W912DS-09-B-0015 Specifications.pdf

PDF 2 MB Posted

Attached to
Gerritsen Creek Ecosystem Tidal Marsh & Coastal Upland Community Restoration in Brooklyn, New York
Solicitation number
W912DS-09-B-0015
Issued by

About this file

Specifications to W912DS-09-B-0015.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW YORK DISTRICT

Marine Park: Tidal Marsh & Coastal Upland Ecosystem Restoration

Gerritsen & Mill Creeks Brooklyn, New York

100% Submission

Specifications

July 2009

MTOC - 1

MAIN TABLE OF CONTENTS

SECTION TITLE

00010 SF 1442 AND BIDDING SCHEDULE

00600 REPRESENTATIONS AND CERTIFICATIONS

(To be included by Contracting Division)

00700 CONTRACT CLAUSES

(To be included by Contracting Division)

00 80 00.00 18 SPECIAL CONTRACT REQUIREMENTS

LIST OF DOCUMENTS, EXHIBITS & OTHER ATTACHMENTS

00900 WAGE RATES

(To be included during advertising of project)

00901 BORING LOGS, TEST PITS, AND HAND AUGERS

00902 PERMITS

TECHNICAL PROVISIONS

01 12 00.00 18 DESIGN AND RECORD DRAWING REQUIREMENTS

01 32 01.00 18 PROJECT SCHEDULE

01 33 00.00 18 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENT SAFETY REQUIREMENTS

01 45 02.00 18 QUALITY CONTROL SYSTEM (QCS)

01 45 04.00 18 CONTRACTOR QUALITY CONTROL

01 54 00.00 18 MOBILIZATION AND DEMOBILIZATION

01 55 00.00 18 MAINTENANCE AND PROTECTION OF TRAFFIC – TYPE B

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 30.00 18 WORK SITE ACCESS ROAD AND STAGING AREA

01 67 00.00 18 RECYCLED/RECOVERED MATERIALS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00.00 18 CLOSEOUT SUBMITTALS

02 33 00.00 18 SILT FENCE

02 38 10.00 18 ANTI-TRACKING PAD

03 11 14.00 10 FORMWORK FOR CONCRETE

03 20 02 STEEL BARS AND WELDED WIRE FABRIC FOR CONCRETE

REINFORCEMENT FOR CIVIL WORKS

MTOC - 2

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE

05 05 23 WELDING, STRUCTURAL

06 10 00 ROUGH CARPENTRY

12 93 00 SITE FURNISHINGS

31 00 00 EARTHWORK

31 05 22 FILTER FABRIC

31 10 00 SITE CLEARING

31 11 00 CLEARING EXISTING VEGETATION AND DEBRIS FROM

THE RESTORATION AREA

31 11 24 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE

BASE COURSE

31 32 11 SOIL SURFACE EROSION CONTROL

32 15 00 AGGREGATE SURFACE COURSE

32 16 13 CONCRETE SIDEWALKS, CURBS AND GUTTERS

32 16 14.00 18 RESTORATION OF STREET PAVEMENT

32 16 15.00 18 NATURE TRAIL

32 31 01 CONSTRUCTION FENCING

32 31 13 FENCING

32 92 19 SEEDING

32 93 00 EXTERIOR PLANTING

32 96 00 TRANSPLANTING EXTERIOR PLANTS

33 40 00 STORM DRAINAGE

33 46 16 SUBDRAINAGE SYSTEM

Marine Park: Tidal Marsh & Coastal Upland Ecosystem Restoration, Gerritsen & Mill Creeks

00 80 00.00 18 - 31

00 80 00.00 18 - 32

00 80 00.00 18 - 33

00 80 00.00 18 - 34

Section 00901

Boring Logs

Boring ID: GCB-1 Date:

by: B. Jankauskas

Depth (ft) Sample Sample No.

Blow

Counts % Recovery Description USCS

0-2 ft yes GCB1-0-2 3-4-7-9 75%

0-3" - brown, m-f SAND, little Silt, trace organics, dry.

3-15" - brown m-f SAND, trace Silt, root, moist.

15-18" - Gray m-f SAND, trace Silt, moist. SP-SM

2-4 ft yes GCB1-2-4 7-9-9-8 70% Gray m-f SAND, little Silt, wet. SP-SM 4-6 ft yes GCB1-4-6 4-4-3-1 50% Gray m-f SAND, little Silt, wet. SP-SM 6-8 ft yes GCB1-6-8 1-0-1-1 50% Meadow Mat OH 8-10 ft yes Shelby* 25% Gray Clayey SILT, little m-f Sand, wet. ML 10-12 ft yes GCB1-10-12 3-1-1-3 40% Gray m-f SAND, trace Silt, wet. SP 12-14 ft yes GCB1-12-14 4-6-8-10 40% Brownish Gray c-f Sand, trace Silt, trace m Gravel, wet. SP

14-16 ft yes GCB1-14-16 2-5-4-3 70% 0-7" Gray organic material and Clayey Silt, trace m-f Sand, wet.

7-16" Brown c-f SAND, trace Silt, wet. OH

16-18 ft yes GCB1-16-18 5-6-7-6 60% Brown c-f SAND, trace fine Gravel, wet. SP 18-20 ft yes GCB1-18-20 3-3-4-4 40% Brown c-f SAND, trace Silt, wet. SP

Bottom of Boring 20 ft.

*Shelby Tube had zero recovery, a sample was collected with split spoon.

Another Shelby Tube was pushed from 6-8 ft (24" Recovery) after boring was completed.

