This document is an Acquisition Plan/Strategy for an Integrated Design and Construction (IDaC) contract for the Howard A. Hanson Dam Additional Water Storage Project - Fish Passage Facility. The IDaC approach involves concurrent design and construction through a fixed-price contract with an economic price adjustment (EPA) clause. Key details include:
The base CLIN is for pre-construction services, with an option CLIN for the construction phase. The construction option will use a fixed-price incentive structure, with a target cost, target profit, ceiling price, and share ratio for cost variances. A Project Labor Agreement (PLA) is required. The contract will be awarded on a best value trade-off basis, considering technical/non-price and price factors. The EPA clause allows for adjustments to material prices during construction. This IDaC approach aims to incentivize the contractor to identify cost savings measures and share the benefit with the government.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQUISITION PLAN/STRATEGY
Integrated Design and Construction (IDaC)
Fixed-Price with Economic Price Adjustment (EPA) Clause
Project Labor Agreement
WHAT IS IDAC?
Integrated Design and Construction (IDaC) is an integrated project delivery method that develops a holistic team consisting of the Government, Designer and Constructor.
"Integrated Design and Construction" means the construction contract type where design and construction are contracted concurrently through two efforts. Specific to this project, the design (i.e., architect-engineer) will be performed in-house (i.e., by the Government), and an award will be made to a construction contractor.
It is not a design contract, a noncompetitive acquisition, a design build contract nor is it a cost reimbursable contract.
Base CLIN: Preconstruction Services; Option CLIN(s): Construction Services.
Government (USACE)
Designer (In-House/AE)
Consultants
IDaC Contractor
Prime-Subcontractor
Stakeholder
INTEGRATED DESIGN & CONSTRUCTION (IDAC)
• IDaC is a design-bid-build delivery method where construction can only commence under a FFP Contract, avoiding a cost reimbursable environment. The contractor is never in a position where they construct at a cost that cannot be supported.
• Focus on the three factors that impact success (AIA & AGC “Integration/Collaboration; Innovation;
Partnering) with an emphasis on Integration and Collaboration.
• The Govt procures the IDAC contractor during design, to work with the DoR, providing pre-construction phase consultation services (at a FFP).
• Pre-construction services is the base scope of work.
• Conversion point: An Option for the construction phase at a maximum binding ceiling price with an Initial Target Cost and Initial Target Profit.
• The construction contractor is incentivized to proactively identify cost saving measures that would bring the Final Target Cost in lower than the Initial Target Cost, resulting in more contractor profit (through shared savings).
• The Ceiling Price is the maximum amount the Government will pay. The Option cannot be exercised if the Final Construction Price is greater than the Ceiling Price. Instead, the contractor is off-ramped and the construction scope can be competed on the open market as a new contract.
• IDaC is executed contractually by adapting the FAR FPIS Clause 52.216-17 (using an authorized deviation) specifically for Army construction projects, resulting in a FFP construction contract with a profit incentive formula.
IDAC PROJECT DELIVERY METHOD
Traditional - DBB
AE Firm-Fixed-Price ConstructionProposal Finish
IDaC
AE
Firm-Fixed-Price Construction FinishPre-Construction ServiceProposal
Traditional FFP Administration
Fixed-Price Incentive Contract
Proposal (Competition) – Initial Target Price (ITP)
Design Progress
Design Milestone (65/80/95/100)
Did Scope Change?
Yes
Negotiate Revision to
Initial Target Cost (ITC)
No
Request Proposal for Firm Target
Cost
(FTC)
Negotiate FTC and apply Profit Adjustment
Agreement
Negotiate FFP using Firm Target as Guide
Agreement
Complete Construction as
FFP
Production Point Reached?
Yes
No
No
Off-Ramp Compete
Design-Bid-Build
No
No
DO NOT Fast Track Construction Prior to
Design Complete
IDAC PROJECT DELIVERY METHOD (CONT)
BEST VALUE TRADEOFF
TECHNICAL /
NON-PRICE
FACTORS
Performance Confidence Technical Approach
• PreCon Services
• Construction Small Business Participation
$ PreCon Services Firm-Fixed-Price $ IDAC Option > Ceiling Price Total Evaluated Price
PRICE
FACTORS
(Best Value Trade-off)
SOURCE SELECTION
PROCESS
FIXED PRICE INCENTIVE CONCEPT
Government point of view As cost decreases, price to the
Government decreases Share the risk of cost increase Ceiling Price limits the
Government’s exposure
Contractor point of view Contractor can increase profit dollars and profit percentage by reducing cost below target cost
Share Ratio above target price provides risk mitigation to the Contractor
IDAC CONTRACT STRUCTURE
Service CLIN
Construction
CLIN
*Total Evaluated Price = CLIN 0001 Firm Fixed Price + CLINs 0002 Ceiling Price **CLIN Price = ITC + ITP; ITC will be evaluated for reasonableness
IDAC CONTRACT STRUCTURE (CONT)
CLIN 0002 Scope of Work Price Breakdown
Item Description Quantity UOM Initial Target Cost 000201 Mobilization and Demobilization 1 JOB $ 000202 Site Improvements 1 JOB $ 000203 Excavation 1 JOB $ 000204 Intake Structure 1 JOB $ 000205 Bulkhead 1 JOB $ 000206 Multi-port Collector 1 JOB $ 000207 Steep Slope Bypass 1 JOB $ 000208 Tower 1 JOB $ 000209 Tunnel 1 JOB $ 000210 Outlet Structure 1 JOB $ 000211 Emergency Mobilization and Demobilization 1 EA $ 000212 Operations and Maintenance (O&M) Manuals 1 JOB $ 500,000 000213 Record Drawings 1 JOB $ 250,000
0002 Initial Target Cost TOTAL $
Design P&S 35% DDR 65% 80% 95% 100%
IDaC Contract Pre-Construction Services Construction
Convert Option
PRECONSTRUCTION SERVICES CLIN
Preconstruction Services include:
Consultation in construction methodology, current market conditions and identification of coordination issues;
Construction cost estimates -to validate designer prepared estimates at each review phase -for alternative designs and materials -for changed market conditions
Cost control When there is a significant difference or the construction estimate exceeds the target, the estimates will be examined to determine the cause for the differences and steps made to correct the Government or contractor estimates
NOTE: The contractor shall not be responsible for any design services.
The responsibility of the design will remain wholly with the Designer of Record.
Preconstruction Services, minimum Key Personnel include:
Pre-Construction Project Manager (PPM) Engineering Manager/Coordinator Construction Superintendent Lead Cost Estimator/Engineer Lead Scheduler
(Reference RFP, Section 00 22 16)
CONSTRUCTION OPTION CLIN
• TARGET COST + TARGET PROFIT = TARGET
PRICE
• CEILING PRICE
• SHARE RATIO AND PROFIT ADJUSTMENT
INCENTIVES
• ONLY EXERCISED BILATERALLY
• CONSTRUCTION MUST BE DEFINITIZED FFP
PRIOR TO EXECUTION.
CONSTRUCTION OPTION CLIN (CONT)
The Offeror proposed a Target Cost of $100 and a Target Profit of $15. Based on the RFP Share Ratio of 60/40 and a proposed Ceiling Price of $130. What will the profit for the Offeror if the actual cost is $110?
EXAMPLE
Cost Variance Target Cost $100
Actual Cost $110= -
-$10
• Cost Variance is the risk associated with cost estimates.
• Cost Variance is divided between the Government and Offeror/Contractor
How do we distribute the risk?
Share Ratio = The Government’s share of risk (%) / Contractor’s Share of risk (%)
RFP Share Ratio of 60/40
Reference RFP Section 00 73 00 - Supplementary Conditions | IDAC CLAUSE 5152.236-XX Integrated Design and Construction Contract. INTEGRATED DESIGN AND CONSTRUCTION CONTRACT (ONE
TIME DEVIATION)
Share Ratio Government 60%
Contractor 40%= /
60% X (-$10) = -$6 40% X (-$10) = -$4/
Based on the example, did the Contractor get a positive or negative incentive?
A negative incentive as the Contractor may not have manage the cost properly.
Actual Price Actual Cost $110
Target Profit $15= +
$121
Contractor’s Share of Risk $4-
Actual Profit Actual Price $121
Actual Cost $110= -
$11
A B C D E
Actual Cost $ Target Cost = $100 Target Profit = $15 Price Ceiling = $130 Share Ratio = 60/40
Cost Variance ($)
[TC – AC]
Contractor's Share of Risk ($)
[Cost Variance X KTR’s Share Risk % [40%]
Actual Price ($)
[AC + TP + KTR’s Share Risk OR
CP]
Actual Profit ($)
[AP – AC]
90 10 4 109 19 95 5 2 112 17
100 0 0 115 15 105 -5 -2 118 13 110 -10 -4 121 11 115 -15 -6 124 9 120 -20 -8 127 7 125 -25 -10 130 5 130 -30 -12 133 0 135 -35 -14 136 -5
140 -40 -16 139 -10 145 -45 -18 142 -15
90 95 100 105 110 115 120 125 130 135 140 145
Actual Price ($)
Actual Price ($)
-20
-15
-10
-5
90 95 100 105 110 115 120 125 130 135 140 145
Actual Profit ($)
Actual Profit ($)
-20 -15 -10
-5
90 95 100 105 110 115 120 125 130 135 140 145
Actual Price ($) Actual Profit ($)
GENERAL EXAMPLE
AWARD CLIN STRUCTURE (EXAMPLE)
Option CLIN – Construction Services
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 PRE-CONSTRUCTION SERVICES 1 Job $ 5,000,000.00 $ 5,000,000.00
FFP
This CLIN funds all labor, material, equipment, etc. to perform Pre-Construction Services IAW the HHD FPF IDaC Scope of Work and accepted proposal dated XX Month YYYY
FOB: Destination
PURCHASE REQUEST NUMBER WXXXXXXXXX
PSC CD: R499
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 OPTION CONSTRUCT HHD FPF 1 Job $
FPI
OPTION CONSTRUCT HHD FPF
Proposed Ceiling Price (IDaC) FOB: Destination
PSC CD: Y1AZ
TARGET COST $ 475,000,000.00
TARGET PROFIT $ 19,000,000.00
TOTAL TARGET PRICE $ 494,000,000.00
CEILING PRICE $ 570,000,000.00
SHARE RATO ABOVE TARGET 60/40
SHARE RATIO BELOW TARGET 40/60
Base CLIN – Pre-Construction Services
ECONOMIC PRICE ADJUSTMENT (EPA)
FAR 16.203 “A fixed-price contract with economic price adjustment provides for upward and downward revision of the stated contract price upon the occurrence of specified contingencies.”
