About this file
Amendment 0004 to Solicitation W912DS-09-B-0015.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIVIL WORKS TEAM
26 FEDERAL PLAZA
NEW YORK NY 10278-0090
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Revise SLIN 0002AM to incorporate 'VERNONIA NOVAEBORACENSIS' and reissue the Bid Schedule; and
3. Answ er the contractor question for INFORMATIONAL PURPOSES ONLY.
The Bid Due Date Remains unchanged at 17 SEP 2009 at 2PM EST.
NOTE: Bidder must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF 30, by separate letter, by telegram or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 33
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Sep-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-09-B-0015
X 9B. DATED (SEE ITEM 11)
07-Aug-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Sep-2009
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE E3H0610
FACILITY CODECODE
EMAIL:TEL:
W912DS-09-B-0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0004
W912DS-09-B-0015
Gerritsen Creek Solicitation
AMENDMENT 0004
1. The Bid Schedule is revised and reissued to reflect changes in SLIN 0002AM:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Base Bid
FFP
The Base Bid shall focus on the restoration and construction of the low and high marsh areas along Gerritsen and Mill Creeks. The restored low marsh areas will be between 0 - 2' NAVD88, and slope on a 1% grade up to the restored high marsh areas. The high marsh areas will fall between 2 - 2.9' NAVD88, and will abut with the transition slope areas (3 - 8' NAVD88). Both the high and low marsh areas will be graded on 3:1 to curtail the potential for Pharmites reinvasion.
Prior to any construction acitivities, the existing Phragmites will be sprayed with herbicide (by others).
FOB: Destination
NET AMT
0001AA 1 Lump Sum
MOBILIZATION AND DEMOBILIZATION
FFP
Furnishing and maintenance of services, equipment, and facilities & removal (as necessary), in accordance with the plans specifications.
0001AB 1 Lump Sum
MAINTENANCE/PROTECTION OF TRAFFIC
FFP
Maintenance and Protection of Traffic - Type "B" in accordance with the plans & specifications.
0001AC 167 Square
Yard
ANTI-TRACKING PAD
FFP
Labor, materials, equipment, installation, maintenance, removal, and restoring vegetations (as necessary) in accorance with the plans & specifications.
0001AD 1,107 Square
WORKSITE ACCESS ROAD
Labor, materials, equipment, installation, maintenance, removal, and restoring
0001AE 3,375 Square
STAGING AREA
Labor, materials, equipment, installation, maintenance, removal, and restoring
0001AF 1,273 Square
RESTORATION OF STREET PAVEMENT
Labor, materials, and equipment IAW plans & specifications.
0001AG 1 Lump Sum
SITE CLEARING
FFP
0001AH 65 Linear
Foot
DEMOLITION: LUMBAR GUIDERAIL
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AJ 2,494 Linear
DEMOLITION: NATURE TRAIL
Labor, equipment, & material removal and disposal in accordance with the plans & speicifcations
0001AK 1 Each
13'-6" SINGLE LINK GATE (6' HIGH)
FFP
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AL 1 Each
6'-6" CHAIN LINK GATE (6' HIGH)
FFP
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AM 1 Each
12' CHAIN LINK GATE (6' HIGH)
FFP
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AN 2,696 Linear
CHAIN LINK SECURITY FENCE (6' HIGH)
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AP 4,043 Linear
CONSTRUCTION FENCE
CONSTRUCTION FENCE (GRASSLAND PERIMETER CONTROL) Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AQ 94 Linear
COR-TEN STEEL BEAM BOX GUIDERAIL
Labor, materials, equipment, installation, maintenance, removal, & replacement of vegetation or pavement (as necessary) in accordance with the plans &
0001AR 10 Each
TRANSPLANTING TREES
FFP
Labor, materials, equipment, & installation in accordance with the plans & specifications
0001AS
DELETED BY AMENDMENT 0003
FFP
THIS SLIN IS DELETED IN ITS ENTIRETY BY AMENDMENT 0003
0001AT 16.40 Acre
HERBIVORY FENCE
FFP
Labor, materials, equipment, & installation in accordance with the plans &
0001AU 170,320 Each
LOW MARSH
FFP
LOW MARSH: SPARTINA ALTERNIFLORA: Labor, materials, equipment, & installation in accordance with the plans & specifications
0001AV 3,630 Each
HIGH MARSH
FFP
HIGH MARSH: DISTICHLIS SPICATA: Labor, materials, equipment, &
0001AW 3,630 Each
HIGH MARSH
FFP
HIGH MARSH: JUNCUS GERARDII: Labor, materials, equipment, &
0001AX 3,630 Each
HIGH MARSH
FFP
HIGH MARSH: SPARTINA PATENS: Labor, materials, equipment, &
0001AY 5,500 Linear
SILT FENCE
Labor, materials, equipment, installation, maintenance, removal & restoring vegetation (as necessary) in accordance with the plans & specifications.
