Amendment No. 0002 RFI Questions and Answers.pdf
PDF 210 KB Posted
- Attached to
- W912DR20B0020 Dalecarlia Clearwells Maintenance
- Solicitation number
- W912DR20B0020
About this file
This document summarizes questions and answers related to a federal contract solicitation for maintenance upgrades at two water treatment plant clearwells. The solicitation seeks rehabilitation of large sluice gates, installation of new flow meters and induction mixers, improvements to clearwell overflow structures, and chemical analyzer drain pipe re-routing. It also involves mold remediation and HVAC upgrades in an adjacent building. The work must be sequenced to only take one clearwell out of service at a time due to their critical role in water supply. Outages are restricted to lower seasonal demand periods. The Washington Aqueduct and Army Corps of Engineers Baltimore District are the agencies managing this project to upgrade infrastructure at the Dalecarlia Water Treatment Plant clearwells.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contracting Officers Report Closed Inquiries
Project: Dalecarlia Clearwells Maintenance and Improvements Review: RFI Responses (00001) (sorted by CommentID ) Displaying 31 inquiries.
Id Discipline Sheet Detail Spec 8841585 General General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm the price range of $2,000,000M - $5,000,000M.
By: Candice Geter; W.M. Schlosser Company, Inc.; (240-455-1498). On: Sep 24 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation Concurred. Confirmed. By: Mark Andrews; Contracting Division; (4435258229) On: Sep
25 2020 1-1 Government Response. Confirmed. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 12
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8846664 General 00 41 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The eight page Bid Schedule (Document 00 41 00 from specbook) is completely different from the two page Price Schedule from the Solicitation. Which is correct?
(Attachment: Pricing.pdf) By: Candice Geter; W.M. Schlosser Company, Inc.; (240-455-1498). On: Sep 28 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation For Information Only. Please refer to Amendment No. 1 for an updated Price Schedule.
By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020 1-1 Government Response. Please refer to Amendment No. 1 for an updated Price Schedule. By: Mark
Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8850416 Electrical 0 0 Comment Classification: UNCLASSIFIED (U)
Will a Plan Holders list and a site visit sign in sheet be supplied to allow subcontractors the ability to bid the General Contractors.
By: Daniel Teague; Gracon LLC; (970-667-2203). On: Sep 30 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation Concurred. Yes, the site visit sign-in sheet(s) will be posted via amendment. By: Mark
Andrews; Contracting Division; (4435258229) On: Oct 12 2020 1-1 Government Response. Yes, the site visit sign-in sheet(s) will be posted via amendment. By: Mark
Andrews; Contracting Division; (4435258229) On: Oct 12 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8852132 Construction Phasing 01 14 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 1 of 10ProjNet: Logged In User
10/16/2020https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminClosed...
Specification section 01 14 00 paragraph 1.2 states the Contractor must perform work on the 30 MG Clearwell first and this work must be complete between November 1 and March 1. The timeframe for procurement of the sluice gates and EMO's (4-6 weeks for submittals, 14 days for Owner review, and 16-20 weeks casting, machining, & testing) is insufficient to allow this work to be complete by March 1, 2021. It is not possible to expedite the procurement to meet the Owner's 2021 work schedule. The timeframe for holding Contractor's bids (120 days) plus the overall contract duration (332 days) is insufficient to allow the 30 MG Clearwell work to be performed starting November 1, 2021 followed by 21 days of testing and 10 weeks for the 15 MG Clearwell work. Please increase the overall project duration to allow the appropriate time for award, submittals, procurement, and construction to begin on the 30 MG Clearwell in November 2021. A Contractor has no mechanism for entitlement post bid to claim there is inadequate time due to procurement delays and it would be irresponsible for a Contractor to bid a job knowing procurement of critical elements cannot occur within the specified timeframe.
By: Brad Gribble; Maverick Construction; (4432626554). On: Oct 01 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation For Information Only. Overall Contract Duration shall be extended to 362 calendar days.
The Owner has accommodated for an additional outage of the 30 MG Clearwell and revised the sequencing requirements as described within an upcoming Amendment of specification Section 01 14 00, Work Restrictions. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. Overall Contract Duration shall be extended to 362 calendar days. The Owner has accommodated for an additional outage of the 30 MG Clearwell and revised the sequencing requirements as described within an upcoming Amendment of specification Section 01 14 00, Work Restrictions. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8857100 Mechanical H-102 Note 8 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 8 on drawing page H-102 states that drawings of the existing HVAC system will be made available upon request. We request these drawings to assist in the estimating of the work.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 06 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation For Information Only. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 07 2020
2-0 Evaluation Concurred. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 12 2020
2-1 Government Response. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 12 2020
2-2 Government Response. This new text supercedes ALL previous replies.
This answer will be updated. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 13 2020
2-3 Government Response. This new text supercedes ALL previous replies.
Due to security concerns record drawing will be provided to the low bidder at the time of award. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8858730 Mechanical Mechanical Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
What material is the existing ductwork located in the Visitor's Center constructed of?
By: Candice Geter; W.M. Schlosser Company, Inc.; (240-455-1498). On: Oct 07 2020. Forward request by email.
1-0 Evaluation For Information Only. The ductwork in the Visitor's Center Basement was installed between 2002 and 2004. Site inspection indicates this ductwork to be of galvanized steel construction. Note to be
Page 2 of 10ProjNet: Logged In User added via forthcoming Amendment. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 14 2020
1-1 Government Response. The ductwork in the Visitor's Center Basement was installed between 2002 and 2004. Site inspection indicates this ductwork to be of galvanized steel construction. Note to be added via forthcoming Amendment. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8858734 Mechanical Mechanical Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Cleaning the existing ductwork in the Visitor's Center will require cutting the existing insulation/mastic. Has a HAZMAT survey been preformed on the existing Ductwork insulation?
By: Candice Geter; W.M. Schlosser Company, Inc.; (240-455-1498). On: Oct 07 2020. Forward request by email.
1-0 Evaluation For Information Only. The ductwork and insulation in the Visitor's Center Basement was installed between 2002 and 2004. Site inspection indicates the insulation to be of fiberglass material. A HAZMAT survey has NOT been performed on the existing ductwork insulation By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. The ductwork and insulation in the Visitor's Center Basement was installed between 2002 and 2004. Site inspection indicates the insulation to be of fiberglass material. A HAZMAT survey has NOT been performed on the existing ductwork insulation By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8858909 Mechanical M-101 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Sluice gate work:
1. Regarding gates 3,4,6 and 8, confirm that replace refers to the wedges only and that there is no other refurbishment.
2. Is a full plant shutdown necessary at any time for the gate work? For instance how are gates 18 and 19 isolated for inspection?
3. Should we assume in bidding that the existing gates are fully functional and capable of controlling flow with minimal leakage?
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 07 2020. Forward request by email.
1-0 Evaluation For Information Only. 1. Confirmed.
2. No total plant shutdown is allowed. The Contractor shall plan to run at least two 6" pumps continuously to handle leakage from the existing sluice gates. Gate 18 can be inspected on the downstream side during the 30mg clearwell outage; Gate 19 can be inspected during the 15mg clearwell outage.
3. Gates that require refurbishments are listed on the Drawings. The Contractor shall plan to run at least two 6" pumps continuously to handle leakage from the existing sluice gates. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. 1. Confirmed.
2. No total plant shutdown is allowed. The Contractor shall plan to run at least two 6" pumps continuously to handle leakage from the existing sluice gates. Gate 18 can be inspected on the downstream side during the 30mg clearwell outage; Gate 19 can be inspected during the 15mg clearwell outage.
3. Gates that require refurbishments are listed on the Drawings. The Contractor shall plan to run at least two 6" pumps continuously to handle leakage from the existing sluice gates. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8858911 Civil M-101 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Clearwell cleaning:
Removal of lime sediment is indicated in one small area of the 30mg clearwell. Other areas of the work may have lime sediment. Is the Corps going to clean the rest of the 30mg and the 15mg clearwell so the work can be
Page 3 of 10ProjNet: Logged In User performed?
Confirm that the lime sediment can be discharged into the sewer.
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 07 2020. Forward request by email.