• EPA should be used when it is anticipated that risks associated with market instability over the duration of a contract are such that proposed prices would include exceptionally high contingency
• Should take into consideration duration of the contract, market conditions, and industry interest
• Should also consider the impact of those cost elements (labor categories, materials, or end products) that will be considered
Established Prices
• Adjustments are based on published or pre-established pricing (price
• Best fit for basic materials where standard or semi-standard pricing is readily available
• FAR Clause 52.216-2 or -3 applies
Actual Costs
• Adjustments based on actual prices
• Contract cannot include significant design
• Actual costs must be sufficiently documented to establish adjustments
• May disincentivize seeking best pricing
• FAR Clause 52.216-4 applies
Indexes
• Adjustments based on price indexes
• Best when quantities can be reasonably estimated, and indexes are available for identified materials/ commodities
• FAR Clause 52.216-4 or Custom clause language
Reference RFP, Scope of Work Price Breakdown Notes, Paragraph 6:
The price proposal must include a completed CLIN 0002 ECONOMIC PRICE ADJUSTMENT TABLE
a. Labor shall not be adjusted. Only the materials identified for base CLIN 0001 and option CLIN 0002 are subject to Economic Price Adjustment (EPA) in accordance with FAR Clause 52.216-4 Economic Price Adjustment – Labor and Material. Please see the Table below for additional information on the schedule of materials. The EPA Table price per unit of measure shall only account for the actual cost of material and shall not be burdened by other associated costs.
b. This is a not to exceed (NTE) quantity. EPA will be based on actual quantities performed. Contractor is to provide an estimated NTE quantity in the table at the time of bid. When submitted for EPA consideration, the quantity shall be rounded to the nearest unit of measure.
c. The CLIN schedule shall be submitted fully completed and error free. The offeror shall input a two (2) decimal price in the “Unit Price.” All final monetary extensions in two decimal positions only. Example: $0.27, not $0.27458.
Misc.
Steel
Structural Steel
Steel (Rebar)
Stainless Steel
Aggregate (Concrete
& Fill) Fly Ash
Cement
Unit Price CLIN 000202 Site Improvements
CLIN 000203 Excavation CLIN 000204 Intake Structure
CLIN 000205 Bulkhead CLIN 000206 Multi-port Collector CLIN 000207 Steep Slope Bypass
CLIN 000208 Tower CLIN 000209 Tunnel
CLIN 000210 Outlet Structure
*Estimated quantities are strictly for the purpose of administrating this clause. This is not for the purpose of variation of estimated quantities, or any other cost/quantity related data as applies to this contract. However, price adjustments to CLIN 0002 are limited to, at a maximum, the estimated quantities identified here.
Propose $ per/Quantity
Propose $ per/Quantity
PROJECT LABOR AGREEMENT (PLA)
What is PLA?
PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f))
Note FAR Provision 52.222-33 Notice of Requirement for Project Labor Agreement, and FAR Clause 52.222-34 PLA, for definitions and requirements pertaining to the use of a PLA for this contract.
The Offerors shall submit an offer subject to PLA requirements in accordance with FAR 22.504, General requirements for project labor agreements. Any PLA reached pursuant to the PLA requirements in the Solicitation does not change the terms of the contract or provide for any price adjustment by the Government.
All Offerors are required to submit a complete and signed Project Labor Agreement (PLA) for evaluation by the Contracting Officer.
UAI 5122.503-100(c) “Since USACE is not an employer engaged primarily in the building and construction industry, USACE will neither negotiate nor become signatory to a PLA. See USACE Desk Guide (UDG) 5122.503-1 for PLA Frequently Asked Questions (FAQs).”
The USACE Head of Contracting Activity provides additional guidance for contractors having difficulties in putting together PLAs. The Laborers International Union of North America (LIUNA) will provide assistance at www.liuna.org.
http://www.liuna.org/
| Acquisition PLAN/strategy |
| What is idac? |
| Integrated design & construction (IDAC) |
| IDaC project delivery method |
| Slide Number 5 |
| Best value tradeoff |
| Fixed Price Incentive concept |
| Slide Number 8 |
| Slide Number 9 |
| Preconstruction services CLIN |
| Construction Option CLIN |
| Construction Option CLIN (Cont) |
| Construction Option CLIN (Cont) |
| Construction Option CLIN (Cont) |
| Construction Option CLIN (Cont) |
| Construction Option CLIN (Cont) |
| General Example |
| Award CLIN Structure (example) |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |