Amendment 0002_W912DS26BA013_Specifications_Section-011100.amd0002.pdf
PDF 66 KB Posted
- Attached to
- Maintenance Dredging of New York and New Jersey Channels – Arthur Kill 35’ Reach, Federal Navigation Project
- Solicitation number
- W912DS26BA013
About this file
This is Section 01 11 00 of a federal dredging contract specification for maintenance dredging of the Arthur Kill 35' Reach in New York and New Jersey Channels, Federal Navigation Project.
The contractor must provide all materials, labor, equipment, and services to dredge approximately 155,035 cubic yards (CY) of silt and clay material and transport it to a contractor-furnished, state-permitted upland placement site. The work is divided into three basic contract line items (CLINs 0002-0004) totaling 71,665 CY and four optional CLINs (0006-0009) totaling 83,370 CY across seven dredging areas, all requiring dredging to -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The contractor must commence work within 5 calendar days of receiving the Notice to Proceed and complete the entire base work within 39 calendar days based on a minimum production rate of 2,500 CY per day; additional time is allowed at one calendar day per 2,500 CY for option quantities. The estimated total contract value ranges from $10,000,000 to $25,000,000. Key contractor responsibilities include obtaining all permits for offloading, transportation, dewatering, processing, and disposal; complying with State Water Quality Certificates and Federal Consistency Determinations; coordinating with the Federal Aviation Administration using Form 7460-1; performing scow monitoring; and performing at least 40 percent of the work with the contractor's own organization and equipment. The work is anticipated to occur between Summer/Fall and Winter 2026, and the contractor must coordinate with the U.S. Coast Guard at least 45 days prior to relocating navigation buoys.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 11 00
SUMMARY OF WORK
02/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G". Submittals not having a "G" classification are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals; G
1.2 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and
(iii) complete the entire base work ready for use, not later than 39 calendar days after the date the Contractor receives the notice to proceed.
Should any option(s) be exercised, an additional one (1) calendar day for each 2,500 cubic yards to be removed under the option(s) will be allowed, for a total of 36 additional calendar days should all options be exercised.
The time stated for completion shall include final cleanup of the premises.
(FAR 52.212-3)
b. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer or Contracting Officer Representative (COR) and subject, in every detail, to his supervision, direction, and instructions.
1.3 WORK COVERED BY THE CONTRACT DOCUMENTS
1.3.1 Project Description
The work to be performed under this project consists of providing all materials, plant, labor, equipment and services (except those furnished by the Government) to perform maintenance dredging of Arthur Kill 35' Reach, New York and New Jersey Channels, Federal Navigation Project, with placement of the material at a Contractor furnished, state-permitted, Upland Placement Site(s). The Contractor will be solely responsible for coordinating, obtaining, and be in compliance with all requirements for transportation, offloading, dewatering, processing, and disposing of the dredge material, as well as for obtaining all permits and for meeting all requirements for the processing and disposal site(s) identified by the Contractor. See Section 35 20 29 DREDGED MATERIAL TRANSPORT AND PLACEMENT MONITORING for more information.
The maintenance for this project consists of dredging a total of approximately 155,035 CY of material based on the plans and specifications survey performed in December 2025. For more details, see ESTIMATED QUANTITIES in Section 01 30 00 ADMINISTRATIVE REQUIREMENTS of these Specifications. The dredge material has been determined to be composed of primarily silt and clay.
A summary of the Dredging Areas is shown in the table below:
DREDGING AREAS TOTAL ESTIMATED
QUANTITY (CY)
BASIC WORK - Dredging Area 16R: (-35' MLLW + 1'
OD)
51,155
BASIC WORK - Dredging Area 18R: (-35' MLLW + 1'
OD)
18,010
BASIC WORK - Dredging Area 19B: (-35' MLLW + 1'
OD)
2,500
OPTION - Dredging Area 16A: (-35' MLLW + 1' OD) 41,320
OPTION - Dredging Area 20D: (-35' MLLW + 1' OD) 40,630
OPTION - Dredging Area 20S: (-35' MLLW + 1' OD) 1,165
OPTION - Dredging Area 25S: (-35' MLLW + 1' OD) 255
Contract time for completion is based on a minimum average production rate of 2,500 cubic yards (CY) per day for dredging, transportation, processing and placement at a contractor furnished, state permitted, Government approved upland placement site(s). Should the total quantity of material exceed the estimated quantities within the Solicitation Contract Form, additional time will be allowed at the rate of one (1) calendar day for each 2,500 cubic yards in excess of the established limit. The time stated for completion shall include final clean up.
The contractor must bid on all items of the bid schedule. The following CLINs require dredging of the Arthur Kill 50' Reach, New York and New Jersey Harbor, Federal Navigation Project, with subsequent transportation, processing and placement of the dredged material at a contractor furnished, state permitted, Government approved upland placement site(s):
CLIN 0002 (BASIC WORK - Dredging Area 16R- requires dredging to the plane of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth).
CLIN 0003 (BASIC WORK - Dredging Area 18R- requires dredging to the plane of -35 feet MLLW plus 1 foot allowable overdepth).
CLIN 0004 (BASIC WORK - Dredging Area 19B- requires dredging to the plane of -35 feet MLLW plus 1 foot allowable overdepth).
CLIN 0006 (OPTION - Dredging Area 16A- requires dredging to the plane of -35 feet MLLW plus 1 foot allowable overdepth).
CLIN 0007 (OPTION - Dredging Area 20D- requires dredging to the plane of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth).
CLIN 0008 (OPTION - Dredging Area 20S- requires dredging to the plane of -35 feet MLLW plus 1 foot allowable overdepth).
CLIN 0009 (OPTION - Dredging Area 25S- requires dredging to the plane of
-35 feet MLLW plus 1 foot allowable overdepth).
Based on the plans and specifications survey performed in December 2025, the maximum quantity available to be dredged is 155,035 CY from the contract areas in the Arthur Kill 35' Reach, New York and New Jersey Channels Federal Navigation Project. For a detailed breakdown of quantity available to be dredged, see paragraph 1.9 ESTIMATED QUANTITIES in Section 01 30 00 of the Specifications.
Scow monitoring is required for this project. The contractor is required to comply with Section 35 20 29 DREDGED MATERIAL TRANSPORT AND PLACEMENT MONITORING, of these specifications.
Sampling and testing was conducted by the Government in 2024. The grain size results are included in the specifications in Section 00 90 01 as Attachment K. The complete sampling and testing results will be provided as attachments to this solicitation on SAM.gov prior to bid opening. Using all test results, the Apparent Low Bidder shall coordinate with the State(s) to obtain necessary offloading, transportation, dewatering, processing, and disposal permits/requirements of the site(s) identified by the Apparent Low Bidder.
The Contractor shall be solely responsible for coordinating, obtaining, and complying with all the offloading, transportation, dewatering, processing and disposal permits/requirements of the site(s) identified by the Contractor.
For State Water Quality Certificate(s) (WQC) and Federal Consistency Determination(s) (FCD), see Section 00 90 02 WATER QUALITY CERTIFICATES.
The contractor must comply with all conditions of the WQC(s)/FCD(s).
NOTE: See WQC Permit Conditions 8.a Environmetnal Windows for Initial Dredge event/cycle and 9 Protected Species Observer for details regarding NYSDEC authorized Environmental Windows and Protected Species Observer requirements for this "initial dredge cycle".
The work is anticipated to be performed within the approximate time period of Summer/Fall to Winter 2026.
Please take note of the Section 00 90 01, Attachment L. The Apparent Low Bidder must determine applicability and notify the Administrator of the Federal Aviation Administration (FAA) of his proposed construction methods, via Form 7460-1, Attachment L in Section 00 90 01. The Apparent Low Bidder is responsible for all coordination with the FAA, and for determining if any more recent FAA requirements now exist. FAA coordination/approval shall not impact the period of performance for this contract. All required FAA approval shall be considered a pre-construction submittal and is required to be provided by the Apparent Low Bidder before or at the pre-construction meeting and prior to the start of work / issuance of the Notice to Proceed.
1.4 PERFORMANCE OF WORK BY THE CONTRACTOR
The Contractor shall perform on the site, and with its own organization and equipment, work equivalent to at least forty (40) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performance of the work, the Contractor requests a reduction and the Contracting Officer and/or his Representative determines that the reduction would be to the advantage of the Government. (FAR 52.236-01)
1.5 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS
The entire work (CLINs 0001 through 0009) is estimated to cost approximately $10,000,000.00 to $25,000,000.00.
1.6 DATUM AND BENCH MARKS
Soundings and Elevations shown in the contract drawings are in US Survey Feet and refer to Mean Lower Low Water (MLLW) [epoch 1983-2001]. The Plane of MEAN LOWER LOW WATER (MLLW) is 3.1-3.3 FEET BELOW NAVD88 AS DETERMINED USING VDATUM (VER. 4.6.1). Coordinates refer to US State Plane coordinate system NAD 1983, New Jersey Mercator - Zone 2900, US Survey Feet. The referenced survey was performed using real time kinematic GPS from station
"PAA-1, AK-2".
NSRS BENCHMARK: RTK ELIZ PARK (PID:CM4261), ELEV. 13.69'
LOCAL CONTROL BENCHMARK: AK 2, ELEV. 20.39
All control should be verified prior to utilization. The contractor may contact the New York District Survey Section at (201)333-0284 for assistance in bench mark discrepancies or clarification in benchmark and / or tide gage location.
1.7 MISPLACED MATERIAL
Should the Contractor during the progress of the work, lose, dump, throw overboard, sink, or misplace any material, plant, machinery, or appliance, which in the opinion of the Contracting Officer and/or his Representative may be dangerous to or obstruct navigation, the Contractor shall recover and remove the same with the utmost dispatch. The Contractor shall give immediate notice, with description and location of such obstructions, to the Contracting Officer and/or his Representative or inspector, and when required shall mark or buoy such obstruction until the same are removed.
Should he refuse, neglect, or delay compliance with the above requirements, such obstructions may be removed by the Contracting Officer and/or his Representative, and the cost of such removal may be deducted from any money due or to become due to the Contractor, or may be recovered under his bond. The liability of the Contractor for the removal of a vessel wrecked or sunk without fault or negligence shall be limited to that provided in Sections 15, 19, and 20 of the Rivers and Harbors Act of March 3, 1899 (33 USC. 410 et seq.) (DOD FARS SUPPL. 52.236-7006).
1.8 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the
Government, its officers, and agents free from liability arising from trespassing or damage occasioned by their operations.
1.9 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.10 RELOCATION OF BUOYS OR OTHER AIDS TO NAVIGATION
The Contractor shall notify the Coast Guard at least 45 days prior to the date desired for having buoys which interfere with dredging operations removed or relocated. Requests shall be made in writing to:
COMMANDER (OAN)
FIRST COAST GUARD DISTRICT
408 ATLANTIC AVENUE
BOSTON, MASS. 02110
or by telephoning (617) 223 8337
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --