This amendment modifies a solicitation for the Dalecarlia Clearwells Maintenance project. The scope of work involves upgrades and improvements to two clearwells and connecting conduits at the Dalecarlia Water Treatment Plant, including upgrades to drain lines, rehabilitation of sluice gates, installation of new flow meters and mixers, and improvements to the clearwell overflow structure. Mold remediation and HVAC upgrades are also required for an adjacent building. Bids are due electronically by 11:00 AM EST on October 23, 2020 and will be opened at 11:30 AM EST via a public conference call. The solicitation requests pricing for upgrades to the 15 MG and 30 MG clearwells and associated work. The awarded contractor must complete work on the 30 MG clearwell between November and April before beginning work on the 15 MG clearwell.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of amendment is to make changes to the Price Schedule, Scope of Work, Attachment A - Specifications, as w ell as addiding a additional site visit. Changes are marked in red. Please see the continuation page for additional information. All other terms remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Oct-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR20B0020

X 9B. DATED (SEE ITEM 11)

23-Sep-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Oct-2020

CODE

U.S ARMY CORPS OF ENGINEERS

2 HOPKINS PLAZA 03-B-07

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR20B0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been modified:

NOTES TO BIDDERS

Offerors must bid on all items. Failure to bid on all items may be cause for rejection of the proposal.

PRICE SCHEDULE

PART I - THE PRICE SCHEDULE

SECTION 00010 - SUPPLIES OR SERVICES AND PRICES

PRICE SCHEDULE – REVISED

Item No. Description Amount

0001 All costs in connection with the new multi-path acoustic flow $__________ meter in the venturi of the conduit between the two Clearwells, the new sample drain system and the rehabilitation of Sluice

Gates 13 - 19, complete as shown on the drawings and as specified.

0002 All costs in connection with the 15 MG Clearwell including the $__________ selective demolition, re-grading, storm water pipe assessment and cleaning, new sluice gate, waterproof membrane installation, drainage chamber and valves, and structural modifications complete as shown on the drawings and as specified.

0003 All costs in connection with the 30 MG Clearwell including the $__________ selective demolition, re-grading, storm water pipe assessment and cleaning, sluice gate rehabilitation of gates 1-12 per Sheet

M-105, drainage chamber, baffle wall and outfall modifications, crack repair, and mixing chamber equipment installation complete as shown on the drawings and as specified.

0004 All costs in connection with the Visitor Center Basement and $__________

Theater repair and modifications, including installation of various Environmental control equipment, waterproofing, and mold remediation, structural and finishing repairs, complete as shown on the drawings and as specified.

TOTAL BID AMOUNT $____________

SCOPE OF WORK

Scope of Work

The Washington Aqueduct provides potable water to approximately one million people in the District of Columbia and Northern Virginia. As part of the water treatment and supply system, the Washington Aqueduct maintains and operates the Dalecarlia and McMillan Water Treatment Plants (WTPs). At the Dalecarlia WTP, two Clearwells are used for final chemical treatment, disinfection, and storage of water before it is pumped to the distribution system.

The 15 million gallon (MG) Clearwell is approximately 25 feet deep. It was constructed in the 1920s and rehabilitated in 2000. The 30 MG Clearwell was constructed in the 1950s and rehabilitated in the 2000s; its approximate depth ranges between 20’ and 50’. Both Clearwells are covered by about 2’ feet of soil and topped with grass cover.

The project consists of implementing upgrades and improvements to these Clearwells and their connecting conduits to include: upgrades to their drain lines to eliminate potential cross connections, rehabilitation and replacement of large sluice gates, installation of new flow meters and induction mixers, improvements to the Clearwell overflow structure, chemical analyzer drain pipe re-routing and soil drainage improvements Both Clearwells are critical in maintaining adequate supply and quantity of water, so outage periods are restricted. The timing of outages must be coordinated with lower seasonal demands and sequenced so that only one Clearwell is out of service at a time. Finally, mold remediation and HVAC upgrades will be required in a building adjacent to the 15 MG Clearwell. Hence, an experienced contractor with resources and expertise to handle the following project constraints is needed:

i. The Clearwell roof surfaces have limited weight restrictions and the 30 MG Clearwell work must be completed between November and April. This work, including and testing the mixers and flow meters, must completed before work within the 15 MG Clearwell can begin.

ii. The demolition and re-building of brick buildings must be done within a limited outage window during the winter months when the reservoir is out of service.

iii. Access into the Clearwells and connecting conduit is limited and all work therein is considered confined space work.

iv. When working in the Clearwells, the Contractor will be required to pump continuously to minimize the impact of water from leaking sluice gates.

v. The Maryland/DC border crosses through the project site. Therefore, the Contractor must be prepared to implement and maintain Erosion and Sediment Control measures from both jurisdictions.

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS

VIRTUAL BID OPENING SOLICITATION INSTRUCTIONS

Due to COVID-19 health concerns, bids submitted in response to this solicitation will be submitted electronically.

The bid opening will be conducted via a telephone conference call that is open to the public.

Electronic Bid Submission

WHAT - Bids shall be submitted electronically, as described. The bid shall not contain classified data. The use of hyperlinks in bids is prohibited.

NOTE: The only authorized transmission method for bids in response to this solicitation is electronically via SAFE online submission. NO OTHER TRANSMISSION METHODS (E- MAIL, FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.) WILL BE ACCEPTED.

WHEN - Bids must be submitted not later than the time designated for bid submission. Bid opening and bid submission times are detailed below. Bids submitted after the bid submission time will be considered late bids.

Bids shall be submitted no earlier than five (5) calendar days before bid opening.

BID SUBMISSION TIME: 11:00 AM EST on 23 OCT 2020

Bids must be received by the Government by the date/time specified in the solicitation.

HOW - Bidders shall electronically send their bids using the following link:

https://safe.apps.mil/

WHO - The SAFE site will require contacts for bid submission to be provided. All requests for information and the bid submission must be sent to BOTH of the below contacts to ensure timely receipt of bids. Please use the following contact information to submit bids:

Contract Specialist: Airron Wiggins at Airron.D.Wiggins@usace.army.mil Contracting Officer: Mark Ryan Andrews at Mark.R.Andrews@usace.army.mil

BIDDERS MUST REQUEST AN UPLOAD LINK: Bidders must e-mail the Contract Specialist and Contracting Officer no later than five (5) working days prior to the bid opening date to receive a request LINK which will allow for file uploads via the SAFE site. Bidders that fail to request a LINK at least five (5) working days before bid opening date may not be able to receive a request code in time to upload their bids.

SUBMISSION FORMAT: Submission shall be in Adobe PDF format. You are limited to five (5) maximum files per upload (total size cannot exceed 2GB). If you have a large number of files, recommend that you combine or ZIP your files before uploading to the SAFE site. Bidders may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.

BID GUARANTEE: This solicitation requires submission of a bid guarantee in accordance with FAR 52.228-1.

Electronic bid submissions must include a scanned copy of the original bid guarantee. In addition, the original bid guarantee with “wet” signature and raised seal (if applicable) must be mailed to the address below and received by the bid opening time and date:

U.S. Army Corps of Engineers 2 Hopkins Plaza c/o Contracting Division: Mark Ryan Andrews Baltimore, MD 21201

Minor discrepancies in receipt of the original bid guarantee due to COVID-19 related impacts may be waived solely at the discretion of the Contracting Officer. A scanned copy of the original bid guarantee must be included in the electronic bid submission for the bid to be considered responsive.

FILE DESCRIPTION: Include a “File Description” for each file you upload. The “File Description” will be included in the e-mail notice to each of the recipients you choose to have access your file(s). NOTE: Do NOT enter Privacy Act Data (Personal Identification Information (PII)) in the File Description.

INSTRUCTIONS TO FOLLOW ON THE SAFE WEBSITE:

1. Once at the SAFE website, select the “Drop-off” icon. This allows users without a Common Access Card (CAC, an ID issued to certain Government users), or users whose computer is not configured to read a CAC the option to access the SAFE site as a guest.

2. After selecting the “Click Here” link, you will be prompted to add your personal information, file information, recipient (Government points of contact) information and e-mail settings.

3. When completing your file information, you will be required to enter the e- mail addresses for all recipients. For this solicitation, the recipients are the Contract Specialist and the Contracting Officer, listed above. Although the e- mail address of the Government employee who initiated the request code will be automatically entered, this address may not be correct. The Bidder must enter and add the e-mail addresses for both the Contracting Officer and Specialist listed above to the Recipient List. The Bidder can enter an additional e-mail address if desired. After entering the e-mail address, click the ADD button to add the e-mail to the “Recipients List” for your response. When your bid is submitted, a notification will be sent to the selected recipients.

NOTE: Do NOT send the SAFE site packages to group e-mail accounts.

Even if you successfully upload your bid to the SAFE site, notification will not be sent to the Government recipients until you verify your e-mail address. Entering an incorrect e-mail may result in the rejection of your submission for lateness. A Bidder can confirm proper submission by the ‘Drop-Off Completed” screen which generates based on proper file submission.

NOTE: It has been reported that documents are more quickly uploaded into the SAFE website when using a Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Bidders will have more success utilizing any particular browser.

TIMELINESS OF BIDS:

For the purposes of establishing whether a bid submission is considered timely, the Government considers the date and time the submission is completely uploaded into the SAFE website. For bids larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases.

The Government will not be responsible for bids delivered to any location or to anyone other than those designated to receive bids. Bidders are responsible for ensuring that bids are submitted so as to reach the designated recipient.

Bidders are responsible for allowing sufficient time for the bid to be received in accordance with the instructions provided.

Bid Opening

Bids will be opened within 30 minutes after the time for bid submission noted above. This 30 minute delay is necessary to allow for downloading and to allow for technical delays. No Government officials will open electronic documents until the Independent Government Estimate is finalized and received by the Bid Opening Official.

BID OPENING TIME: 11:30 AM EST on 23 OCT 2020

The bid opening will be conducted via public conference call. Bidders and members of the public may use the below information to access the conference call:

Call In Number: 888-675-2535 Access Code: 8210313 Security Code: 1234

During the bid opening, the Bid Opening Official will read the bid totals in the order received electronically. The Bid Opening Official will then read the line item prices and total for each submission. The Contract Specialist will record the bid opening results, which will be posted to www.beta.SAM.gov as quickly as practicable following the bid opening.

In accordance with FAR 14.402-1(c), interested persons may examine the bids after the bid opening. Interested persons may contact the Contract Specialist identified above following the bid opening to request an electronic copy of the bid(s). Please be considerate of limited Government resources and request bid copies only as necessary.

To preserve conference line stability, bidders are asked to limit the number of individual calls to the conference line to the minimum needed for participation. The bid opening will proceed as scheduled even if individual bidders or members of the public are not able to access the telephone line at the bid opening time. Any interested party may access the results of the bid opening on www.beta.SAM.gov shortly after the bid opening.

Additional Information:

a. SF 1442 BACK (Page 2 of the Solicitation): Offerors are required to acknowledge the receipt of all amendments to the Solicitation on the Standard Form 1442 in Block 19. Offerors shall fully complete all the required areas located under the section designated as “OFFER” (refer to Items 14 through 20C).

b. BID GUARANTEE: The bidders are required to submit a Bid Guarantee for this procurement. Any bidder failing to submit an authentic Bid Guarantee will be considered non-responsive to the Solicitation and ineligible for award.

The Bid Guarantee shall be in the amount of 20% of the bidder’s price or $3,000,000.00, whichever is less.

c. BONDS AND INSURANCE: The Contractor will be required to furnish proof of insurance, including copies of the required endorsements, and performance and payment bonds within 10 calendar days following the Contractor’s receipt of the contract award.

Requests for information:

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 12 OCT 2020 at 11:00 AM EST. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.

Current Quick Add Key is: FF8F4R-UD496V

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

Responses to RFIs via ProjNet are for informational purposes only. Official responses will be provided by amendment.

****** NOTE: QUESTIONS ANSWERED IN PROJNET ARE NOT OFFICIAL UNTIL AN AMENDMENT IS

ISSUED. ***

SECTION 00 72 00 - GENERAL CONDITIONS

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $759.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

LIST OF ATTACHMENTS

ATTACHMENTS:

Attachment A: Drawings Attachment B: Specifications Attachment C: Standard Form LLL Attachment D: EFT Form Attachment E: Certificate of Corporate Authority Form

(End of Summary of Changes)