Summary of changes in Amendment 3 (R0003).docx
DOCX document 20 KB Posted
- Attached to
- Libby Dam DC Boards and Breakers, Libby, MT Federal contract opportunity
- Solicitation number
- W912DW22R0036
About this file
This document is a summary of changes made in Amendment 3 to the solicitation and plans for the Libby Dam DC Boards and Breakers replacement project in Libby, Montana. Key changes include revising project descriptions and work sequences, modifying payment retainage terms, revising mobilization specifications, updating electrical panel layouts and notes, adding requirements for conduit and tray design, and adjusting cable schedules including lengths, conductor types and removing internal cables. The related federal contract opportunity is solicitation number W912DW22R0036 issued by the Department of the Army Corps of Engineers Engineering District Seattle to replace DC boards and breakers at Libby Dam. The solicitation, plans and specifications are attached for prospective bidders to review the project scope and requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 22R0036_0003.pdf | ||
| Amendment 3 Contract Drawings R0003.pdf | ||
| SUBMITTAL REGISTER R0003.pdf | ||
| TABLE OF CONTENTS R0003.pdf | ||
| 01 11 10.00 26 R0003.pdf | ||
| 01 12 16.00 28 R0003.pdf | ||
| 01 30 00 R0003.pdf | ||
| 00 73 00-A R0003.docx | DOCX document | |
| 01 22 00 R0003.pdf | ||
| 22R0036R2.pdf | ||
| W922R0036R1.pdf | ||
| Libby PLANS DC Boards and Breakers Replacement Color .pdf | ||
| FY21 Powerhouse DC Boards and Breakers Replacement.pdf | ||
| Reference Drawings Rev. 5.pdf | ||
| W912DW22R0036.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY21 Powerhouse DC Boards and Breakers Replacement 21016 Kootenai River, Montana Summary of changes in Amendment no. 3 (R0003)
1. 01 11 10.00 26 SUMMARY OF WORK
Changes: Revised project descriptions
2. 01 12 16.00 28 WORK SEQUENCE
Changes: New specification being added
3. 01 22 00 MEASUREMENT AND PAYMENT
Changes: Revised Retainage of Payment
4. 01 30 00 ADMINISTRATIVE REQUIREMENTS
Changes: Revised mobilization
5. ED202 - AUXILIARY CONTROL SWBD ER1 - 24/48 & 125VDC PANELS CD1, CO2, & CE1 – REMOVAL Changes: UPDATED ER14PANELLAYOUTAND NOTE 3TO CLARIFY INTENT
6. E-103 - PARTIAL PLAN EL 2114.00 INSTALL
Changes: ADDED NOTE 3 FOR THE CONTRACTOR TO DESIGN TRAY AND CONDUITS ROUTING
7. E-202 - AUXILIARY CONTROL SW BD ER1 24/48 & 125VDC PANELS CD1, CD2, CE9 INSTALL Changes: 1. UPDATED ER14PANELLAYOUTTO CLARIFY INTENT. 2.UPDATED BREAKER PANELSCHEDULES FOR CE9,CE1AND CE2
8. E-207 - UNIT CE BOARDS CE1-CE6 ELEVATION VIEWS INSTALL
Changes: ADDED NOTE 2TO SUPPLY CE6PANELONLY
9. E-701 - BATTERY SW ITCHBOARD SB1 W IRING DIAGRAM INSTALL
Changes: UPDATED CABLE NAMES TO MATCH C&C SCHEDULES
10. E-801 - CABLE AND CONDUIT SCHEDULE - SHEET 1 OF 5 – INSTALL
Changes: 1. UPDATED CABLE LENGTHS, REMOVED INTERNALCABLES. 2. UPDATED SOME SINGLE CONDUCTOR CABLES TO MULTI-CONDUCTOR CABLES
11. E-802 - CABLE AND CONDUIT SCHEDULE - SHEET 2 OF 5 – INSTALL
Changes: 1. UPDATED CABLE LENGTHS, REMOVED ALLINTERNALCABLES. 2. UPDATED SOME SINGLE CONDUCTOR CABLES TO MULTI-CONDUCTORS CABLES
12. E-803 - CABLE AND CONDUIT SCHEDULE - SHEET 3 OF 5 – INSTALL
Changes: 1. UPDATED CABLE LENGTHS, REMOVED ALLINTERNALCABLES. 2. UPDATED SOME SINGLE CONDUCTOR CABLES TO MULTI-CONDUCTORS CABLES
13. E-804 - CABLE AND CONDUIT SCHEDULE - SHEET 4 OF 5 – INSTALL
Changes: 1. UPDATED CABLE LENGTHS, REMOVED ALLINTERNALCABLES. 2. UPDATED SOME SINGLE CONDUCTOR CABLES TO MULTI-CONDUCTORS CABLES
14. E-805 - CABLE AND CONDUIT SCHEDULE - SHEET 5 OF 5 – INSTALL
Changes: 1. UPDATED CABLE LENGTHS, REMOVED ALLINTERNALCABLES. 2. UPDATED SOME SINGLE CONDUCTOR CABLES TO MULTI-CONDUCTORS CABLES 1 R0003