Louis Berger Group, Inc. - Boring Log Gerritsen Creek - Brooklyn, New York

April 25, 2002

Boring ID: GCB-2 by: B. Jankauskas

Depth (ft) Sample Sample No. Blow Counts % Recovery Description USCS

0-2 ft yes GCB2-0-2 2-3-5-6 75% 0-5" - Brown f SAND, little Silt, dry.

5-13" - light Brown f SAND, trace Silt, dry. SP-SM

2-4 ft yes GCB2-2-4 5-7-6-6 55% 0-4" - light Brown f SAND, trace Silt, wet.

4-9" - Gray f SAND, trace Silt, wet. SP

4-6 ft yes GCB2-4-6 2-2-2-1 70% Gray f SAND, little Silt, wet. SP-SM

6-8 ft yes GCB2-6-8 1-1-1-1 90% 0-7" - Gray f SAND, little Silt, wet.

7-15" - Meadow Mat

SP-SM

OH

8-10 ft yes GCB2-8-10 1-1-1-1 90% Meadow Mat OH

10-12 ft yes GCB2-10-12 2-3-5-4 40% 0-2" Meadow Mat 2-10" Gray f SAND, little Silt, wet.

OH

SP-SM

12-14 ft yes GCB2-12-14 2-3-3-4 55% Gray f SAND, and Silt, wet. SM

14-16 ft yes GCB2-14-16 2-1-3-9 40% 0-6" Gray f SAND, and Clayey Silt, wet.

6-10" Gray c-f SAND,little Silt, trace f Gravel, wet.

SM SP-

SM

16-18 ft yes GCB2-16-18 8-7-9-9 50% Brownish Gray c-f SAND, little Silt, wet. SP-SM 18-20 ft yes GCB2-18-20 5-6-11-10 40% Gray c-f SAND, trace silt, wet. SP

Bottom of Boring 20 ft

Shelby Tube pushed from 6-8 ft (24" Recovery) after boring was completed.

Louis Berger Group, Inc. - Boring Log Gerritsen Creek - Brooklyn, New York

April 25, 2002

GERRITSEN CREEK

SOIL-BORINGS Two Foot Split Spoons April 25, 26, 2002

GCB-3

Depth (ft) Sample Sample No. Blow Counts(inches) % Recovery Description USCS 0 - 2 yes GCB3-0-2 3 - 6 - 6 - 8 75% fine roots,humus,black color,med-cors san SW-SM

2ft - 4ft yes GCB3-2-4 7 - 10 - 11 - 13 50% some humus,moist,course sand,dark grey SP-SM 4ft - 6ft yes GCB3-4-6 10 - 6 - 7 - 4 100% moist sand,brown some grey color SW-SM 6ft - 8ft yes GCB3-6-8 2 - 1 - 1 for 12 100% Clay, moist,brown-black,some plasticity CL-ML 8ft - 10ft yes 4 - 1 - 1 for 12 50% sat.sand,H2S smell, SC - SM

SHELBY 100%

GCB-4

0 - 2 yes GCB4-0-2 2 - 3 - 4 - 5 50% organic matter 0-6 inches,med cors snd SW-SM 2ft - 4ft no GCB4-2-4 5 - 5 - 6 - 5 66% shell bits 3ft.,moist,lgt brn color snd SW-SM 4ft - 6ft yes GCB4-4-6 2 - 2 - 3 - 2 75% moist, silty sand brown grey color SM 6ft - 8ft no GCB4-6-8 6 - 1 - 1 - 1 100% moist,med-fine gran snd,lite-dark tan-grey SW-SM 8th - 10th no GCB4-8-10 1 - 2 - 2 - 3 80% cors snd,saturated,dark grey SW-SM

SHELBY 100%

GCB-5

0 - 2 no 2 - 4 - 5 - 6 50% 0 - 1ft organic/roots,moist snd, tan color SW-SM 2ft - 4ft no 4 - 4 - 5 - 4 5% fill material 4ft - 6ft no 2 - 1 - 4 - 1 0% 6ft - 8ft no 4 - 6 - 5 - 5 50% fill, fine sand,brown-dark tan color SM 8ft - 10ft no 5 - 1 - 1 - 6 5% fill, slight leachate smell 10ft - 12ft no 3 - 2 - 3 - 1 0% 12ft - 14ft no 2 - 1 - 1 - 2 0% 14ft - 16ft no 2 - 1 - 7 - 10 50% saturated sand, meadow mat SM 16ft - 18ft no 9 - 8 - 4 - 4 25% coarse snd,dark grey SW

NO SHELBY

GCB-6

0 - 2 no 1 - 1 - 2 - 2 66% 0-1ft organic/roots,dry snd,tan-grey color SM 2ft - 4ft no 1 - 1 - 1 - 1 20% debris, fill 4ft - 6ft no 1 - 1 - 1 - 1 50% 4-5ft debris,5-6ft brown-black fine grain SM 6ft - 8ft no 2 - 3 - 1 - 4 10% slight oil smell,black fine grain silty snd SM 8ft - 10ft no 3 - 3 - 3 - 4 5% moist more soil like, black-brown OH 10ft - 12ft no 3 - 2 - 2 - 2 0% 12ft - 14ft no 2 - 2 - 2 - 2 75% saturated,black-grey color,silty clay, mat SC-SM 14ft - 16ft no 3 - 2 - 1 - 2 0% 16ft - 18ft no 2 - 4 - 5 - 10 10% soft clay,sand,light to dark tan color SC 18ft - 20ft yes 7 - 7 - 10 - 12 10% dark brown silty to coarse sand SM

GCB-7

0 - 2 no 1 - 1 - 2 - 3 50% dry,fine grain sand,tan to grey color SW 2ft - 4ft no 3 - 3 - 4 - 7 50% moist,organic layer,fine sand,tan-dark tan SW 4ft - 6ft no 4 - 3 - 3 - 2 100% moist,fine grain sand, tan color SW 6ft - 8ft no 1 - 1 - 1over12 100% mat at 7ft. OH 8ft - 10ft yes SHELBY 100% 10ft - 12ft no 3 - 2 - 5 - 6 100% consistent gray color, sand saturated SW-SM

GERRITSEN CREEK

SOIL-BORINGS Two Foot Split Spoons

GCB - 8 Southwest corner of deposition area 0 - 2 ft no 1 - 1 - 1 - 2 0 recov 2 - 4 ft no 2 - 1 - 1 - 9 4 inch recov fill, oily smell 4 - 6 ft no 18 - 6 - 4 - 2 50% recov moist sand, some roots, silty sand, oil smell 6 - 8 ft no 2 - 1 - 1 - 2 0 recov 8 - 10 ft no 10 - 9 - 5 - 2 4 inch recov black fines oily smell, coal gas smell 10 - 12 ft no 4 - 4 - 4 - 6 4 inch recov oily smell, brown sand, silty sand 12 - 14 ft no 2 - 1 - 2 - 3 100%recov saturated sand, stiff clay, silty clay, oil smell 14 - 16 ft no 9 - 7 - 9 - 11 3/4 recov wet brown med-fine sand, sandy clay, oil smell 16 - 18 ft no 5 - 9 - 16 - 20 100% recov brown wet coarse-fine sand, oil smell 18 - 20 ft no 17- 16 - 15 - 15 50% recov brown wet coarse-fine sand, oil smell

GCB - 9 along path, by overlook 10 - 12 ft no 9 - 4 - 2 - 3 0 recov 12 - 14 ft no 2 - 1 - 2 - 1 1/3 recov sandy clay - clay wet, slight oil smell

GCB-10 off path by look-out 0 - 2 no 10 - 9 - 8 - 9 12 inch recov debris, glass bits 2 - 4 ft no 7 - 6 - 3 - 5 6 inch recov dry fill, glass bits 4 - 6 ft no 3 - 3 - 2 - 2 12 inch recov dry - moist clay consistentcy 6 - 8 ft no 2 - 1 - 3 - 2 0 recov 8 - 10 ft no 5 - 7 - 5 - 3 0 recov 10 - 12 ft no 10 - 6 - 7 - 11 0 recov 12 - 14 ft no 10 - 5 - 3 - 2 0 recov 14 - 16 ft no 2 - 1 - 2 - 2 0 recov 16 - 18 ft np 4 - 3 - 2 - 3 50% recov sandy clay, moist, gray - black 18 - 20 ft no 7 - 9 - 18 - 20 4 inch recov wet black sand, med - coarse grain 20 - 22 ft no 24 - 21 - 16 - 11 100%recov dark brown silty, cobble to 4 mm wet

GCB-11 northeast corner of disposition area 12 - 14 ft no 7 - 7 - 5 - 3 100% recov moist, gray sands, sandy clay, silty sands 14 - 16 ft no 3 - 6 - 9 - 12 100% recov gray silty sands, moist, 16 - 18 ft no 12 - 14 - 14 - 16 3/4 recov moist, gray sands, 4mm cobble, sandy clay 18 - 20 ft no 11 - 13 - 16 - 13 3/4 recov wet, med-coarse gray sand

GCB - 12 near water side of excavation area 10 - 12 ft no 3 - 4 - 2 - 2 0 recov 12 - 14 ft no 2 - 3 - 2 - 1 4 inch recov wet, dark brown sand, silty sand to coarse

June 4, 2002

Section 00902

Permits

STATE OF ~-.lEW YORK

DEPARTMENT OF STATE

41 STATE STREET

ALBANY. NY" 12231-0001

GEORGE E. PATAK:

GOYER NOR

March 9, 2004 RANDY A.

SECRETARY

DM!lELS

O~- ~TATE

Melissa Alvarez es Atmy Corps of Engineers New York District Environmental Analysis Branch Jacob J. Javits Federal Building New York, NY 10278

Re: F-2003-0726 US Atmy Corps of Engineers - Gerritsen Creek Ecosystem Restoration Section 1135 Gerritsen Creek, City of New York, Kings County Concurrence with Consistency Determination

Dear Ms. Alvarez:

The Department of State has completed its review of the U.S. Atmy Corps of Engineers consistency deterroinationregarding the consistency ofthe Gerritsen Creek EcosystemRestoration proj ect with the New York State Coastal Management Program, as it is expressed in the City of New York's Waterfront Revitalization Program.

Based upon the inforroation submitted, the Department of State concurs with the consistency determination regarding this matter.

Sincer9ly, _/7 #??_<-.'"""-_---~ ~ .. <-- / 'A"

Sam Messina Deputy Director Division of Coastal Resources

SEMibk c: NYC WRP - Eddie Greenfield

WVvW.DOS STATE. NY. us E-MAIL".NFO@DCS.C:"T"ATE.NY.US

New York State Department of Environmental Conservation

Division of Environmental Permits, Region 2 ~

47-40 21 sT Street, Long Island City. NY 11101-5407 .....Phone: (718) 482-4997 • FAX: (718) 482-4975 Website: www.dec.state.ny.us ~

Erin M. Crotty Commissioner

June 30, 2004

Melissa D. Alvarez U.S. Army Corp. of Engineers - Planning Division

Jacob K. Javitz Federal Building

26 federal Plaza - Room 2 I36

New York. New York 10278-0090

Re: NYSDEC Permit No. 2-6107-00638/00001 U.S. Army Corp. of Engineers

Gerritsen Creek Ecosystem Restoration

Brooklyn, New York

6NYCRR Part 608 - Water Quality Certification

ECL Article 15 - Protection of Waters

ECL Article 25 - Tidal Wctlands

NOTICE OF PERMIT ISStJANCE

Dear Ms. Alvarez:

Enclosed is your permit. Please read it carefully. Compliance with all permit conditions is required.

