01 12 16.00 28 R0003.pdf

PDF 525 KB Posted

Attached to
Libby Dam DC Boards and Breakers, Libby, MT Federal contract opportunity
Solicitation number
W912DW22R0036
Issued by
Department of the Army Corps of Engineers Engineering District Seattle

About this file

This solicitation package includes specifications for replacing direct current boards and breakers at Libby Dam in Montana. The work will require providing temporary power to switchboards and panelboards during equipment replacement. Outages for connecting temporary power are limited to one hour, and generating unit outages require 24 days' advance notice to allow the power administration time to adjust operations. The contractor must submit an equipment replacement and cutover plan at least 90 days prior to installation start detailing the removal and installation procedures and outage schedule. Temporary power cables must meet wire and cable specifications. The solicitation number is W912DW22R0036 from the Department of the Army Corps of Engineers Engineering District Seattle for replacing equipment at Libby Dam.

View the file

Other files for this federal contract opportunity

Other files attached to Libby Dam DC Boards and Breakers, Libby, MT, newest first.
File Type Posted
22R0036_0003.pdf PDF
Amendment 3 Contract Drawings R0003.pdf PDF
SUBMITTAL REGISTER R0003.pdf PDF
TABLE OF CONTENTS R0003.pdf PDF
01 22 00 R0003.pdf PDF
01 11 10.00 26 R0003.pdf PDF
01 30 00 R0003.pdf PDF
00 73 00-A R0003.docx DOCX document
Summary of changes in Amendment 3 (R0003).docx DOCX document
22R0036R2.pdf PDF
W922R0036R1.pdf PDF
Libby PLANS DC Boards and Breakers Replacement Color .pdf PDF
Reference Drawings Rev. 5.pdf PDF
W912DW22R0036.pdf PDF
FY21 Powerhouse DC Boards and Breakers Replacement.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY21 Powerhouse DC Boards and Breakers Replacement 21016 Libby Dam, MT

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 12 16.00 28

WORK SEQUENCE

03/13/18

PART 1 GENERAL

1.1 COORDINATION

1.2 SUBMITTALS

1.3 EQUIPMENT REPLACEMENT AND CUTOVER PLAN

1.4 TEMPORARY POWER

1.5 OUTAGES

1.5.1 Generating Unit Outage Requests

1.5.2 Outage to Connect/Disconnect Temp Power

PART 2 PRODUCTS

2.1 Temporary Power Cables

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 12 16.00 28 Page 1

W912DW22R0036 R0003

01 12 16.00 28

WORK SEQUENCE

03/13/18

PART 1 GENERAL

The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.

1.1 COORDINATION

The construction sequence is critical in maintaining operability of Libby Dam's main unit generators, transformers and transmission lines during this work. Equipment and systems outages shall be kept to a minimum and shall be coordinated with the Contracting Officer's Representative (COR).

Temporary outages will be required as loads are transferred from existing equipment to new equipment. Proper sequencing of the work shall be required to minimize the duration of these outages. All loads must be supported by Government approved temporary power sources furnished by the Contractor 24 hours a day, 7 days a week during the affected work.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

EQUIPMENT REPLACEMENT AND CUTOVER PLAN; G, HDC

SD-03 Product Data

Temporary Power Cables; I, HDC

1.3 EQUIPMENT REPLACEMENT AND CUTOVER PLAN

Submit at least 90 days prior to the start of equipment installation the proposed step-by-step removal and installation procedure and system cutover schedule. This schedule's format shall match the Contractor's project schedule submissions as required in section 01 32 01.00 10 "PROJECT SCHEDULE." The plan shall include a detailed sequential list of activities, duration of each activity, duration of all outages required, and temporary power plan if required. The plan shall reflect the coordination with the Government's safe clearance procedure (LOCK-OUT/TAG-OUT) for de-energizing equipment. The plan shall be coordinated with the overall project schedule required by SECTION 01 32 01.00 10 PROJECT SCHEDULE. No work will be allowed to commence until the plan is approved. Any revisions to the approved plan shall be submitted for approval.

SECTION 01 12 16.00 28 Page 2

The Contractor shall provide information regarding what temporary power equipment that will be used (MCC, panel, battery bank). The plan shall include a connecting means for existing cabling that utilizes bolt on connections via a termination enclosure.

1.4 TEMPORARY POWER

Contractor must provide Temporary Power to all 125V DC Switchboards and Panelboards; and to all 120VAC Preferred AC Switchboards and Panelboards.

Additional equipment may require temporary power. The Government will not pay additional compensation for equipment requiring temporary power not specifically listed here.

1.5 OUTAGES

1.5.1 Generating Unit Outage Requests

The Government must provide notice to Bonneville Power Administration (BPA) 45 days in advance of any time main generating units are unable to provide power. Due to this requirement, all main generating unit outage requests will require notice to the Contracting Officer 24 work days in advance. Work days are Monday thru Thursday. Notice provided after 1630 will be considered received on the next business day. This requirement does not apply to outages which will not affect the ability to produce power from generating units.

1.5.2 Outage to Connect/Disconnect Temp Power

Equipment outage to connect or disconnect temporary power to loads shall be limited to one (1) hour per outage.

PART 2 PRODUCTS

2.1 Temporary Power Cables

Temporary power cables must comply with specification 26 05 19.00 26

INSULATED WIRE AND CABLE.

PART 3 EXECUTION

Not used.

-- End of Section --