such evidence will adversely influence the evaluation of the proposal.

1.9. References to “confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal.

The Offeror including confidential information in its proposal that they do not want to be disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall clearly mark their proposals IAW the instructions at FAR Clause 52.215-1, Instructions to Offerors –Competitive Acquisition, paragraph (e), Restriction on disclosure and use of data.

1.10. Use of the words “shall” or “must” indicate a mandatory requirement for which failure to comply at the time and date for submission of proposals may result in the Offeror’s proposal being disqualified from consideration for the award, or a deficiency or weakness being assessed for the factor. Failure to comply with non-pricing or pricing requirements annotated with the words “should” or “may” can result in an unacceptable rating, affecting the Offeror being selected for the contract award. The Government may elect during discussions with Offerors, to provide a means by which appropriate corrections by the Offeror(s) can be made.

If stated as a number of days, time periods are calendar days unless otherwise specified.

1.11. Project Labor Agreements (PLA) Executive Order 14063, Use of Project Labor

Agreements for Federal Construction Projects, issued 04 February 2022, provides that it shall be the policy of the Federal Government to use PLAs in connection with large-scale construction projects (defined as projects where the total cost to the Federal Government of the project is at least $35 million (using appropriated funds)) to promote economy and efficiency in Federal procurement.

Offerors shall submit an offer subject to Project Labor Agreement (PLA) requirements IAW FAR 22.504, General requirements for project labor agreements. Any PLA reached pursuant to the PLA requirements in the solicitation does not change the terms of the contract or provide for any price adjustment by the Government.

2. E-BUSINESS REGISTRATION REQUIREMENTS

2.1. System for Award Management (SAM). The Offeror shall be registered in SAM at the time an offer is submitted. Failure to have an active and completed registration in SAM [https://sam.gov/] may determine an Offeror ineligible for the award and removed from the competition. A successful Offeror with incomplete or expired registrations at the time of award may not be eligible for a contract. In such instances, the Government will award to the next successful Offeror who is eligible for the award. Information contained within an Offeror’s registration shall be current and valid. The responsibility of maintaining current information contained in an Offeror’s registration rests solely on the Offeror.

2.2. Procurement Integrated Enterprise Environment (PIEE). The Offerors shall submit its proposal through the PIEE Solicitation Module [https://piee.eb.mil/].

Note: Only those with a PIEE vendor registration role as ‘Proposal Manager’ may upload an offer.

Point of Contact for Vendor Registration/Technical System issues Email:

disa.global.servicedesk.mbx.eb-ticket-requests@mail.mil | Phone: 866-618-5988

The Offerors are cautioned to log into PIEE Solicitation Module with sufficient time to ensure the electronic proposal package is completely uploaded and time-stamped in the system by the due date and time specified for receipt of proposals.

2.3. Solicitation Inquiries

All inquiries regarding the Solicitation are to be submitted via ProjNet:

https://www.projnet.org/.

Telephone and e-mail inquiries will not be accepted. ProjNet is a web-based program that allows offerors to post question regarding the Solicitation and view all question by other offerors and responses by the Government.

a. The Offerors shall only submit one question per inquiry. All inquiries containing multiple questions will be rejected.

b. The Offerors will receive an acknowledgement of its question(s) via e-mail, followed by an answer to its question(s) after it has been processed. The Offerors may view all inquiries through ProjNet.

c. Inquiries shall be submitted fourteen calendar days prior to the proposal due date. The Offerors will not be able to submit inquires after this date.

To submit and review inquiries, offerors will need to use the inquiry key presented below and follow the instructions listed below the key for access.

The Inquiry Key is: 4M4T85-UNCM3X

Specific Instructions for ProjNet inquiry access:

a. From the ProjNet home page link: https://www.projnet.org/projnet/ click on

Quick Add (upper right side of the screen).

b. Identify the Agency: This should be marked as “USACE.”

c. Key: Enter the Inquiry Key listed above.

d. E-mail: Enter the e-mail address you would like to use for communication.

e. Click Continue. A page will then open saying that a user account was not found, and it will ask you to create one using the provided form.

f. Enter your first and last name, company, city, state, phone, e-mail, secret question, secret answer, and time zone. Make sure to remember your secret question and answer, as they will be used from the point you access the ProjNet system.

g. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

2.4. Submit questions or review questions and answers. An Offeror who submits a question will receive an automated e-mail notification that its question has been received. When an answer is posted to a question, the question and answer are then available for all other offerors to review.

2.5. Pre-Proposal Conference/Site Visit. A formal site visit will be conducted. The Offerors are encouraged to visit the site prior to submitting a proposal.

2.6. Late Proposals. Any proposals, amendments, or revision received by the

Government after the exact time specified for receipt offers is “late” and will not be considered unless it is received before award is made, the KO determines that accepting the late offer would not unduly delay the acquisition, and 1) if it was transmitted through an electronic commerce method authorized by the Solicitation, and it was received at the initial point of entry to the Government infrastructure no later than 4:00 PM (Pacific Standard Time), one calendar day prior to the date specified for receipt of proposals; or 2) there is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or 3) it is the only proposal received. However, a late amendment of an otherwise successful proposal that makes its terms more favorable to the Government will be considered at any time it is received and may be accepted.

2.7. Joint Venture. A joint venture (JV) is defined as a legal business entity formed between two or more companies to undertake the performance activities of a contract together. The Offerors proposing as JV shall provide evidence that the JV as a legal entity has been duly formed. The JV shall include a copy of the legal JV agreement signed by an authorized officer from each of the firms comprising the JV, with the Chief Executive of each entity identified. The Government will not evaluate the capability of any firms that are not included in the JV agreement. If submitting a proposal as a JV, the experience of each of the JV partners can be submitted for the JV entity. The experience of either JV partner will be considered the experience of the JV entity. Prospective Offerors that submit proposals may not change their JV firms, if selected for award. If an Offeror is a JV, the JV entity shall have a valid registration representing the JV as one business/firm/entity in SAM. The Government will not accept separate registrations and licenses from each separate entity representing the JV.

2.8. Subcontractor Substitutions. Approval will not be given unless the KO considers the proposed substitute equal or better in all respects to the originally proposed subcontractor and that the substitution is in the Government’s best interests. If the Offeror’s proposal includes the use of subcontractors, the Offeror may only change subcontractors with the KO approval. If the Offeror proposes to change subcontractors after award, the Offeror may not change subcontractors or Letter of Commitment (LOC) without the KO’s approval.

2.9. Unsuccessful Offerors will be notified IAW FAR Subpart 15.5. An unsuccessful offeror may request a pre-award debriefing or a delayed debriefing after award (post-award debriefing) by submitting a written request to the KO within three-calendar days after receipt of the notice excluding an offeror from the competition and award. The Offerors are entitled to no more than one debriefing for each proposal (e.g., pre- or post-award debriefing).

3. PROPOSAL VOLUME INSTRUCTIONS, REQUIREMENTS, CONTENTS, AND

FORMAT

INSTRUCTIONS TO OFFERORS

3.1. Content – General.

An Offeror’s proposal without the minimum content may be determined ineligible for award and removed from the competition. The Government will not make assumptions concerning intent, capabilities, or experiences. Clear identification of proposal details shall be the sole responsibility of the Offeror. The Government may reject incomplete proposals after initial evaluation without further consideration.

All information intended to be evaluated as part of the technical proposal shall be submitted within the technical proposal. Do not include references to material or information not found within its respective volumes. Information submitted in the wrong volumes could lead to an Offeror’s proposal being determined unacceptable if materially incomplete in any aspect.

The Government will not evaluate any material that exceeds the page limits specified within each evaluation factor. Elaborately prepared proposals are optional, and any material over what is requested, such as corporate marketing information, will not be considered.

The submission shall be clearly indexed and logically assembled. The Offeror’s proposal must set forth full, accurate, and complete information as required by the Solicitation. Absence of information will be deemed as if no support for that criterion was provided. The Offerors submitting proposals should limit submission to data essential for evaluation of proposals so that a minimum of time and money is expended in preparing information required by the Solicitation.

Penalty for making false statements in its proposal is prescribed in Title 18 United States Code (U.S.C.) Section 1001.

3.2. File Format

The Offeror’s proposal shall be submitted via electronic – Portable Document Format, filename extension “.pdf,” suitable for viewing in Adobe Reader, and text must be searchable.

3.3. Proposal Format

Cover Page: A cover page shall appear at the beginning of each volume and, at a minimum, shall consist of the following information:

a. Solicitation Number

b. The Offeror’s name, physical mailing addresses, telephone number, and email address of the official having the authority to bind the Offeror contractually.

c. The Offeror’s (if a JV provide each firm’s) Unique Entity Identifier (UEI), Commercial and Government Entity (CAGE) code, and Tax Identification Number (TIN).

Table of Contents: The Offeror shall provide a table of contents, placed in each volume, and shall identify major areas by title, volume location, and page number.

Volumes: The Offeror shall provide three separate proposal volumes: Volume I – General and Contract Documentation, Volume II – Technical Proposal, and Volume III – Cost/Price

Proposal volume organization, number of copies, and page limits. The Offeror shall prepare its proposal as set forth below. The Government will not evaluate any pages that exceed the page limitations identified in the Solicitation.

VOLUM

E

TAB VOLUME TITLE

DIGITAL

COPIES

PAGE LIMIT

(Any pages over the page limit will not be reviewed)

I General and Contract Documentation

1 No limit

II

Technical Proposal

Factor 1: Construction Management Approach

20 pages, including excluding the GANT

Chart

2 Factor 2: Past Performance 1 15 pages Project

Descriptions, excluding CPARS and PPQs.

3 Factor 3: Pre-Construction Services 1

20 pages Pre- Construction Services Management Plan and

Design Review, excluding team resumes.

4 Factor: Small Business Commitment 1 No Limit

III Factor 5: Cost/Price 1 No Limit

Relative Importance of Evaluation Factors is in descending order Factor 1:

Construction Management Approach, Factor 2: Past Performance, Factor 3: Pre- Construction Services, and Factor 4: Small Business Commitment. The non-priced factors when combined are significantly more important than price.

***Evaluation Criteria for PLA: The PLA will not be an evaluation factor, but it will be evaluated by the Contracting Officer to ensure the PLA addresses the requirements of FAR Provision 52.222-33. The PLA must address the requirements of FAR 52.222-33 or the offer will be unacceptable for an award.

Volume I – General and Contract Documentation

Volume I shall be clearly marked “VOLUME I – SOLICITATION W912DW24R0004 – General and Contract Documentation.”

a. Signed Solicitation, Offer, and Award (Standard Form (SF) 1442) with Blocks

14 thru 20c completed, including acknowledgement of all amendments.

b. Completed Representation and Certification (Section 00 45 00)

c. A statement indicating compliance with all insurance requirements stated herein and that evidence of such will be provided after contract award.

d. Bid Bonds (see reference to FAR Provision 52.228-1)

e. Proof of Bonding Capability. The Offeror must provide a letter or other documentation from a surety appearing on the Department of Treasury Circular 570 (list of approved sureties) stating that the Offeror is able to obtain performance and payment bonds in at least the amount of the offered total evaluated price of the construction services appearing on the proposal schedule. Before the construction option CLIN is converted into an FFP construction CLIN, the contractor shall furnish payment and performance bonds to the KO in the amount equal to 100 percent of the final construction price.

f. A list of present commitments, including the dollar value thereof. Include names and telephone numbers of personnel within the organization who are familiar with company’s performance. For a newly formed JV, each JV partner must submit a list of present commitments.

g. Organizational Conflicts of Interest (OCI) Disclosure. The Offeror shall provide a disclosure statement with its proposal that concisely describes all the relevant facts concerning any past or present OCIs relating to the Solicitation. If applicable, in the same statement, the Offeror shall provide information to assure the Government that the conflicts of interest have been mitigated and/or neutralized to the maximum extent possible. If a conflict of interest is discovered after the award, the KO will decide on whether to terminate the contract. If no conflicts of interest exist, the Offeror shall provide a statement stating no Conflicts of Interest exist.

h. Financial Statement. Submit a copy of your most recent financial statements.

The statements must include a Balance Sheet and Income Statement. Include the names of banks or other financial institutions with which business is conducted (mailing addresses, points of contact and phone number). If the financial statements are more than 60 days old, attach a certificate stating that the financial condition is substantially the same, or if not the same, describe the changes which have taken place since the financial statements were prepared.

i. Bank Letters. Provide evidence of adequate financing arrangements, such as commitments from lending institutions, etc., to perform this contract. Include the names of banks or other financial institutions where business is conducted (mailing addresses, points of contact, and phone numbers). Reference letters should include the following information: (1) the date the Offeror’s account was opened with the financial institution, (2) the average balance for the last 12 months on the Offeror’s account (i.e., balance in the xx digits), (3) if there is a credit line established with the financial institution, what is the credit amount and how much is available at this time? If not, would the financial institution be willing to establish a line of credit for the Offeror? And if so, for how much (i.e., low xx figure range), (4) how does the financial institution evaluate the Offeror as a customer (i.e., poor, fair, very good, excellent, etc.), and (5) the financial institution should declare whether the Offeror’s account is in good standings. This information will be treated confidentially but may be checked for verification.

j. Project Labor Agreements. All Offerors are required to submit a complete and signed Project Labor Agreement (PLA) for evaluation by the Contracting Officer. Any PLA submitted with the offer must comply with the requirements of FAR Provision 52.222-33. (A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f)).

Volume II – Technical Proposal

Volume II shall be clearly marked “VOLUME II – SOLICITATION W912DW24R0004 – Technical Proposal.”

Volume III – Cost/Price

Volume III shall be clearly marked “VOLUME III – SOLICITATION W912DW24R0004 – Cost/Price.”

SECTION 00 72 00 - GENERAL CONDITIONS

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 518 365 days for Design/1,824 days for Construction. Total duration for pre-construction and construction services is 2,189 days. The time stated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)