01 12 16.00 28 R0003.pdf
PDF 525 KB Posted
- Attached to
- Libby Dam DC Boards and Breakers, Libby, MT Federal contract opportunity
- Solicitation number
- W912DW22R0036
About this file
This solicitation package includes specifications for replacing direct current boards and breakers at Libby Dam in Montana. The work will require providing temporary power to switchboards and panelboards during equipment replacement. Outages for connecting temporary power are limited to one hour, and generating unit outages require 24 days' advance notice to allow the power administration time to adjust operations. The contractor must submit an equipment replacement and cutover plan at least 90 days prior to installation start detailing the removal and installation procedures and outage schedule. Temporary power cables must meet wire and cable specifications. The solicitation number is W912DW22R0036 from the Department of the Army Corps of Engineers Engineering District Seattle for replacing equipment at Libby Dam.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 22R0036_0003.pdf | ||
| Amendment 3 Contract Drawings R0003.pdf | ||
| SUBMITTAL REGISTER R0003.pdf | ||
| TABLE OF CONTENTS R0003.pdf | ||
| 01 22 00 R0003.pdf | ||
| 01 11 10.00 26 R0003.pdf | ||
| 01 30 00 R0003.pdf | ||
| 00 73 00-A R0003.docx | DOCX document | |
| Summary of changes in Amendment 3 (R0003).docx | DOCX document | |
| 22R0036R2.pdf | ||
| W922R0036R1.pdf | ||
| Libby PLANS DC Boards and Breakers Replacement Color .pdf | ||
| Reference Drawings Rev. 5.pdf | ||
| W912DW22R0036.pdf | ||
| FY21 Powerhouse DC Boards and Breakers Replacement.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY21 Powerhouse DC Boards and Breakers Replacement 21016 Libby Dam, MT
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 12 16.00 28
WORK SEQUENCE
03/13/18
PART 1 GENERAL
1.1 COORDINATION
1.2 SUBMITTALS
1.3 EQUIPMENT REPLACEMENT AND CUTOVER PLAN
1.4 TEMPORARY POWER
1.5 OUTAGES
1.5.1 Generating Unit Outage Requests
1.5.2 Outage to Connect/Disconnect Temp Power
PART 2 PRODUCTS
2.1 Temporary Power Cables
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 12 16.00 28 Page 1
W912DW22R0036 R0003
01 12 16.00 28
WORK SEQUENCE
03/13/18
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 COORDINATION
The construction sequence is critical in maintaining operability of Libby Dam's main unit generators, transformers and transmission lines during this work. Equipment and systems outages shall be kept to a minimum and shall be coordinated with the Contracting Officer's Representative (COR).
Temporary outages will be required as loads are transferred from existing equipment to new equipment. Proper sequencing of the work shall be required to minimize the duration of these outages. All loads must be supported by Government approved temporary power sources furnished by the Contractor 24 hours a day, 7 days a week during the affected work.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00, SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
EQUIPMENT REPLACEMENT AND CUTOVER PLAN; G, HDC
SD-03 Product Data
Temporary Power Cables; I, HDC
1.3 EQUIPMENT REPLACEMENT AND CUTOVER PLAN
Submit at least 90 days prior to the start of equipment installation the proposed step-by-step removal and installation procedure and system cutover schedule. This schedule's format shall match the Contractor's project schedule submissions as required in section 01 32 01.00 10 "PROJECT SCHEDULE." The plan shall include a detailed sequential list of activities, duration of each activity, duration of all outages required, and temporary power plan if required. The plan shall reflect the coordination with the Government's safe clearance procedure (LOCK-OUT/TAG-OUT) for de-energizing equipment. The plan shall be coordinated with the overall project schedule required by SECTION 01 32 01.00 10 PROJECT SCHEDULE. No work will be allowed to commence until the plan is approved. Any revisions to the approved plan shall be submitted for approval.
SECTION 01 12 16.00 28 Page 2
The Contractor shall provide information regarding what temporary power equipment that will be used (MCC, panel, battery bank). The plan shall include a connecting means for existing cabling that utilizes bolt on connections via a termination enclosure.
1.4 TEMPORARY POWER
Contractor must provide Temporary Power to all 125V DC Switchboards and Panelboards; and to all 120VAC Preferred AC Switchboards and Panelboards.
Additional equipment may require temporary power. The Government will not pay additional compensation for equipment requiring temporary power not specifically listed here.
1.5 OUTAGES
1.5.1 Generating Unit Outage Requests
The Government must provide notice to Bonneville Power Administration (BPA) 45 days in advance of any time main generating units are unable to provide power. Due to this requirement, all main generating unit outage requests will require notice to the Contracting Officer 24 work days in advance. Work days are Monday thru Thursday. Notice provided after 1630 will be considered received on the next business day. This requirement does not apply to outages which will not affect the ability to produce power from generating units.
1.5.2 Outage to Connect/Disconnect Temp Power
Equipment outage to connect or disconnect temporary power to loads shall be limited to one (1) hour per outage.
PART 2 PRODUCTS
2.1 Temporary Power Cables
Temporary power cables must comply with specification 26 05 19.00 26
INSULATED WIRE AND CABLE.
PART 3 EXECUTION
Not used.
-- End of Section --