Specs_FINAL RTA_Watervliet Arsenal Radial Forge Infrastructure_Jan2023 Vol.1 of 3.pdf

PDF 8 MB Posted

Attached to
Radial Forge Infrastructure Project
Solicitation number
W912DS24R0009
Issued by

About this file

This document provides specifications for a radial forge infrastructure project at Watervliet Arsenal in New York. The project scope includes selective demolition of existing infrastructure as well as new construction of architectural, civil, structural, mechanical, electrical, and utility systems to support installation of a new radial forge by others. Relevant details include selective demolition of cooling towers, air compressors, piping, fire alarm devices, doors, partitions and other interior finishes. New construction includes exterior wall panels and penetrations, partitions, stairs, interior finishes, utility relocation, fire water service, equipment pads, fencing, pavements, duct supports, concrete slabs, floor and roof framing, foundations, a cooling tower, baghouse, air handling equipment, piping, oil/water separator, air compressors, fire alarm devices, transformers, switchgear, motor control panels, lighting, and other infrastructure. The solicitation number is W912DS24R0009 and was issued by the US Army Corps of Engineers New York District for the project at Watervliet Arsenal.

View the file

Other files

File Type Posted
Amendment 0009.pdf PDF
Amendment 0008 (3).pdf PDF
Amendment 0007.pdf PDF
S-115_Amendment 06.pdf PDF
Amendment 0006.pdf PDF
Radial Forge Infrastructure Amendment 05 Attachment 1 RFI 35 Response.pdf PDF
Amendment 0005.pdf PDF
S-SU0312.pdf PDF
Amendment 0004_04MARCH2024 Site Visit Photos_.pdf PDF
Amendment 0004_Site Visit Sign In Sheet_04MAR2024.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003- 01 45 35.pdf PDF
Amendment 0003- S501.pdf PDF
Amendment 0003- 01 45 35.pdf PDF
Amendment 0003.pdf PDF
Amendment 2-Site Visit Photos_22FEB2024.pdf PDF
Amendment 2-Site Visit Photos_22FEB2024.pdf PDF
Amendment 0002.pdf PDF
Amendment 2-Site Visit Photos_22FEB2024.pdf PDF
Amendment 2 - Site Visit Sign In Sheet_22FEB2024.pdf PDF
Amendment 0001.pdf PDF
WVA Radial Forge Infrastructure_BAA Waiver DF (Non-Availability)_REV1 (2).pdf PDF
JA - WVA B135 Radial Forge Infrastructure (Simplex) - 12 Jan 2024 final signed.pdf PDF
2024.01.16_Final RTA_WVA Forge Infrastructure.pdf PDF
Specs_FINAL RTA_Watervliet Arsenal Radial Forge Infrastructure_Jan2023 Vol.3 of 3.pdf PDF
Specs_FINAL RTA_Watervliet Arsenal Radial Forge Infrastructure_Jan2023 Vol.2 of 3.pdf PDF
W912DS24R0009.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RADIAL FORGE

INFRASTRUCTURE

WATERVLIET ARSENAL, NY

Contract No. W912DS21D0001

Task Order No. W912DS23F0011

SPECIFICATIONS – VOLUME 1 OF 3

FINAL READY TO ADVERTISE

15 JANUARY 2024

This page intentionally left blank.

Radial Forge Infrastructure Final Ready to Advertise Watervliet Arsenal, New York

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 05/22 COVER SHEET

00 00 07 01/24 SEALS PAGE

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/11, CHG 14: 02/22 WORK RESTRICTIONS

01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/18, CHG 1: 11/21 FACILITY DATA REQUIREMENTS

01 91 00.15 18 05/19, CHG 3: 05/22 TOTAL SYSTEM COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION AND DECONSTRUCTION

02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION

02 83 00 11/18 LEAD REMEDIATION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE

03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR

BELOW GRADE CONSTRUCTION

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 51 00 08/23 METAL STAIRS

05 52 00 08/23 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

PROJECT TABLE OF CONTENTS Page 1

VOLUME 1

VOLUME 2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS

07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

DIVISION 09 - FINISHES

09 51 00 08/20 ACOUSTICAL CEILINGS

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 69 13 11/15, CHG 1: 08/18 RIGID GRID ACCESS FLOORING

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 44 16 11/19 FIRE EXTINGUISHERS

DIVISION 12 - FURNISHINGS

12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS

12 93 00 08/17, CHG 1: 08/18 SITE FURNISHINGS

DIVISION 21 - FIRE SUPPRESSION

21 13 18 08/20 PREACTION SPRINKLER SYSTEMS, FIRE

PROTECTION

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND

SEISMIC CONTROL

22 14 29.00 40 05/17 SUMP PUMPS

22 15 14.00 40 11/17 GENERAL SERVICE COMPRESSED-AIR

SYSTEMS, LOW PRESSURE

22 15 19.19 20 05/11 NONLUBRICATED ROTARY SCREW AIR

COMPRESSORS (100 HP AND LARGER)

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 15 05/22 COMMON PIPING FOR HVAC

23 05 48.00 40 05/22 VIBRATION AND SEISMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT

23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 08 01.00 20 04/06 TESTING INDUSTRIAL VENTILATION SYSTEMS

PROJECT TABLE OF CONTENTS Page 2

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 21 23 08/17 HYDRONIC PUMPS

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 35 19.00 20 02/10, CHG 2: 08/18 INDUSTRIAL VENTILATION AND EXHAUST

23 51 43.00 20 02/10 DUST AND GAS COLLECTOR, DRY SCRUBBER

AND FABRIC FILTER TYPE

23 58 00.00 10 05/20 CENTRAL STEAM HEATING AND UTILITIES

SYSTEMS

23 65 00 11/16, CHG 2: 08/18 COOLING TOWERS AND REMOTE

EVAPORATIVELY-COOLED CONDENSERS

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS

DIVISION 26 - ELECTRICAL

26 05 13.00 40 05/20 MEDIUM-VOLTAGE CABLES

26 05 43 11/23 UNDERGROUND DUCTS AND RACEWAYS FOR

ELECTRICAL SYSTEMS

26 05 71.00 40 02/17 LOW VOLTAGE OVERCURRENT PROTECTIVE

DEVICES

26 05 73 08/23 POWER SYSTEM STUDIES

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 11 16 11/21 SECONDARY UNIT SUBSTATIONS

26 12 16 10/23 DRY-TYPE, MEDIUM-VOLTAGE, 3-WINDING,

DRIVE ISOLATION TRANSFORMER

26 13 13 11/21 METAL-CLAD SWITCHGEAR

26 13 14 11/21 SWITCHGEAR HOUSE

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 22 02 PASSIVE HARMONIC FILTERS FOR 6-PULSE

VFDS

26 23 00 05/15, CHG 2: 11/19 LOW-VOLTAGE SWITCHGEAR

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 53 00.00 40 11/15 EXIT SIGNS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 08/08, CHG 2: 02/21 EARTHWORK (EXTERIOR)

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 31 13 11/21 CHAIN LINK FENCES AND GATES

PROJECT TABLE OF CONTENTS Page 3

VOLUME 3

DIVISION 33 - UTILITIES

33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING

33 30 00 05/18 SANITARY SEWERAGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION 00 00 01

COVER SHEET

05/22

PART 1 GENERAL

NEW YORK DISTRICT

CORPS OF ENGINEERS

NEW YORK, NEW YORK 10278-0090

INVITATION FOR BIDS

FOR

1. Attached is INVITATION FOR BIDS (IFB) NO. W912DS-23-F-0011

2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS TO BIDDERS (Section 00 21 13).

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation.

(See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 72 00 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

6. GENERAL CONDITIONS - SECTION 00 72 00, note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause.

7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

8. Sections indicated in the cover sheet are part of the Solicitation package.

DOCUMENT 00 00 01 Page 1

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

SECTION 00 01 07 page 1

DOCUMENT 00 01 07

SEALS PAGE

1.1 DESIGN PROFESSIONALS OF RECORD

A. Structural Engineer:

Scott L. Chambers License Number: 056892E Commonwealth of Pennsylvania Responsible for Divisions 3 and 5.

B. Architect:

Gregory D. Ninow License Number: 044959 State of New York Responsible for Divisions 4, 6, 7, 8, 9, 10 and 12.

C. Fire Protection Engineer:

Anson Nowka License Number: E-13550 State of Nebraska

Responsible for Divisions 21 and 28.

D. Mechanical Engineer:

Michael J. Whalen License Number: 087246 State of New York Responsible for Divisions 22 and 23.

E. Electrical Engineer:

Joseph M. Hole License Number: PE075343 Commonwealth of Pennsylvania Responsible for Division 26.

F. Civil Engineer:

Kyle Moser License Number: PE081181 Commonwealth of Pennsylvania Responsible for Divisions 31, 32 and 33.

-- End of Section --

1-15-2024

1/15/2024

1/15/2024

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 00 07 Page 2

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use, not later than 792 calendar days after the date the Contractor receives the notice to proceed. This action will not operate to extend the performance time for the balance of the work. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3)

b. The Contractor shall furnish all labor, materials, equipment, and services for the following work: shown in the plans and specifications.

c. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 SUBMITTALS

Government approval is required for submittals classification. Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G, RO

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes balance of plant scope to include selective demolition, architectural, civil, structural, mechanical, plumbing, fire alarm,electrical and incidental related work to support a new radial forge being designed, provided and installed by others. The selective demolition work includes but is not limited to demolishing the existing cooling tower, air compressors, select piping, fire alarm devices, interior doors, partitions, interior finishes, concrete slabs and lighting fixtures. The architectural work includes but is not limited to exterior wall penetrations and infills, new exterior wall panels, partitions, doors, stairs and interior finishes. The civil work includes but is not limited to exterior utility relocation, new fire water service, equipment pads, bollards, fencing and pavements. The structural work includes but is not limited to duct supports, concrete slabs and trenches, floor and roof framing, foundations and equipment pads. The mechanical work includes but is not limited to a new exterior cooling tower, exterior baghouse with exterior and interior ductwork, exterior air handling equipment and

SECTION 01 11 00 Page 1 ductwork. The plumbing work includes but is not limited to a new oil/water separator, duplex sump pump, exterior air compressor equipment and associated piping. The fire alarm scope includes but is not limited to new fire alarm devices and associated appurtenances. The fire protection scope includes but is not limited to fire water piping, backflow preventer, pre-action equipment and sprinkler system. The electrical work includes but is not limited to new transformers, switchgear, motor control panels, lighting and associated conduit/wiring/cabling. The work also includes hazardous materials abatement as related to the above scope.

1.3.2 Location

The work is located at the Watervliet Arsenal, New York approximately as indicated. The exact location will be shown by the Contracting Officer.

1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $10,000,000 and $25,000,000.

1.5 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.6 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

c. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmenship to the existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone). Contractor shall provide immediate notification of the Contracting Officer and verbal procedures to restore. The Contractor must immediately assemble personnel, equipment and material necessary to restore. Compliance with Contract Documents for quality installation must be included. The work must proceed at 24-hours per day until satisfactorily restored service is achieved. Fixing loose ends requires Contracting Officer approval to perform during normal working hours.

The request to perform repairs during normal working hours requires Contractor's written approval. The write up of procedures to repair must be submitted ASAP.

SECTION 01 11 00 Page 2

d. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.7 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

No excavation whether minor or major including trenching, sidewalk replacement, etc. will be permitted without an approved digging permit.

Contractor shall apply for renewal of work permits as required if the work continues beyond the original permit expiration date. Verify existing utility locations indicated on contract drawings, within area of work.Dig safes are to be submitted to the Contracting Officer's Representative a minimum of 30 days prior to commencement of that item of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.7.1 Notification Prior to Excavation

Notify the Contracting Officer at least 30 days prior to starting excavation work.

1.8 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.9 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area at no additional cost to the U.S. Government.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until

SECTION 01 11 00 Page 3 disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

11/11, CHG 14: 02/22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13 (2022; ERTA 3 2022) Standard for the Installation of Sprinkler Systems

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittalsclassification. Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

Digging Permit; G, RO

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

SECTION 01 14 00 Page 1

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.3.2 Working Hours

Working Hours Regular working hours will consist of an 8 hour period, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays. Night and weekend work may be necessary as required by the Contracting Officer's Representative so as to not impact ongoing operations of the facility. When requested, the contractor will amend their working hours as needed to accommodate ongoing Watervliet Arsenal operations. The contractor may submit a request for equitable adjustment for costs solely due to the change in working hours directed by the U.S. Government.

Scheduling of major demolition activities that are particularly noisy or involve excessive vibration must be coordinated with the Contracting Officer and may be outside regular working hours. Excessive noise is defined as exceeding 85-dBA when the equipment is in use or activity is ongoing (measure by a sound level meter set for A scale, slow response).

The vicinity of measure is defined as a distance not to exceed 1 meter from the equipment or activity. Techniques such as sound level averaging or exposure time weighting shall not be used to meet this requirement.

Excessive vibration shall adhere to the requirements within EM 385-1-1, chapter 29, for maximum total energy loads (ER) and maximum total peak particle velocities (PV), whichever is more stringent.

1.3.3 Working Conditions

Comply with paragraph Fatigue Management Plan (FMP) of EM 385-1-1.

a. Open trenches or road restrictions will not be permitted without the approval of the Contracting Officer.

b. Access ways must be fully usable.

c. All cost for conformance with the above stated requirements must be included with the lump sum contract amount and no claim for extra cost must be considered.

1.3.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise. The Contractor must comply with paragraph Fatigue Management Plan (FMP) of EM 385-1-1.

SECTION 01 14 00 Page 2

1.3.5 Occupied Building

The Contractor shall be working in an existing building which are occupied.

Do not enter the buildings without prior approval of the Contracting Officer.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the finished areas during the construction period.

Relocate movable furniture as required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.

The Government will not remove and relocate other Government property in the areas of the buildings scheduled to receive work.

1.3.6 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 8 hours. This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.4 DIGGING PERMIT

The Contractor must be responsible for obtaining a digging permit prior to commencing excavations. No excavation whether minor or major including trenching, side-walk replacement, etc. will be permitted without an approved digging permit. Contractor must carefully avoid contact or damage with known or identified underground utilities. Work on or near roadways must be flagged in accordance with EM 385-1-1, which forms a part of these specifications. Work located along the alert force route cannot cause blockage, and the Contractor must maintain un-obstructed access for alert force traffic at all times.

Contractor is required to locate and verify all underground utilities and thereafter maintain those locations on the ground and/or on the contract

SECTION 01 14 00 Page 3 drawings for use through out the project by all interested.

Dig safe permit must be submitted to the contracting officer's representative a minimum of 30 days prior to the commencement of any work requiring.

1.5 CONTRACTOR'S PROJECT WORK ATTENDANCE

The Contractor is responsible to inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, the Contractor is required to notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.

1.6 SUBCONTRACTORS

It is the responsibility of the Contractor to inform all their subcontractors of all the instructions contained in this information sheet. Subcontractors are responsible to report project work attendance through the Prime Contractor to the COR whenever they are on post.

1.7 ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON) AT WATERVLIET

ARSENAL

Impact on Contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.

1.8 RANDOM ANTITERRORISM MEASURES PROGRAM (RAMP) AT THE WATERVLIET ARSENAL

In accordance with AR 525-13, Contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g., vehicles, wearing of ID badges, etc.) and installation security program.

1.8.1 Badges

All personnel will report to the Visitors Center daily to be issued a pass. They must return the pass when they leave for the day by dropping it off in the drop box by the Visitors Center attached to the barrier to the left prior to entering the exit lane of the south gate. All personnel must show a driver's license or state identification card (picture ID) to the security guard in order to get the pass. If the personnel will be working on the arsenal for over 90 days, they may be authorized a WVA picture badge, which will allow them access during normal work hours without getting a daily pass.

1.8.2 Picture Badges

The Contractor may request through the Contracting Officer a picture badge if the term of the contract warrants. Requests must be made in writing on company letterhead to the Contracting Officer listing the following:

a. Contract Number.

b. Indicate that the individual(s) work for said company.

c. Project name and location of work site (i.e., Bldg. #).

SECTION 01 14 00 Page 4

d. Duration of performance (start and stop dates).

e. All personnel being issued a picture badge shall present a passport or original birth certificate (with a raised seal) and driver's license.

(A social security card is not an acceptable form of identification).

f. During performance of the contract, the Contractor is responsible for prompt return of badges for any employee who no longer requires access to the work site.

g. Upon completion or termination of the contract or expiration of badge(s), the Contractor shall ensure that they are returned to the issuing office.

h. Final payment on the contract will be held until all badges are properly returned.

i. Possession of a picture badge does not relieve the badge holder from the responsibility to notify the COR of project work attendance.

1.9 ACCESS POLICY

a. All Contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a U.S. Government organization or a Contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.

b. At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, may be denied access to the Watervliet Arsenal. Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or Mission Essential Vulnerable Area (MEVA).

1.10 NON-CITIZENS

Non-citizens of the U.S. may not be approved for access.

1.11 CAMERAS

a. The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer. Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

b. For any photos that have been approved by the Security Office and Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet

SECTION 01 14 00 Page 5

Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.

c. All photos must be reviewed by the security office before the photo capture system (i.e., camera, cell phone, etc.) has left the arsenal.

1.12 TRAFFIC CONTROL

Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic Laws. Any moving or nonmoving violation may result in a traffic citation being issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function. Vehicles cannot be left unattended in other than valid parking spaces. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended. Both the Fire Department and Security Department must be notified prior to blocking of streets. The Contractor must coordinate through the COR for approval to block or close streets.

1.13 DELIVERIES

Deliveries to Contractors shall enter the post through the South Gate.

Contractors expecting deliveries should notify the South Gate (266-5821) prior to the arrival of the delivery. The Contractor's representative must accept deliveries. Materials, which are delivered to the site, are the responsibility of the Contractor. Storage and special conditions must be coordinated with the COR for approval to block or close streets.

1.14 CONTRABAND

Alcohol, illegal drugs, and any firearms are prohibited. Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

1.15 RESTRICTION OF WVA PROVIDED DOCUMENTS

Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command - Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189. Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.

1.16 SECURITY OF EQUIPMENT

Contractors are responsible for securing all of their equipment. WVA is not responsible for stolen or lost items.

1.17 VEHICLES IN BUILDINGS

Contractors' vehicles and equipment using fuel shall receive clearance from

SECTION 01 14 00 Page 6 the Fire Chief before entering the building. Refueling of vehicles in a building requires Fire Department standby.

1.18 STORAGE SHED/TRAILERS/TEMPORARY OFFICES

The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public Works Division, the Watervliet Arsenal Fire department, and the Watervliet Arsenal Security Department. The Contractor shall submit their placement request in writing 10 business days in advance to the project COR or technical POC for request evaluation and approval.

(Note: Request approval is not guaranteed.) All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by NFPA 13. The Fire Inspection Staff will assist Contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.

1.19 EQUIPMENT, DUMPSTER, STORAGE CONTAINER/SHED, TRAILER, and OFFICE

IDENTIFICATION

Contractor shall prominently display the following information on all Contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices:

a. Contractor Company Name.

b. Project Number/Contract Number or Equivalent (information will be provided to Contractor by the Watervliet Arsenal, the Arsenal Partnership (AP), or the AP's Construction Manager).

c. Contractor Project Point of Contact (POC) with phone number or Arsenal/AP Project POC with phone number (information will be provided to Contractor by the Watervliet Arsenal, the AP, or the AP's Construction Manager).

1.20 GASOLINE CONTAINERS AND FLAMMABLES

Gasoline will be stored in safety containers equipped with self closing lids and other features as certified by the Underwriters' Laboratories.

Flammable liquids will be kept in National Fire Protection Association or UL approved containers; Fire Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (i.e., flammable).

1.21 FIRE HYDRANTS

Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension 5990). If permission is granted to use hydrants, the Contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the Contractor. It is the responsibility of the Contractor to ensure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.

1.22 DISCHARGES

Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the

SECTION 01 14 00 Page 7

Industrial Waste Treatment Plant (IWTP). Except when WVA has established with the Contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.

1.23 DOCUMENTATION OF DISPOSITION OF MATERIALS AND ITEMS REMOVED FROM

WATERVLIET ARSENAL

The Contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled). All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The Contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.

1.24 WASTE DISPOSAL

All hazardous waste shall be disposed of by the Contractor. The Contractor is responsible for management and disposal of all hazardous waste in accordance with applicable regulations, WVA's Hazardous Waste Management Plan, Section 01 57 19 - 3.4.3.1 and the Contractor's Approved Environmental Protection Plan. Hazardous waste shall be moved to Building 145 for 90 day storage in accordance with the RCRA "three day" rule. Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the Contractor via appropriate sampling and analysis to not be hazardous waste (such demonstration shall be to the satisfaction of WVA). The Contractor is responsible for disposal of other wastes, unless noted otherwise. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc., is prohibited. The Contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities. The Contractor shall furnish copies of documents for each waste shipment, such as Bills of Lading, etc., (Including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA) through the COR to Facilities Engineering. Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards (POPS)) for containerizing waste. Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster.

Covers shall be secured in place whenever the Contractor leaves the job site, and whenever precipitation is possible or occurring. Scrap metals that are recycled at an approved scrap metal facility do not required testing and waste characterization. Proper cleaning (triple rinse) is still required.

1.25 INDUSTRIAL WASTE TREATMENT PLANT (IWTP)

Due to OSHA Process Safety Management rule requirements, the Contractor shall coordinate with the IWTP Leader regarding IWTP-specific requirements when work is to be performed in and/or around the IWTP.

SECTION 01 14 00 Page 8

Requirements will include:

a. Hazard awareness of chemicals used at the facility to include sulfur dioxide (so2), chromic acid, and sulfuric acid.

b. Hazmin system-access by IWTP leader for all chemicals/sds upon request.

c. Proper PPE to be used when working with chemicals. This shall include protective suites (Tyvek), hardhats, chemical resistant gloves, respiratory protection, and hearing protection.

d. Building evacuation procedures when so2 alarm activates.

e. Must sign in/out of IWTP roster as acknowledgment this procedure.

1.26 UTILITY CLEARANCE PERMIT (UCP)

All contracted work is subject to the WVA Regulation on utility clearance permits, WVAR 420-02. The Contractor will assist the COR in preparing the UCP. The Contractor shall review the project site, project documents and utility record plans to determine the presence of concealed utilities within the area(s) of the project work. The Contractor is required to sign the UCP and concur / non-concur with the project UCP.

1.27 MARKING UNDER GROUND UTILITIES

All contract work, which involves the installation or unearthing of underground utilities, shall include the marking of these utilities as part of the required project work. The tape shall be detectable by a metal detector when buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities.

The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified below and shall bear a continuous printed inscription describing the specific utility.

RED: ELECTRIC

BLUE: WATER SYSTEM

GREEN: SEWER SYSTEM

YELLOW: GAS LINE OR PIPELINE (FOR NATURAL GAS, OIL,

STEAM/CONDENSATE OR OTHER DANGEROUS MATERIALS)

ORANGE: FIBER OPTIC (TELEPHONE, TELEVISION, SECURITY OR FIRE ALARM)

1.28 SULFUR DIOXIDE (SO2) AWARENESS

Due to the presence of highly hazardous chemicals located in the Industrial Waste Treatment Plant, always follow the instructions of WVA officials quickly and completely in the event of any emergency. This is especially important when working in or near the Industrial Waste Treatment Plant

(IWTP).

Because of the requirements of OSHA's Process Safety Management (PSM) standard (For specific requirements see Title 29 of the Code of Federal Regulations, Part 1910.119 on the OSHA website) safe work practices have been developed that provide for the control of hazards during operations such as lockout/tag out; confined space entry; line breaking of process associated piping; control over IWTP facility entry. These safe work practices apply to all employees and Contractors equally. Contractors must follow all safe work practices while working on the installation and

SECTION 01 14 00 Page 9 provide training to employees on PSM before working within the IWTP.

For Contractors performing maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process, contact the Contracting Officer's Representative (COR) for more instructions on special provisions of the PSM standard that applies to this work.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 10

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 3: 02/23

PART 1 GENERAL

1.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.2 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2.1 Contract Line Item 0001

1.2.1.1 Payment

Payment will be made for costs associated with operations necessary for construction all work (includes all plant, labor, and material) for Radial Forge Infrastructure as described in the plans and specifications except for work included in the remaining Contract Line Items..

1.2.1.2 Unit of Measure

Unit of measure: job.

1.2.2 Contract Line Item 0002

1.2.2.1 Payment

Payment will be made for costs associated with operations necessary for all work (includes all plant, labor, and material) for demolition of existing infrastructure as described in the plans and specifications..

1.2.2.2 Unit of Measure

Unit of measure: job.

SECTION 01 20 00 Page 1

1.2.3 Contract Line Item 0003

1.2.3.1 Payment

PaymentPayment will be made for costs associated with operations necessary for the Final Record Drawing Submission and O&M Manuals.

1.2.3.2 Unit of Measure

Unit o measure: job.

1.2.4 Contract Line Item 0004

1.2.4.1 Payment

Payment will be made for costs associated with operations necessary for all work (includes all plant, labor and material) for the construction of the electrical substations 3B1-B1 and 3B1-B2 exclusive of wiring.

1.2.4.2 Unit of Measure

Unit of measure: job.

1.2.5 Contract Line Item 0005

1.2.5.1 Payment

Payment will be made for costs associated with operations necessary for all work (includes all plant, labor and material) for the construction of the exterior dust collector inclusive of the exhaust fan and stack but exclusive of the ductwork beyond the inlets.

1.2.5.2 Unit of Measure

Unit of measure: job.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 2

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 2: 05/22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals. Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

Work to be Performed by the Contractor; G, RO

Eng Form 93; G, RO

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for

SECTION 01 30 00 Page 1 unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by New York State law and 52.228-5 - Insurance - Work on a Government Installation.

a. Before commencing work under this contract, the Contractor must notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance must contain an endorsement to the effect that cancellation or material change adversely affecting the Government's interest cannot be effective for such a period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than 30 days after written notice thereof to the Contracting Officer.

b. The Contractor must insert the substance of this clause, including this paragraph (b), in subcontracts under this contract that require work on a Government installation and must require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor must maintain a copy of all subcontractors' proofs of required insurance, and must make copies available to the Contracting Officer upon request.

c. This insurance will be included at no additional cost to the government.

1.6 SUBMITTAL OF WORK TO BE PERFORMED BY THE CONTRACTOR

Provide the Contracting Officer, within five days after award, items of work to be performed by…