Please note that Natural Resource Permit Condition 4 of the permit requires submission ofthe attached

"Notice oflntent to Commence Work" at least 5 days before beginning the permitted act,vity.

Technical questions concerning this matter should be directed to Stephen Zahn, N YSDEC Marine

Resources. 71 8 482-6464. Administrative questions should be directed to me at the above number.

Sincen;ly.

',/;;j-;::eotZt;1 k"/~' ~'jt.~.:_{) . Tamara A. GreCo Environmental Analyst cc: NYSDEC Marine Resources / Law Enforcement

NEW YORK STATE DEPART'\'1ENT OF ENVIRONMENTAL CONSERVATION -

Facility DEC ID 2-6107-00638 -

PERMIT

Under the Environmental Conservation Law (ECL)

Permittee and Facility [nformation

Pel-mit [ssued To:

US DEPT OF THE ARMY

THE PENTAGON

WASHINGTON. DC 20310

Facility:

lJ S DEPT OF THE ARMY - GERRITSEN

CREEK

GERRITSEN CREEK

BROOKLYN. NY

Facilit." Location: in KINGS COUNTY Village: Brooklyn Facility Principal Reference Point: NYTM-E: 590.862 NYTM-N: 4494.991 Project Location: Marine Park on Gerritsen Creek

Authorized Activity: Restore approximately 35.5 acres of wetland and upland habitat- which includes approximately 20.5 acres of inter tidal salt marsh and approximately 15 acres of coastal/maritime grassland. The restoration of the historic intertidal marsh will require the removal of approximately

85.000 cubic yards offIll material which will then be placed in the upland areas to create the new coastal maritime grassland. The areas 10 be restored will be planted with appropriate vegetation and a nature trail system will be established.

Permit Authorizations

Tidal Wetlands - Ii nder Artiele 25 Pennit ID 2-6107-00638/0000 I

New Permit Effective Date: 6/30/2004 Expiration Date: 17 /31/20 II Water Quality Certification - Under Seetion 401 - Clean Water Act Permit ID 2-6107-00638/00002

New Permit Effective Date: 6/30/'004 Expiration Dat~. 12/31/'0.1 J

Excavation & Fill in Navigable Waters - Under Artiele 15, Title 5 Permit ID 2-6107-00638/00003

New Permit Effer1ive Date: 6/30/2004 Expiration Date: 1;:f3l/7 011 e

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION

Facility DEC lD 2-6107-00638

NYSDEC Approval

By acceptance of this permit, thc permittee agrees that the permit is contingent upon strict compliance with the ECL, all applicable regulations, and all conditions included as part of this permit.

Pcrmit Administrator: JOHN F CRYAN. Regional Pcrmit Administrator Address: NYSDEC REGION 2 HEADQUARTERS

47-40 21ST STREET

LONG ISLAND CITY. NY 11101 -5407

, r . C', Authorized Signature: \1>.,. /\ ." \,', ,,'\

/ Y' . \"-.\

GENERAL CONDITIONS. APPLY TO ALL AUTHORIZED PERMITS

NOTIFICATION OF OTHER PERMITTEE OBLIGATIONS

NATURAL RESOURCE PERMIT CONDITIONS - Apply to the Following

Permits: TIDAL WETLANDS; WATER QUALITY CERTIFICATION;

EXCAVATION & FILL IN NAVIGABLE WATERS

1. Conformance With Plans All activities authorized by this permit must be in strict conform,mee with the approved plans submitted by the applicant or his agent as part of the permit application. Such approved plans were prepared by The Louis Berger Group. Inc., titled 'Tidal Marsh & Coastal Upland Community Restoration Design for GClTitsen Creek', sheets 1-33 of 33, dated 4/19/04, received by NYSDEC on April 26, 2004.

2. Final Drawings At least thirty (30) days prior to thc start of work. the Permittee must submit final design drawings to NYSDEC Bureau of Marine Resources, 47-40 21st Street. Long Island City. New York 1110 I (Attention: Stephen Zahn) for review and approval. Said drawings should clearly identify the location of site access points and staging areas.

3. Project Cooperation Agreement Letter Prior to the start of work Permittee must submit to the NYSDEC Regional Permit Administrator. 47-40 2 Ist Street, Long Island City. New York 1110 I a copy of the Project Cooperation Agreement Letter between New York City Parks and Recreation and the US Anny Corps for the Gerritsen Creek Ecosystem Restoration, Section 1135, Brooklyn. plY.

4. Written Notification to NYSDEC At least five (5) days prior to the stmt of work Permittee must complete and submit the attached "Notice oflntent to Commence Work" form to the NYSDEC Bureau ofMmine Resources. 47-40 21st Street, Long Island City. New York 11101 (Attention: Stephen Zahn).

5. Pre-Construction Meeting Prior to the stm1 of work, the Permittee must hold a pre-construction meeting with the contractor. The NYSDEC Bmeau of Mmine Resources. 47-40 21 5t Street. Long Island

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION --Facility DEC ID 2-6107-00638

City. New York IIIOI (Attention: Stephen Zahn) must be notified of this meeting at least live (5) days in advance.

6. Posting of NYSDEC Permit Sign The attached NYSDEC permit sign must be posted. protected from the weather. in a conspicLlllUs outdoor location at the project site. This sign is to be posted for the duration of work authorized by this permit.

7. Project Sign \Vithin thirty (30) days of permit issuance. the Permittee must contact the NYSDEC Bmeau of Marine Resources. 47-40 21st Street. Long !sland City. New York [IIO! (Attention: Stephen l:al1l1) in order to develop proper content for a project sign.

8. Best Management Practices Best management practices must be employed to prevent construction materials, debris. and sediment from entering the wetlands or waterways. Such practices may include.

but are not limited to silt fencing. hay bales. and containment booms.

9. Storage of Construction Equipment and Materials The storage of construction equipment and materials must be confined to within the project work site and or upland arcas greater than 30 linear feet from the tidal wetland boundary.

10. No Equipment Below Appareut High Water Equipment operation below apparent high water is strictly prohibited.

[l. Concrete or Leachate Must Not Escape During construction, concrete or leachate must not escape or be discharged. nor will washings from transit mix trucks, mixers, or other devices enter tidal \vetl,mds and or protected buffer areas.

12. Soil Distnrbance All areas of soil disturbance resulting from this project must be stabilized as per specilications identified on plans referenced in Natural Resources Permit Condition1.

13. Water Quality Certification The NYS Department of Environmental Conservation hereby certifies that the subject project will not contravene etlluent limitations or other limitations or standards under Sections 301, 302. 303. 306 and 307 of the Clean Water Act of 1977 (PL 95-217) provided that all of the conditions listed herein are met.

14. State May Order Removal or Alteration of Work If future operations by the State of New York reqnire an alteration in the position of the structure or work herein authorized. or if in the opinion of the Department of Environmental Cl1Jlservation it shall cause unreasonable obstruction to the tree navigation of said waters or flood flows or endangcr the health. safety or welfare of the people of the State. or cause loss or destruction of the natural resources of the State, the owner may be ordered hy the Department to remove or alter the structural work. ohstrnct;ons. or hazards caused thereby without expense to the State.

and if upon the expiration or revell'ation of this permit. the structure. fill. excavation. or other modification of the watercourse hereby authorized shall not be completed, the owners. shall. without expense to the State. and 10 such extent and in such time and manner as the Department of Environmental Conservation may require. remove all or any pOliion of the uncompleted structure or jill and restore to its fonner condition the navigable and flood capacity of the watercourse. No claim shall be made against the State of New York on account of any such removal or alteration.

15. State Not Liable for Damage The State of New York shall in no case be liable ;~jr any llamage or injllrv to the structure or \vork Ilcrein authorized which may be caused by or result ji-om future operations undcrUkell hy the State (lu'lhc conservation or improvement of navigation. or for other purposes. and no claim or right to compensation shall accrue hom any such damage.

a..- NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVAnON

Facility DEC ID 2-6107-00638

16. Permittee Responsible For Other Approvals Granting of this permit does not relieve the applicant ofthe responsibility of obtaining any other permission, consent or approval from the U.S.

Army Corps of Engineers. U.S. Coast Guard. New York State Omce of General Services or local government which may be required.

17. Precautions Against Contamination of Waters All necessary precautions shall be taken to preclude contamination of any wetland or waterway by suspended solids. sediments, fuels. solvents.

lubricants. epoxy coatings. paints. concrete. leachate or any other environmentally deleterious materials associated with the project.

18. No Interference With Navigation There shall be no unreasonable interference with navigation by the work herein authorized.

19. State May Require Site Restoration Hupon the expiration or revocation of this permit. the project hereby authorized has not been completed. the applicant shall, without expense to the State. and to such extent and in such time and manner as the Department of Environmental Conservation may require. remove all or any portion of the uncompleted structure or fill and restore the site to its former condition. No claim shall be made against the State ofNew York on account of any such removal or alteration.

GENERAL CONDITIONS - Apply to ALL Authorized Permits:

I. Facility Inspection by The Department The permitted site or facility. including relevant records. is subject to inspection at reasonable hours and intervals by an authorized representative of the Department of Environmental Conservation (the Depal"tmeut) to determine whether the permittee is complying with this permit and the ECL. Such representative may order the work suspended pursuant to ECL 71- 0301 and SAPA 401(3).

The permittee shall provide a person to accompany the Depmtment's representative during an inspection to the permit area when requested by the Department.

A copy ofthis permit. including all referenced maps, drawings and special conditions, must be available for inspection by the Department at all times at the project site or facility. Failure to produce a copy of the permit upon request by a Department representative is a violation of this permit.

2. Relationship of this Permit to Other Department Orders and Determinations Unless expressly provided for by the Department, issuance of this permit does not modify. supersede or rescind any order or determination previously issued by the Department or any of the terms, conditions or requirements contained in such order or determination.

3. Applications For Permit Renewals, Modifications or Transfers The permittee must submit a separate written application to the Department for permit renewal. modification or transfer of this permit. Such application must include any !()rms or supplemental information the Department requires.

Any renewaL modification or transfer granted by the Department must be in writing. Submission of applications for pcrmit rcncwal. modification or transfer arc to be submitted to:

Regional Permit Administrator

NYSDEC REGION 2 HEADQUARTERS

Page 4 of6

Facility DEC ID 2-6 J07-00638

47-40 21ST STREET

LONG ISLAND CITY, NYll101 -5407

4, Submission of Renewal Application The permittee must submit a renewal application at least 30 days bef()!"c pelmit expiration for the following permit authorizations: Water Quality Certification, Excavation & Fill in Navigable Waters, Tidal Wetlands.

5, Permit Modifications, Suspensions and Revocations by the Department The Department reserves the right to modify, suspend or revoke this pennit. The grounds for modification, suspension or revocation include:

a. materially false or inaccurate statements in the permit application or supporting papers;

b. failure by the permittee to comply with any terms or conditions of the permit;

e. exceeding the scope of the project as described in the permit application:

d. newly discovered material information or a material change in environmental Lvnditions, relevant technology or applicable law or regulations since the issuance of the existing permit;

e. noncompliance with previously issued permit conditions, orders of the commissioner. any provisions of the Environmental Conservation Law or regulations of the Department rclated to the permitted activity.

6, Permit Transfer Permits are transferrable unless specifically prohibited by statute, regulation or another permit condition. Applications for permit transfer should be submitted prior to actual transfer of ownership.

NOTIFICATION OF OTHER PERMITTEE OBLIGATIONS

Item A: Permittee Accepts Legal Responsibility and Agrees to Indemnification The permittee expressly agrees to indemnifY and hold harmless the Department of Environmental Conservation of the State of New York. its representatives. employees, and agents ("DEC") for all claims. suits, actions. and damages. to the extent attributable to the permittee's acts or omissions in connection with the permittee's undertaking of activities in eOillleetion with, or operation and maintenance of~ the facility or facilities authorized by the pennit whether in compliance or not in compliance with the telms and conditions of the permit. This indemnification does not extend to any claims, SLlits, actions. or damages to the extent attributable to DEC's own negligent or intentional acts or omissions. or to any claims, suits, or aClions naming the DEC and arising under Article 78 of the New York Civil Practice Laws and Rules or any citizen suit or civil rights provision under federal or state laws.

Item B: Permittee's Contractors to Comply with Permit The permittee is responsi bie for informing its independent contractors, employees, agents and assigns of their responsibility to comply with this permit. including all special conditions while acting as the permittees agent with respect to the permitted activities, and such persons shall be subject to the same sanctions for violations of the Environmental Conservation Law as those prescribed for the permittee.

Item C: Permittee Responsible for Obtaining Other Required Permits Page 5 01'6

Facility DEC lD 2-6107-00638

The permittee is responsible lor obtaining any other permits. approvals. lands. easements and rights-oJ~ way that may be required to carry out the activities that are authorized by this permit.

Item D: No Right to Trespass or Interfere with Riparian Rights This permit does not convey to the permittee any right to trespass upon the lands or intert~re with the riparian rights of others in order to perform the permitted work nor does it authorize the impainnent of any rights. title. or interest in real or personal property held or vested in a person not a party to the permit.

NOTICE OF INTENT TO COMMENCE WORK

NYSDEC Marine Resources Attn. Stephen Zahn N.Y.S.D.E.C Region 2 Office 47-40 21st Street Long Island City. N.Y. 11101

Re: l'It'SDEC Permit No. 2-6107-00638/00001 US Army Corps Gerritsen Creek Restoration Marine Park Brooklyn, New York

Dear Mr. Zahn:

In accordance with Natural Resource Condition "4" of the referenced permit, I hereby serve notice to commence work on , 200

This is also to certify that, having read this entire permit, I am fully aware of and understand the general and natural resource conditions therein, and agree to comply with all such conditions further understand that prior to undertaking any modification to the subject work, I must seek and receive written approval of the NYSDEC Regional Permit Administrator.

Signature of Permittee Signature of Contractor

Name of Permittee (please print) Name of Contractor (please print)

Street Address of Contractor

City, State, & Zip Code of Contractor

Telephone Number of Contractor

WARNING

The permittee ancl his contractor (if any) are requirecl to follow all permit conditions. Violations of the permit may lead to legal action, inducling die imposition of substantial monetary fines and corrective worb.

cc: Environmental Permits

95·20·1 (8187)-9d

New York State

Department of Environmental Conservation

....., ....TIC~ ~

The Department of Environmental Conservation (DEC) has issued permit(s) pursuant to the Environmental Conservation Law for work being conducted at this site. For further information regarding the nature and extent of work approved and any Departmental conditions on it, contact the Regional Permit Administrator listed below. Please refer to the permit number shown when contacting the DEC. (1,0

/,/ \'-\j'r~~ "'=--,,) ~ \'_ -tA_.,\,,(\/\, ,-, ~__---- _

/ Re~ional Permit"Adfnin1"strator I \ , ' ~\

2-6107-00638/00001 John F/Cryanl ) \ Permit Number ~ 47-40 ~1'1 Street

12131/11 LIe, N-Y 11101

Expiration Date _

(718) 482-4997NOTE: This notice is NOT a permit

Marine Park: Tidal Marsh & Coastal Upland Ecosystem Restoration GERRITSN

SECTION 01 12 00.00 18

DESIGN AND RECORD DRAWING REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

All RECORD DRAWINGS (or "as-builts") to be provided under this contract shall be accomplished and developed using computer-aided design and drafting (CADD) software and procedures conforming to the following criteria.