0001AZ 167 Square
FILTER FABRIC - STABILIZATION
Labor, materials, and equipment IAW plans & specifications
0001BA 4,482 Square
FILTER FABRIC - SEPARATION
0001BB 85,579 Cubic
UNCLASSIFIED EXCAVATION & ROUGH GRADING
UNCLASSIFIED EXCAVATION & ROUGH GRADING IN GRASSLAND
AREAS. Labor, equipment, hauling & any necessary pumping or diversions IAW plans & specifications
0001BC 50 Linear
CONCRETE SIDEWALKS, CURBS, AND GUTTERS
OPTION OPTION Item No. 1
FFP
Option #1 incorporates the restoration of the upland coastal grassland community, implementation of a stormwater management system, and .
installation of recreational features.
The grassland areas will be overlain with the clean excavated sand material sourced from the low and high marsh areas in the Basic Contract to create a 30" sand layer. The 30" layer will be capped with 6 inches of clean imported sand fill, and graded prior to planting and seeding.
The herbivory fence shall remain in place for two full growing seasons to allow for establishment of the coastal grassland community.
The upland stormwater management system will consist of a network of swales, trench drains, lawn inlets, and culverts.
Recreational features shall include the realignment of the existing nature trail, reinstallation of park signs and benches, resetting of the rock boulders, and new photo point bollards and osprey nest platforms.
0002AA 1,247 Linear
OPTION DEMOLITION: NATURE TRAIL
Labor, equipment, & material removal and disposal IAW plans & specifications
0002AB 8 Each
OPTION REINSTALLATION OF PARK SIGNS
FFP
Labor, materials, equipment, installation & maintenance IAW plans &
0002AC 10 Each
OPTION REMOVAL AND INSTALLATION
FFP
REMOVAL AND INSTALLATION OF BACKLESS BENCHES. Labor, materials, equipment, installation & maintenance IAW plans & specifications.
0002AD 29 Linear
OPTION REMOVAL AND RESETTING
REMOVAL AND RESETTING OF EXISTING GUIDERAIL: Labor, materials, equipment, installation & maintenance IAW plans & specifications.
0002AE 63 Each
OPTION RESETTING OF EXISTING BOULDERS
FFP
Labor, materials, equipment, installation & maintenance IAW plans &
0002AF
OPTION DELETED BY AMENDMENT 0003
FFP
0002AG 7 Each
OPTION PERMANENT PHOTO POINT MONUMENTS
FFP
Labor, materials, equipment, installation IAW plans & specifications
0002AH 2 Each
OPTION OSPREY NEST PLATFORMS
FFP
Labor, materials, equipment, installation, maintenace IAW plans & specifications
0002AJ 1.10 Cubic
OPTION CONCRETE FOR BENCHES AND SIGNS
Labor, materials, equipment IAW plans & specifications
0002AK 5,476 Linear
OPTION NATURE TRAIL
0002AL
OPTION DELETED BY AMENDMENT 0003
FFP
0002AM 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
VERNONIA NOVAEBORACENSIS: Labor, materials, and equipment IAW plans & specifications.
0002AN 227 Cubic
OPTION AGGREGATE SURFACE COURSE (TRENCH DRAIN)
0002AP 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
EUPATORIUM HYSSOPIFOLIUM: Labor, materials, and equipment IAW plans & specifications
0002AQ 31,890 Each
OPTION TRANSITION/ GRASSLAND PLANTING
FFP
CAREX PENSYLVANICA: Labor, materials, and equipment IAW plans &
0002AR 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
ASCLEPIUS SYRIACA: Labor, materials, and equipment IAW plans &
0002AS 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
ASCLEPIAS TUBEROSA: Labor, materials, and equipment IAW plans &
0002AT 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
MONARDA FISTULOSA: Labor, materials, and equipment IAW plans &
0002AU 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
SOLIDAGO SEMPERVIRENS: Labor, materials, and equipment IAW plans &
0002AV 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
EUPATORIUM FISTULOSUM: Labor, materials, and equipment IAW plans &
0002AX 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
EUPATORIUM MACULATUM: Labor, materials, and equipment IAW plans &
0002AY 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
ASTER LAEVIS: Labor, materials, and equipment IAW plans & specifications.
0002BA 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
PANICUM VIRGATUM: Labor, materials, and equipment IAW plans &
0002BB 31,890 Each
OPTION TRANSPLANTING/GRASSLAND PLANTING
FFP
RUDBECKIA HIRTA: Labor, materials, and equipment IAW plans &
0002BC 31,890 Each
OPTION TRANSITION/GRASSLAND PLANTING
FFP
APOCYNUM CANNIBINUM: Labor, materials, and equipment IAW plans &
0002BD 16.60 Acre
OPTION GRASSLAND A SEED MIX
FFP
GRASSLAND SEED MIX (VARIOUS): Labor, materials, and equipment IAW plans & specifications.
0002BE 7.10 Acre
OPTION GRASSLAND B SEED MIX
FFP
GRASSLAND B SEED MIX (VARIOUS): Labor, materials, and equipment IAW plans & specifications.
0002BF 1.50 Acre
OPTION TRANSITION SLOPE SEED MIX (VARIOUS)
FFP
0002BG 1.70 Acre
OPTION MOW STRIP SEED MIX (VARIOUS)
FFP
0002BH 7,000 Linear
OPTION SILT FENCE
Labor, materials, equipment, installation, & maintenance IAW plans &
0002BJ 10 Each
OPTION INLETS, NJDOT TYPE A
FFP
0002BK 3,064 Linear
OPTION 8" PERFORATED PVC PIPE
8" PERFORATED PVC PIPE, TYPE PS46 (TRENCH DRAIN)
0002BL 125 Linear
OPTION 12" RCP (CROSS-DRAIN)
0002BM 252 Linear
OPTION 18" RCP (CROSS-DRAIN)
0002BN 2 Each
OPTION 12" CONCRETE FLARED END
FFP
0002BP 3 Each
OPTION 18" CONCRETE FLARED END
FFP
0002BQ 16 Cubic
OPTION EROSION CONTROL RIPRAP
0002BR 1,728 Square
OPTION FILTER FABRIC - DRAINAGE
0002BS 9,241 Square
OPTION FILTER FABRIC - SEPERATION
0002BT 27,290 Cubic
OPTION CLEAN SAND, IMPORTED
0002BU 23.50 Acre
OPTION FINAL GRADING
FFP
0002BV
OPTION DELETED BY AMENDMENT 0003
FFP
THIS SLIN WAS DELETED IN ITS ENTIRETY BY AMENDMENT 0003
0002BW
OPTION DELETED BY AMENDMENT 0003
FFP
THIS SLIN WAS DELETED IN ITS ENTIRETY BY AMENDMENT 0003
OPTION OPTION Item No. 2
FFP
Option Item No. 2
0003AA 5,000 Cubic
OPTION OPTION Item No. 3
FFP
Option Item No. 3
0004AA 10,000 Cubic
OPTION Item No. 4
FFP
Option Item No. 4
0005AA 23.80 Acre
OPTION TEMPORARY SEEDING
FFP
TOTAL
TOTAL OF BASE CLINS (0001): $___________________
TOTAL OF OPTIONS (CLIN 0002 - 0005): $___________________
TOTAL OF BASE PLUS OPTIONS (0001-0005): $___________________
NOTES FOR PRICE SCHEDULE:
CLIN (Contract Line Item Number) is the same as “Item No”
1 Bidders are required to bid on both the Base Bid Items and the Optional Items on the Price Schedule or their bid will be rejected.
2 The low bidder for the purpose of award will be the conforming responsible bidder offering the lowest amount for the Total Base Bid & Optional Items. The Government is under no obligation to award any Optional Item.
3 Any bid which is materially unbalanced as to the price for the Base Bid Item and Optional Item may be rejected. An unbalanced bid is one, which is based on price significantly less than the cost for some work and prices are significantly overstated for other work.
4 The government may award all the optional bid Items at the time of award of the basic contract.
Exercise of options is at the discretion of the government and not guaranteed. The Government is under no obligation to award any Option
5 Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidders thereto may render the bid non-responsive and be cause for its rejection.
6 Option 1 may be awarded within 100 calendar days from issuance of the Notice to Proceed date and no additional time will be added to the contract duration.
7 Option 2 and 3 may be awarded within 200 calendar days from issuance of the Notice to Proceed date and no additional time will be added to the contract duration.
8 Option 4 may be awarded within 100 calendar days from issuance of Notice to Procedd date and no additional time will be added to the contract duration, this option will not be awarded if Option 1 is awarded.
2. The following question has been answered for INFORMATIONAL PURPOSES
ONLY:
a. Question: Q&A #7 for Addendum #3 states that EUPATORIUM HYSSOPIFOLIUM & VERNONIA NOVAEBORACENSIS were added to the bid item list however only EUPATORIUM HYSSOPIFOLIUM was. Please advise on how we are to proceed with cost allocation of the missing landscaping item VERNONIA NOVAEBORACENSIS.
Response: CLIN 0002AM has been revised to add VERONIA NOVAEBORACENSIS to the Bid Schedule with a quantity of 31,890.
(End of Summary of Changes)