Section_31_21_13_Radon_Mitigation_June_24_2013.pdf

PDF 20 KB Posted

Attached to
Ballistic Evaluation Center, Phase III, Picatinny NJ
Solicitation number
W912DS-13-R-0027
Issued by

About this file

Attachments for W912DS-13-R-0027 AMENDMENT 0007 SECTION 31 21 13 RADON MITIGATION

View the file

Other files

File Type Posted
W912DS-13-R-0027_AMENDMENT_0010.pdf PDF
W912DS-13-R-0027_Amendment_0009.pdf PDF
W912DS-13-R-0028_AMENDMENT_0008.pdf PDF
IMG_0142.JPG JPG image
IMG_0141.JPG JPG image
IMG_0143.JPG JPG image
IMG_0140.JPG JPG image
130624_BEC_Phase_III_-_Amendment_No_7_-_Full_Size_Dwgs.pdf PDF
07_27_00_45_10.pdf PDF
IMG_0155.JPG JPG image
130624_BEC_Phase_III_-_Amendment_No_7_-_Half_Size_Dwgs.pdf PDF
IMG_0138.JPG JPG image
IMG_0139.JPG JPG image
W912DS-13-R-0027_Amendment_0007.pdf PDF
W912DS-13-R-0027_AMENDMENT_0006.pdf PDF
BEC_Phase_III_-_Amendment_No_5_-_Full_Size_Dwgs.pdf PDF
BEC_PH_III_-_Amendment_0005.pdf PDF
W912DS-13-R-0027_AMENDMENT_0004.pdf PDF
130422_BEC_Phase_III_-_RTA_Drawings_-_Full_Size.pdf PDF
W912DS-13-R-0027-0003_AMENDMENT_0003.pdf PDF
Pre_Propsal_Site_Visit_31_May_13.pdf PDF
W912DS-13-R-0027-0002_Amendment.pdf PDF
W912DS-13-R-0027-0001_AMENDMENT.pdf PDF
W912DS-13-R-0027_Solicitation.xlsx.pdf PDF
00_80_00_00_18_Attachment_Project_Identification_Sign_Details.pdf PDF
130422_BEC_Phase_III_-_RTA_Drawings_-_Half_Size.pdf PDF
130422_BEC_Phase_III_-_Specifications_-_Volume_II.pdf PDF
00_80_00_00_18_Attachment_Soil_Management_Procedures.pdf PDF
130422_BEC_Phase_III_-_Specifications_-_Volume_I.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BEC - PHASE III 24 JUNE 2013

NEW YORK DISTRICT USACOE - PICATINNY

SECTION 31 21 13

RADON MITIGATION

08/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C920 (2011) Standard Specification for Elastomeric Joint Sealants

ASTM D2665 (2011) Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings

INTERNATIONAL CODE COUNCIL (ICC)

ICC IMC (2009) International Mechanical Code

ICC UMC (1997; Errata 2 & 3 1997) Uniform Mechanical Code

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1378 (1995) Thermoplastic Duct (PVC) Construction Manual, 2nd Edition

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 402-R-93-078 (1993; R 1994) Radon Mitigation Standards

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 18 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Radon mitigation systems; G, RO

SD-03 Product Data

Radon mitigation systems components; FIO

SECTION 31 21 13 Page 1

1.3 QUALITY ASSURANCE

1.3.1 Contractor Qualifications and Experience

Within 15 days after award, submit written evidence or data demonstrating that the Contractor and/or one or more subcontractors employed by the Contractor possess the qualifications and experience specified below.

1.3.1.1 Contractor Qualifications

The person responsible for construction and on-site supervision, as required by the specifications, shall have successfully completed the requirements of and shall be maintaining a current listing in the USEPA RCP Program. Alternatively, in a State with legislation requiring mandatory credentialing for this work, compliance with the State legislation is acceptable. Evidence showing successful completion of the requirements of the USEPA National RCP Program shall include copy of current, valid USEPA RCP photo identification card or equivalent documentation issued by the State.