1.2 GRAPHIC FORMAT

All CADD data shall be supplied in Bentley Systems, three-dimensional, MicroStation V8, native electronic digital format (i.e., .dgn, .cel). The contractor shall ensure that all digital files and data (e.g., model files, sheet files, reference files, cell libraries) are compatible with the Government's target CADD system (i.e., basic and advanced CADD software, platform, database software), and adhere to the standards and requirements specified herein. The term "compatible" means that data can be accessed directly by the target CADD system without translation, preprocessing, or postprocessing of the electronic digital data files. It is the responsibility of the contractor to ensure this level of compatibility.

1.3 CADD STANDARDS

CADD drawings shall be prepared in accordance with the New York District CAD Standard Version 1.0, the governing subset of the Department of Defense Architectural/Engineering/Construction (A/E/C) Computer-Aided Design and Drafting (CADD) Standard, Release 3.0. Standard drawing size shall be ANSI-D CADD drawings shall be prepared using inch-pound units.

All model files and sheet files shall include the following project code in their A/E/C CADD Standard file-name GERRITSEN_CREEK_.

The Contractor shall submit a written request for approval of any deviations from the Government's established A/E/C CADD standard. No deviations from the Government's established A/E/C CADD standard will be permitted unless prior written approval of such deviation has been received from the Government.

1.4 DELIVERY MEDIA AND FORMAT

All CADD data and files developed under this contract shall be delivered to the Government on electronic digital media atproject completion, with each submittal as required in the Schedule of Work. The electronic digital data and files shall be provided on optical media (CD-ROM or DVD-R), referred to as a "disc." Each disc shall be delivered to the Government in a separate container, commonly referred to as a "jewel box." The electronic digital media shall be in a format that can be read and processed by the Government's target CADD system.

SECTION 01 12 00.00 18 Page 1

Model files, sheet files, and other associated files shall not be device-dependent, nor shall the directory structure of the disc require any reconfiguration or other manipulation on the Government's part to view, print, and plot the files directly from the disc. The directory structure of the disc shall be configured such that a complete download of the disc's contents to an electronic folder on a Government computer's hard drive will not require any reconfiguration or other manipulation on the Government's part to view, print, and plot the files.

A tagged portable document format (.pdf) file containing the set of full-sized plotted Sheet Files shall be also included on each disc. This .pdf set shall contain active bookmarks linking to each drawing in the set. The initial view of this set shall conform to the following settings: Layout and Magnification/Navigation Tab set to Bookmarks Panel and Page. Layout and Magnification/Page Layout set to Single Page. Layout and Magnification/Magnification set to Fit Page. (For further information on tagged .pdf documents refer to this website:

http://blogs.adobe.com/acrolaw/2006/01/understanding_t_1.html.)

Each disc shall be labeled with a printed label and each printed disc label shall contain, as a minimum, the following information:

(1) The Project's Name, Contract Number (and Delivery Order Number if applicable), date, and version and/or submission number.

(2) The name of the preparer's firm and the name and phone number of the preparer's Point-of-Contact for the project.

(3) The sequence number of the digital media for multiple-disc submittals.

(4) A description of the contents of the disc (e.g., "Architectural Plans," etc.).

Note: it is acceptable, storage permitting, to include specifications, design analyses and other data on the disc as space permits. These items shall be included in the disc label in accordance with paragraph above.

1.5 HARD COPY TRANSMITTALS

A transmittal letter shall accompany each electronic digital media submittal to the Government. The transmittal letter shall be dated and signed by the appropriate Contractor's representative. The transmittal letter shall be provided to the Government on 8-1/2-inch by 11-inch paper.

An electronic copy of the transmittal letter in .pdf format shall also be provided on the electronic digital media submitted to the Government. The transmittal letter shall contain, as a minimum, the following information:

(1) The information included on the external label of each CD-ROM, along with the total number being delivered, and a list of the names and descriptions of the files on each media unit.

(2) List of all new symbol cells created for the project, which were not provided to the Contractor with the Government-furnished materials. List of all new figures, symbols, tables, schedules, details, and other cells created for the project, which were not provided to the Contractor with the Government-furnished materials, and any associated properties. List of all database files associated with each drawing, as well as a description and documentation of the database format and schema design. Recommended modifications which will be necessary to make the data available for GIS

SECTION 01 12 00.00 18 Page 2 use.

(3) Certification that all delivery media are free of known computer viruses. A statement including the name(s) and release date(s) of the virus-scanning software used to analyze the delivery media, the date the virus scan was performed, and the operator's name shall also be included with the certification. The release or version date of the virus-scanning software shall be the current version which has detected the latest known viruses at the time of delivery of the digital media.

(4) A statement indicating that the A-E will retain a copy of all delivered electronic digital media (with all files included) for at least one year and, during this period of time, will provide up to 2 additional copies of each to the Government, if requested, at no additional cost.

(5) List of any deviations from the Government's standard level scheme and file-naming conventions and a copy of the Government's signed and dated approval letter allowing these exact deviations from the New York District CAD Standard.

The Contractor shall also provide paper copies of drawings as indicated in the paragraph entitled "Record Drawings" in Section 00 80 00.0018 SPECIAL

CONTRACT REQUIREMENTS.

