Green Brook Segment C2 Federal contract opportunity
Solicitation number
W912DS-18-B-0027
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

Amendment 0006

View the file

Other files for this federal contract opportunity

Other files attached to Green Brook Segment C2, newest first.
File Type Posted
Bid_Abstract.xlsx XLSX spreadsheet
W912DS18B0027-Amendment_0005.pdf PDF
GB_SEG_C2_CD-101XXX_Sep172018_F.pdf PDF
W912DS18B0027-Amendment_0004.pdf PDF
GB_SEG_C2_CD-106XXX_Sep172018_F.pdf PDF
NJDEP_permits_for_Green_Brook_(002).pdf PDF
09_97_02_Painting.pdf PDF
31_41_16_-_Sheet_Piling.pdf PDF
W912DS18B0027-Amendment_0003.pdf PDF
C-501.pdf PDF
EC-101.pdf PDF
Segment_C2_Contract_1_-_Amendment_2_-_Drawings.pdf PDF
Segment_C2_Contract_1_-_Amendment_2_-_Specifications.pdf PDF
W912DS18B0027-amendment0002.pdf PDF
Amendment_0001.pdf PDF
Solicitation_final.pdf PDF
Segment_C2_Contract_1_Specifications_Final.pdf PDF
1_-_General_(G)_Series.pdf PDF
5_-_Reference_Drawings.pdf PDF
2_-_Geotechnical_(B)_Series_(1).pdf PDF
4_-_Structural_(S)_Series.pdf PDF
3_-_Civil_Series_(C,CD,CG,EC,L,V,X).pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

Answ er questions from prospective bidder for informational purposes only

Bid due date remains 21-Sep-2018 at 2:00 P.M. EST NOTE: Bidders must acknow ledge receipt of this amendment of date specified in the bid (or as amended ) by one of the follow ing methods:

In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE MODIFICATION OF BID, OR LATE WITHDRAWAL OF

BID (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS18B0027

X 9B. DATED (SEE ITEM 11)

13-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Sep-2018

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS18B0027

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0005

(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).

Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications.).

QUESTION #1:In the answers 2 & 4 from Amendment 3, it is stated excavated soil is to only be hauled from the site if it is unusable for the rest of construction, and if it is hauled from the site the hauling will be paid for under Item #0011 or #0014. Based on our calculations, we believe there is a total of approximately 8,000CY of EXCESS soil (including spoils from Micro‐Pile installation), that will not have anywhere to be placed in the construction of the project (will be unusable for the rest of construction). In that proposal quantity for bid item #0011 is only for 1,000CY and Item #0014 is for only 1,000CY, we expect that the actual quantity for Bid Item #11 will have to be substantially increased. Therefore please increase the proposal quantity of Bid Item #0011 to account for all excess soil off‐site hauling accordingly. If that's not the case, and the intent is to stockpile the excess soil onsite for future segment construction, please clarify that the stockpile shown on drawing EC‐104 is large enough to handle this excess soil quantity, and that it can remain there after the project completion

ANSWER #1: Bid item 0011 is for the haul and disposal of unsatisfactory material and not surplus material.

Bid item 0014 is for the haul and disposal of contaminated non‐hazardous material and not for surplus material. Any satisfactory surplus material shall be included under the bid items for the applicable work.

No quantities require adjustment.

(End of Summary of Changes)