1.3.1.2 Contractor Experience

Submit written evidence demonstrating that the Contractor has successfully designed and installed at least two radon mitigation systems of the same or similar to the type required herein. Experience proof shall include but not be limited to:

a. The contract name and number, completion dates of the project and the total cost of the project;

b. The names, telephone numbers and fax number of the facility or installation for whom the radon mitigation system design, construction and/or testing were performed;

c. The name, telephone number and fax number of a supervisory level point of contact at each facility or installation who has knowledge of the Contractor's performance.

1.3.2 On-Site Supervision

No work at the site will be permitted without the presence of a person possessing the qualifications specified elsewhere in this section, namely USEPA RCP listing or the State equivalent, where applicable .

1.4 DELIVERY, STORAGE AND HANDLING

1.4.1 Delivery of Products

Deliver materials to the site in an undamaged condition. Deliver proprietary items in manufacture's original unopened and undamaged containers of packages with manufacture's name and brand and other pertinent data such as specification number, type, and class, date of manufacture. Schedule deliveries of materials to coincide with scheduled installation.

1.4.2 Storage and Handling

Carefully store materials off the ground to provide proper ventilation, drainage and protection against weather and dampness. Protect materials

SECTION 31 21 13 Page 2 from marring, staining, rust, damage and overload and from contaminants such as grease, oil and dirt. Store materials at temperatures recommended by the manufacturer. Handle material to avoid damage such as chipping and breaking. Replace damaged material.

PART 2 PRODUCTS

2.1 RADON MITIGATION SYSTEMS

2.1.1 System Performance

Radon mitigation systems shall reduce and maintain radon concentration levels.

2.1.1.1 System Piping

Route radon mitigation systems piping so as not to interfere with the daily operations and functions of the building occupants. Keep visibility of the systems to a minimum. Enclose each radon mitigation system in occupied spaces, however, all operating components shall be accessible for maintenance and repair. All spaces shall be considered to be occupied spaces except for mechanical and electrical rooms, warehouses, storerooms, janitor closets, crawl spaces, and attic spaces. Enclosures are not required for portions of systems installed above suspended acoustical ceilings.

2.1.1.2 System Outlet Location

Mitigation system discharge points shall be as specified in EPA 402-R-93-078.

Prevent foreign objects from entering the outlet. Maintain water tight seal through all penetrations to the building exterior.

2.1.2 Radon Mitigation Systems Components

Mechanical and electrical materials, fabrication, construction and installation shall conform to the following industry standards:

a. Poly(vinyl chloride) (PVC) Piping: ASTM D2665, Schedule 40.

b. Sealants: ASTM C920, polyurethane, Type S, Grade P for horizontal application, Grade NS for vertical application, Class 25, Use T.

PART 3 EXECUTION

3.1 RADON MITIGATION SYSTEMS INSTALLATION

3.1.1 Installation

Provide radon mitigation systems as indicated in the design drawings, as specified in EPA 402-R-93-078 and as required by the specifications and standards referenced herein for the respective materials using workmen skilled in the trades involved. Install piping plumb and parallel to existing walls, partitions and ceilings as appropriate, slope horizontal runs to drain, and secure in place in a rigid and substantial manner.

Seal new and existing floor slab penetrations in accordance with EPA 402-R-93-078 and as specified herein. Prevent entry of soil gas into the building and exhausting of conditioned air via the radon mitigation system. Seal cracks and openings around floor slab penetrations with

SECTION 31 21 13 Page 3 polyurethane sealant. Provide backer rod or comparable filler material as required. Insure that all penetrations to the building exterior are weathertight.

Lay work out in advance. Exercise care where cutting, channeling, chasing or drilling floors, walls, partitions, ceilings or other surfaces as necessary for proper installation, support or anchorage. Patch and repair damage to buildings, piping and equipment using workmen skilled in the trades involved.

Coordinate all work with the Contracting Officer.

3.1.2 Mechanical Work

ICC IMC, ICC UMC, SMACNA 1378 and EPA 402-R-93-078.

3.1.3 System Identification

Label all components of the radon mitigation systems including, but not limited to, piping (every ten feet) and enclosures. Labels shall read:

Radon Reduction System. Do Not Remove.

Public Works Office Phone Number: ___________ or as specified by the Contracting Officer.

-- End of Section --