AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Revise the Specifications and Draw ings.
2. Incorporate Pre-Bid Conference Singn in Sheet.
3. Answ er Bidders questions for information purposes only. Responses do not revise the solicitation, plans or specifications.
The Bid Opening date is 24 November 2015 and the time is changed from 2:00 PM to 10:00 AM NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Nov-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-15-B-0013
X 9B. DATED (SEE ITEM 11)
26-Oct-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Nov-2015
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-15-B-0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 24-Nov-2015 02:00 PM to 24-Nov-2015 10:00 AM.
SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
AMENDMENT 0002
W912DS-15-B-0013
Amendment No.2
USACE, Department of the Army, NYD Corps of Engineers New York, NY 10278-0090 AMENDMENT NO.2 for IFB NO. W912DS-15-B-0013
1. The following changes shall be made to the specifications The New York District received questions about the solicitation.
Bid time changed from 2:00 PM to 10:00 am on November 24, 2015
1) SPECIFICATIONS:
-SECTION 00902:
1-Additional WQC Documents are added to the contract to SECTION 00902 and are posted in the FBO with this amendment
-SECTION 35 20 23.00 18
Replace paragraph 5.1.1 in its entirety as below
“5.1.1 Paid Dredge Tolerance To cover the inaccuracies of the dredging process, material actually removed from within the specified areas to be dredged (pay template), including paid dredge tolerance as specified below, will be estimated and paid for at the contract unit price. Paid dredge tolerance will only be paid in those areas where material exists above project grade of -50.0 ft MLW and -52.0 ft MLW in work area 2 and 4 (see plans). Within work areas 1, 3, 5 and 6 paid dredge tolerance will also be paid within 50ft of a shoal of -50.0ft MLW.
Paid dredge tolerance dredging will be permitted to a depth of not more than
1.0 ft (0.5 ft in area 6).
Paid dredge tolerance dredging will be measured and paid for at the applicable contract price in the same manner as specified for the overlying material.”
2) DRAWINGS AND OTHER REPORTS:
-All additional files are placed on the FBO website.
1-As Built Records and Reports.
2- Presentation for pre Bid Meeting On November 12, 2015.
These files are for bidder’s reference only, and are not to be considered as a part of the Contract Documents.
Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided. No representation is made as to availability of this data, its convertibility with user’s system
5) QUESTIONS AND ANSWERS:
The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation.
This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents. Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided. Questions and answers are issued to the Bidders for information only.
Q1. Based on the timing conflicts listed above, we respectfully request that the USACE consider modifying the contract documents to reflect an anticipated NTP issuance of 01 June 2016 (or an amendment that similarly alleviates the timing conflicts present in this solicitation).
A1. The Government expects to either 1) expeditiously award and issue the NTP with the winning offeror mobilizing quickly so that areas with environmental windows can be largely, if not altogether cleared, prior to the window. (As part of this expectation, efforts are underway to allow some flexibility in the work as it relates to environmental windows. For bidding purposes, unless changed in a future amendment, bidders should prepare their bid assuming that there are no windows on the water siphons, referred to as “WORK AREA 2” and “WORK AREA 4”), or 2) should no flexibility be achieved regarding the solicitation's existing environmental windows, that the government expects to postpone bid opening to early 2016 so sufficient time exists following bid opening for the work to be performed consistent with the existing environmental windows.
Q2. Do Work Areas 1, 3, and 5 allow excavation utilizing a hopper dredge?
A2. A hopper dredge is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q3. Do Work Areas 1, 3, and 5 allow hopper dredge overflow?
A3. Hopper dredge overflow is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q4. Do Work Areas 2 and 4 allow excavation utilizing a hopper dredge?
A4. A hopper dredge is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q5. Do Work Areas 2 and 4 allow hopper dredge overflow?
A5. Hopper dredge overflow is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q6. Does Work Area 6 allow excavation utilizing a hopper dredge?
A6. A hopper dredge is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q7. Does Work Area 6 allow hopper dredge overflow?
A7. Hopper dredge overflow is not precluded by the NYSDEC permit. Some operational restrictions have been included by NMFS. See Section 00902. See the technical specifications for specific hopper dredge related requirements.
Q8. Does the work in the Port Jersey Channel allow excavation utilizing a hopper dredge? Does the work in the Port Jersey Channel allow hopper dredge overflow?
A8. The Corps of Engineers has requested that the NJDEP permit be amended to permit this. For purposes of bidding, unless a future amendment states otherwise, offerors are to assume that a hopper dredge will be allowed to operate in Port Jersey with no barge overflow.