1.6 OWNERSHIP

The Government, for itself and such others as it deems appropriate, will have unlimited rights under this contract to all information and materials developed under this contract and furnished to the Government and documentation thereof, reports, and listings, and all other items pertaining to the work and services pursuant to this agreement including any copyright. Unlimited rights under this contract are rights to use, duplicate, or disclose text, data, drawings, and information, in whole or in part in any manner and for any purpose whatsoever without compensation to or approval from the Contractor. The Government will at all reasonable times have the right to inspect the work and will have access to and the right to make copies of the above-mentioned items. All text, electronic digital files, data, and other products generated under this contract shall become the property of the Government. By reference, the following DFAR clauses are included in this contract as a part of the requirements herein:

a. DFAR 252.227-7013, "Rights in Technical Data - Noncommercial Items."

b. DFAR 252.227-7017, "Identification and Assertion of Use, Release, or Disclosure Restrictions."

c. DFAR 252.227-7020, "Rights in Special Works."

d. DFAR 252.227-7028, "Technical Data or Computer Software Previously Delivered to the Government."

e. DFAR 252.227-7037, "Validation of Restrictive Markings on Technical Data."

f. DFAR 252.227-7025, "Limitations on the Use or Disclosure of Government-Furnished Information Marked with Restrictive Legends."

g. DFAR 252.227-7014, "Rights in Noncommercial Computer Software and Noncommercial Computer Software Documentation."

SECTION 01 12 00.00 18 Page 3

1.7 GOVERNMENT-FURNISHED MATERIALS

The New York District CAD Standard, Cover and Border sheet model files shall be downloaded from this website:

http://www.nan.usace.army.mil/business/buslinks/contract/ae/index.htm.

The A/E/C CADD Standard shall be downloaded from this website:

https://cadbim.usace.army.mil/CAD.

1.8 RETAINAGE

Failure of the contractor to provide the associated design or construction documents in compliance with the New York District CAD Standard, will result in the following retainages. The retainage shall be released following the approval of the New York District CAD Standard compliant deliverables. These retainages reflect the cost to the Government to revise and correct the design or construction documents to bring them into compliance with the New York District CAD Standard:

All electronic submittals. $2,000 retainage shall be held from the contractor if electronic submittals are not in compliance with the provisions of paragraph titled DELIVERY MEDIA AND FORMAT above.

Final CAD submittal. $25,000 retainage shall be held from the contractor if CAD deliverables are not in compliance with the New York District CAD Standard.

Record ("As-Built") CAD submittal. $35,000 retainage shall be held from the contractor if record ("as-built") CAD deliverables are not in compliance with the New York District CAD Standard.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

SECTION 01 12 00.00 18 Page 4

SECTION 01 32 01.00 18

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Progress, Schedules, and Network Analysis Systems

ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanichal Systems in Construction

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 18 SUBMITTAL PROCEDURES:

SD-01 PreConstruction Submittals

Narrative Report; G, RO Schedule Reports; G, RO

Four copies of the reports showing numbers, descriptions, dates, float, starts, finishes, durations, sequences, etc., as required.

SD-07 Certificates

Qualifications Statement;

Documentation showing the qualifications of personnel preparing the reports.

SD-12 Schedules

Initial Project Schedule; G, RO Preliminary Project Schedule; G, RO Periodic Project Schedule; G, RO

Four copies of the schedules showing codes, values, categories, numbers, and other items, etc., as required.

SECTION 01 32 01.00 18 Page 1

1.3 QUALITY ASSURASNCE

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall have previously developed, created, and maintained at least 2 electronic schedules for projects similar in nature to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULES FOR CONSTRUCTION CONTRACTS and Section 00 80

00.00 18 Special Contract Requirements, paragraph 19 SCHEDULING AND DETERMINATION OF PROGRESS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design (if design-build projects) and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.

SubContractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The schedule must be a forward planning as well as a project monitoring tool.

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions, and to provide the basis of all progress payments. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

3.1.3 Default Terms

Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract.

SECTION 01 32 01.00 18 Page 2

Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 BASIS FOR PAYMENT AND COST LOADING

Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update or qualified scheduling personnel will result in an inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification and shall be capable of producing the Standard Data Exchange Format (SDEF) file discussed in ER 1-1-11. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule. Scheduling software that meets the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 are Primavera Project Planner (P3) or Primavera Project Management (P5) by Primavera, and Open Plan by Deltek. Manual methods shall not be utilized to produce any required information. The contractor shall be required to furnish to the Gov't the software scheduling program with one software license for the duration of this contract.

3.3.1 Critical Path Method

Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).

3.3.2 Level of Detail Required

With the exception of the initial and preliminary schedule submission, the Project Schedule shall include an appropriate level of detail. Failure to develop or update the Project Schedule or provide data to the Contracting Officer at the appropriate level of detail, as specified by the Contracting Officer, shall result in the disapproval of the schedule. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the Project Schedule:

3.3.2.1 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities

SECTION 01 32 01.00 18 Page 3 are defined herein.

3.3.2.2 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, deliver, installation and testing.

3.3.2.3 Mandatory Tasks

In addition to other activities as required to complete the project, the Progress Schedule shall include the following as separate line activities:

a. Submission and approval of O & M manuals.

b. Submission and approval of as-built drawings.

c. Contractor's pre-final inspection.

d. Correction of punchlist from Contractor's pre-final inspection.

e. Government's pre-final inspection.

f. Correction of punch list from Government's pre-final inspection.

g. Final inspection.

3.3.2.4 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.2.5 Workers Per Day

All activities shall have an estimate of the average number of workers per day that are expected to be used during the execution of the activity to produce the expected completion date. If no workers are required for an activity, in the case of activities related to procurement, for example, then the activitity shall be identified as using zero workers per day. The workers per day information for each activity shall be identified by the Workers Per Day Code.

3.3.2.6 Activity Responsibility Coding (RESP)

Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities

SECTION 01 32 01.00 18 Page 4 shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.

3.3.2.7 Activity Work Area Coding

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.

3.3.2.8 Contract Changes/Requests for Equitable Adjustment (REA) Coding

(MODF)

Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.

Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .