Green Brook, Segment C-1
AMENDMENT # 1
SECTION 03 25 30
BRIDGE CONSTRUCTION USING MOVEMENT SYSTEMS
PART 1 GENERAL
1.1 DEFINITIONS
A. Bridge Move: Bridge move refers to all components including, but not limited to Self Propelled Modular Transporters (SPMT), cranes, jacks, pumps, excavators and processes including but not limited to, submittal preparation, execution of the bridge movement, pre-move and post-event inspections, and remedial action related to moving the newly constructed bridge from the temporary staging area onto the permanent area within the railroad embankment.
B. Move Device: The main piece of equipment performing the moving of the bridge such as but not limited to SPMT, cranes, or other heavy load moving equipment.
C. Rail Road Shutdown: Rail road shut down refers to the time period during which the bridge move must be executed. During this time period the railroad tracks will be taken out of service. The rail road shut down will occur as described in Section 01 14 00 WORK RESTRICTIONS.
D. NJ Transit Operations: NJ Transit operations refer to the work to be performed by NJ Transit or its subcontractor at the start and at the end of the railroad shutdown. The contractor will not be allowed to perform construction activities that may interfere with the execution of NJ Transit operations. The work at the start of the shutdown includes but it is not limited to cutting the rails, removing the ties, and removing the ballast. The work at the end of the shutdown includes but is not limited to placing the ballast, placing the ties, placing and splicing the rails.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule; G, RO
Submit a detailed hour by hour schedule addressing the timing and sequence of the bridge move including but not limited to excavation of the railroad embankment, subgrade preparation, transportation of the bridge, and backfilling. The schedule shall also show the time allotted for NJ Transit Operations in accordance with section 1.2(C).
Work Plan; G, RO
Obtain approval from New Jersey Transit prior to ordering materials or
SECTION 03 25 30 Page 1 commencing related work.
PRE-OPERATIONS CHECKLIST; G, RO
Submit a checklist showing the bridge move step by step activities in sequential form for tracking the progress of the operations.
SD-02 Shop Drawings
BRIDGE MOVEMENT SYSTEMS; G, RO
Submit working drawings and calculations for Engineer approval prior to ordering materials or commencing related workSubmit working drawings and calculations signed by a NJ Professional Engineer for COR approval prior to ordering materials or commencing related work. Show complete details and substantiating calculations of the method, materials, and equipment to be used for the bridge move. The design shall be in accordance with the AASHTO Guide Design Specifications for Bridge Temporary Works. The move device shall be capable of supporting a minimum load of 1,700 kips (850 ton) of segment 1 bridge plus the weight of any additional shoring, rigging, or auxiliary device as required by the bridge movement system for moving the bridge into the final location. Provide complete details of the Bridge staging area as required in section 1.3.
The EngineerCOR reserves the right to review these drawings for up to 15 working days without granting an increase in the number of working days for the project. This right applies each time drawings are submitted.
SD-03 Product Data
EQUIPMENT CATALOGS; G, RO
Submit equipment catalogs showing the technical specifications, dimensions, self-weight, and loading capacity of the move device to be used for the bridge move.
1.3 QA/QC procedures
1. Provide a plan showing the BSA layout of the construction zones upstream and downstream. The plan shall show at a minimum access roads, staging area locations, permanent bridge location, equipment travel paths, stockpiles, and location of construction equipment.
2. The Contractor shall verify that the Bridge Staging Area is suitable for all proposed construction operations and shall develop/design methods to stabilize all excavations and to support temporary works and move devices. Provide calculations and details for temporary foundation plans. Provide calculations demonstrating the temporary foundations' anticipated settlements.
3. Contingency plans shall be included in the work plan referenced on section 3.1.2 for the specific bridge moving system proposed by the contractor.
4. Personnel qualifications. The contractor or its sub-contractor responsible for the bridge moving operations shall have a minimum of 5 years of experience performing similar bridge movement work and shall demonstrate a minimum of 5 successfully completed similar projects. The contractor shall designate a bridge movement project manager (BMPM)
SECTION 03 25 30 Page 2 which will be responsible for the overall coordination of all aspects and phases of the bridge move including but not limited to planning, coordination with agencies, authorities and any other third parties, submittal preparation, resource and equipment availability, etc.. . The BMPM shall be on-site directing the operations during the bridge movement execution as part of his/her responsibilities. The BMPM shall have a minimum demonstrated experience of 10 year performing similar work and a minimum of 5 successfully completed similar projects. The contractor shall also designate a bridge movement project engineer (BMPE) responsible for all aspects of the operation of the bridge move device including but not limited to site preparation, pre-move submittals, pre-move equipment testing, bridge move, and post-move operations. The BMPE shall be on-site during the execution of the bridge move. The BMPE shall be an expert in the use of the selected move device and shall have a minimum of 5 years performing similar work with similar move devices and a minimum of 5 successfully completed similar projects.
PART 2 PRODUCTS
2.1 CONSTRUCTION USING MOVEMENT SYSTEMS
1. Provide all materials for the permanent features of the project in conformance with the contract specifications.
2. Provide all temporary features of the project suitable to sustain applied forces.
3. Provide satisfactory replacement material at no additional expense to the Army Corps of Engineers.
4. Contact the EngineerCOR for qualified product information.
PART 3 EXECUTION
The intent during movement is to ensure that the structure is delivered to the Owner, in its final location, with no damage, adverse loss of strength, loss of performance or loss of long-term durability. Any damages to the permanent structure caused by the move shall be repaired at no additional cost to the Owner.
All work shall be performed in accordance with the 2012 "Guidelines for Working within or in Vicinity of NJ Transit' Right-of-Way."
3.1 PREPARATION FOR TRANSPORT OF SUPERSTRUCTURE
3.1.1 New Jersey Transit Coordination
3.1.1.1 Schedule
The Contractor shall contact NJ Transit at the beginning of the contract and before submittals to coordinate all aspects of the bridge move. The initial contact shall be NJ TRANSIT, Raymond Maleski, Principal Project Engineer, (973)-491-8301.
Coordinate relocation of utilities within the railroad embankment in accordance with the project drawings and specifications.
SECTION 03 25 30 Page 3
3.1.2 Work Plan
The Contractor shall submit work plan for approval by New Jersey Transit and the contracting officers representative for approval. The work plan shall be in accordance with the submitted hour by hour schedule and shall indicate all equipment, operations and contingency plans. The work plan shall indicate the proposed equipment and resource redundant capabilities to ensure that the bridge construction is performed on schedule as it is critical that the contractor is prepared for unanticipated problems and/or equipment failures.
The work plan shall include the resumes of the contractor or sub-contractor firm performing the bridge move as well as the resumes of the bridge move project manager and the bridge move project engineer. The minimum qualification requirements are listed in section 1.3.4
3.1.3 Pre-Move Operations
Complete the pre-operations checklist as activities as performed.
Conduct a pre-move crack survey of the structure within seven days prior to the bridge move. Marking cracks visible from a standing position. Measure marked cracks and identify cracks greater than 0.02 inches wide.
Establish survey control points and benchmarks as necessary. Establish transverse and longitudinal reference lines for setting the structure on the final position as necessary. Final plan alignment and location shall be within 2 inches of the location shown on the contract plans.
Check final subgrade elevations along the proposed footing lines. Final elevations shall be within 1 inch of the elevations shown on the plans.
Final grade shall be level.
Perform excavation in accordance with Section 31 23 00.00 20 Excavation, Fill, and Backfill for Structures.
3.2 LIFT, TRANSPORT, AND PLACEMENT OF SUPERSTRUCTURE
General:
A. Follow procedures shown on the Working Drawing for the step-by-step sequence of operations for movement of the superstructure span.
B. Lift and transport structure in accordance with the lifting points established in the drawings.
C. Deliver the structure to its final location with no damage or loss of strength, performance, or long-term durability.
Monitoring:
A. Monitor the structure for stability and integrity of the move system during lifting, transport, and placement following the plans for the equipment's and methods of monitoring.
3.2.1 BRIDGE MOVEMENT SYSTEMS
The bridge movement system shall be designed to lift the bridge at the pick points indicated on the contract drawings. Calculations shall be included to show that the stresses and deflections imposed on the bridge during the bridge move will not exceed those shown on the contract drawings.
SECTION 03 25 30 Page 4
The Contractor shall design all elements of the bridge move system. Design shall be done in conformance with the current edition of the AREMA Eng Man (AREMA Manual for Railway Engineering), AASHTO GDSBTW (AASHTO Guide Design Specifications for Bridge Temporary Works) and AASHTO LRFDCONS Bridge Construction Specifications.
Alternatively, the design shall be in conformance with the current edition of the AASHTO SSHB Division II (AASHTO Standard Specifications for Highway Bridges, Division II).
The shop drawings and calculations shall include any systems proposed to transfer the loads to the move device and to move the structure, such as shoes, jacks, shoring, rigging, or other load carrying or guiding elements.
The bridge move designer shall verify that the equipment has adequate stroke, reach, etc. to negotiate the travel path. The calculations shall reference the submitted equipment catalogs where applicable.
For SPMT and similar transporter devices calculate the anticipated lateral forces due to for example braking, turning, and vertical grades and provide a system to transfer loads to SPMTs.
The calculations shall include a check to demonstrate that the ground stresses from the bridge move system shall be equal to or less than those indicated on the project plans. The shop drawings shall indicate all ground improvements and soft soil mitigation within the Bridge Staging Area where the move device will be operating. The drawings shall also show clearances from above ground obstacles and provide mitigation if required.
3.3 POST-MOVE OPERATIONS
Conduct a post move visual crack survey of the structure immediately after placing the structure in its final location. Compare observed cracks with the pre-move crack pattern. Notify the engineerCOR of any cracks caused by the bridge moves greater than 0.020 inches wide.
Perform backfill in accordance with Section 31 23 00.00 20 Excavation, Fill, and Backfill for Structures.
Complete the bridge move within the specified railroad shutdown time frame including the NJ Transit operations.
The Contractor is advised that severe impacts are experienced by the traveling public occasioned by having the railroad tracks closed beyond the specified railroad shutdown. In the event that the Contractor fails to complete the work within the specified time frame causing delays in the operation of the tracks, the Army Corps of Engineers will have the right to collect a Track Occupancy Charge for the occupancy of the tracks beyond the allowable shutdown hours until such time that the tracks are reopened to railroad traffic. Therefore, the contractor will be assessed a Track Occupancy Charge for a delay in the reopening of the tracks, premised upon track user costs and costs incurred by the NJ Transit for engineering, inspection, and administration (including overhead). The Track Occupancy Charges shall be collected by deducting the appropriate Charges, from the Contractor's partial payments.
The Track Occupancy Charges in this Contract are shown in the table below, and they will be assessed after the expiration of the permissible railroad shutdown period, until such time as the lane is fully available for use by
SECTION 03 25 30 Page 5
NJ Transit.
Reopening Of Lane Is Late By:
Track Occupancy Charge Assessed:
1 to 15 minutes $[XXX]
16 to 30 minutes $[XXX]
31 to 45 minutes $[XXXX]
46 to 60 minutes $[XXXX]
61 to 75 minutes $[XXXX]
76 to 90 minutes $[XXXX]
91 to 105 minutes
$[XXXX]
106 to 120 minutes
$[XXXX]
Notes:
Every 15 minutes late after 2 hours is an additional charge of $[XXXX] to a maximum total daily charge of $[XXXXX].
Note that the charges above shall not be added together. The Lane Occupancy Charge to be assessed is the single value in the right-hand column corresponding to the lateness of work zone pick up found in the left-hand column.
-- End of Section --
This page intentionally left blank.
SECTION 03 25 30 Page 6
| 03 25 30 - BRIDGE CONSTRUCTION USING MOVEMENT SYSTEMS |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.2 SUBMITTALS |
| 1.3 QA/QC procedures |
| PART 2 PRODUCTS |
| 2.1 CONSTRUCTION USING MOVEMENT SYSTEMS |
| PART 3 EXECUTION |
| 3.1 PREPARATION FOR TRANSPORT OF SUPERSTRUCTURE |
| 3.1.1 New Jersey Transit Coordination |
| 3.1.1.1 Schedule |
| 3.1.2 Work Plan |
| 3.1.3 Pre-Move Operations |
| 3.2 LIFT, TRANSPORT, AND PLACEMENT OF SUPERSTRUCTURE |
| 3.2.1 BRIDGE MOVEMENT SYSTEMS |
3.3 POST-MOVE OPERATIONS