1-0 Evaluation For Information Only. It is not the Contractor's responsibility to remove sediment except in the indicated area at the 30MG influent area to the southwest as delineated on M-101. Other areas may need sediment to be moved (but not removed) to facilitate completion of work. Removed sediment must be disposed at a landfill that accepts this type of waste material. Discharging back into the sewer will not be allowed. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. It is not the Contractor's responsibility to remove sediment except in the indicated area at the 30MG influent area to the southwest as delineated on M-101. Other areas may need sediment to be moved (but not removed) to facilitate completion of work. Removed sediment must be disposed at a landfill that accepts this type of waste material. Discharging back into the sewer will not be allowed. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8859789 General S113 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Can you please provide the record drawings discussed in note 2 of sheet S-113 so the contractor can better understand the required travel path between FRP panels in the 30 MG Clearwell.
In addition to above, we request any asbuilts be provided for the 15 MG clearwell.
By: Brad Gribble; Maverick Construction; (4432626554). On: Oct 08 2020. Forward request by email.
1-0 Evaluation For Information Only. Record drawings will not be provided during the bidding phase of the project. The baffle locations in their entirety are illustrated on sheet M-101. Specific work locations are as stipulated on Sheet S-113. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. Record drawings will not be provided during the bidding phase of the project.
The baffle locations in their entirety are illustrated on sheet M-101. Specific work locations are as stipulated on Sheet S-113. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8860857 Civil C-104 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide a specification for the 48" flap gate
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 08 2020. Forward request by email.
1-0 Evaluation For Information Only. Flap gate to have materials as stated in Section 33 11 00, subpart
2.1.2.4, and to be flat-back style with minimum 10-ft opening head. By: Andy Rankin; River to Tap, Inc.
(R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. Flap gate to have materials as stated in Section 33 11 00, subpart 2.1.2.4, and to be flat-back style with minimum 10-ft opening head. By: Mark Andrews; Contracting Division;
(4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8860864 Mechanical M-101 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide an as-built of the 30mg clearwell gatehouse sluice gates. (lower level-only upper level was provided)
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 08 2020. Forward request by email.
1-0 Evaluation For Information Only. No separate as-built plans will be provided. Upper and lower (bottom) plans of existing and proposed conditions are provided on Sheet M-104 and also Sheet S-112. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1
Page 4 of 10ProjNet: Logged In User
Government Response. No separate as-built plans will be provided. Upper and lower (bottom) plans of existing and proposed conditions are provided on Sheet M-104 and also Sheet S-112. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8860870 Structural M-107 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
M-107 (one example) shows a portable hoist. There is no specification. Are these hoists provided by the Corps? If not, how many are required?
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 08 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation For Information Only. Loading specifications are provided on S-111. Additional material and performance specifications have been added to Spec Section 05 50 13 via forthcoming Amendment. By:
Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. Loading specifications are provided on S-111. Additional material and performance specifications have been added to Spec Section 05 50 13 via forthcoming Amendment By:
Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8860873 Mechanical M-102 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please clarify note 1. We interpret that the wall thimble is to remain. Please confirm.
By: Richard Norair; Norair Engineering Corp; (3014992202). On: Oct 08 2020. Forward request by email.
1-0 Evaluation For Information Only. The intent is for only the embedded wall thimble to remain. The rest of the gate will be removed. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 13 2020
1-1 Government Response. Text: The intent is for only the embedded wall thimble to remain. The rest of the gate will be removed. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864264 Mechanical M-101 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
If as-builts of existing gates (and wall thimbles) are not available or provide inadequate information for ordering gates, (Part A) please advise if the clearwells can be dewatered for gate inspection before ordering gates.
If dewatering is not allowed prior to ordering gates, a flange adaptor plate can be cast onto the back of the gates which allows for drilling a bolt pattern after the casting. However, this method results in the stem being shifted approx. 4" further from the face of the wall, requiring a new roof penetration. (Part B) Please advise if installing new roof penetrations is allowed should flange adapter plates be required.
By: Brad Gribble; Maverick Construction; (4432626554). On: Oct 12 2020.
Requires Amendment.
Forward request by email.
1-0 Evaluation For Information Only. An additional clearwell outage has been added as stipulated in a forthcoming Amendment. Please refer to revised Section 01 14 00, WORK RESTRICTIONS. The Contractor shall verify all sluice gate measurements prior to shop drawing fabrication. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. An additional clearwell outage has been added as stipulated in a forthcoming Amendment. Please refer to revised Section 01 14 00, WORK RESTRICTIONS. The Contractor shall verify all sluice gate measurements prior to shop drawing fabrication. By: Mark Andrews; Contracting Division;
(4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Page 5 of 10ProjNet: Logged In User
Information for this report is procurement sensitive.
8864265 General 01 14 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the work hours be expanded beyond those listed in 1.6.2 during the 10 week outage periods? We request that the work hours be unrestricted during the outages.
By: Brad Gribble; Maverick Construction; (4432626554). On: Oct 12 2020. Forward request by email.
1-0 Evaluation For Information Only. As stated in the specifications, if the Contractor wishes to work outside of the regularly scheduled hours, a written request must be provided to the Government for consideration. The Government will consider extended work hours provided adequate manpower is available. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. As stated in the specifications, if the Contractor wishes to work outside of the regularly scheduled hours, a written request must be provided to the Government for consideration. The Government will consider extended work hours provided adequate manpower is available. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864271 Mechanical M-108 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please advise at what elevation or location the ammonia piping transitions from stainless steel hard pipe to the hose assembly provided by the mixer manufacturer.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. The transition shall occur in the Built Up Hatch vault beneath davit crane at around Elev. 142.00, as shown on on detail 5, S-111 By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. The transition shall occur in the Built Up Hatch vault beneath davit crane at around Elev. 142.00, as shown on detail 5, S-111 By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864272 Mechanical M-108 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please provide the wall thickness of the existing ammonia feed pipe, along with any coating that the pipe has applied to it.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. Existing pipe is 1" schedule 40 stainless steel pipe. Contractor to match existing coating system for new 50' of installed pipe. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. Existing pipe is 1" schedule 40 stainless steel pipe. Contractor to match existing coating system for new 50' of installed pipe. By: Mark Andrews; Contracting Division; (4435258229) On:
Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864273 Mechanical M-108 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please advise if the ammonia feed will be shut down and drained by the Owner in order for the contractor to perform their work.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0
Page 6 of 10ProjNet: Logged In User
Evaluation For Information Only. Yes, as the 30 MG Clearwell is being drained, the ammonia feed system will be simultaneously shut down and drained by the Government. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. Yes, as the 30 MG Clearwell is being drained, the ammonia feed system will be simultaneously shut down and drained by the Government. By: Mark Andrews; Contracting Division;
(4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864274 Civil C-104 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm the existing concrete culvert that the new flap gate is mounted to on the 30 M gallon clearwell is 48" in diameter, or provide the dimensions if it is not.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. Record drawings indicate that the overflow pipe is 48" concrete.
Contractor to field verify all dimensions. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 13 2020
1-1 Government Response. Record drawings indicate that the overflow pipe is 48" concrete. Contractor to field verify all dimensions. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864275 Mechanical M-103 n/a 33 11 00 2.1.2.1.c Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
M-103 calls "for 30" motorized gate valve (Typ of 2)", but 33 11 00 2.1.2.1.c calls for handwheel operators.
a. Please clarify what type of operator is required.
b. If the valves are to be motorized, please specify what the operational and electrical specifications are.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. New valves to have electric motor actuators and handwheel operators for backup. Actuators are described in 40 95 00, Process Control, subpart 2.4.5. Additional electrical descriptions are provided in table on E-101. This will be clarified in upcoming Amendment. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. New valves to have electric motor actuators and handwheel operators for backup. Actuators are described in 40 95 00, Process Control, subpart 2.4.5. Additional electrical descriptions are provided in table on E-101. This will be clarified in upcoming Amendment. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864276 Mechanical M-104 n/a 33 11 00 2.1.2.1.c Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please advise if the new gate valves shown on M-104 are to be manually operated or electrically actuated.
a. If the gates are to be electrically actuated, please specify the operating and electrical specifications.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. New valves to have electric motor actuators and handwheel operators for backup. Actuators are described in 40 95 00, Process Control, subpart 2.4.5. Additional electrical descriptions are provided in table on E-101. This will be provided in upcoming Amendment. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. New valves to have electric motor actuators and handwheel operators for backup. Actuators are described in 40 95 00, Process Control, subpart 2.4.5. Additional electrical descriptions are provided in table on E-101. This will be provided in upcoming Amendment. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Page 7 of 10ProjNet: Logged In User
Information for this report is procurement sensitive.
8864277 Civil C-103 Note 4 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 4 on C-103 discusses earth cover of 2' on clearwell, can you provide drawings showing details of the backfill, the clearwell structure, and/or what is the top of the clearwell elevations?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. No additional drawings will be provided. The clearwell roof slopes approximately 3" per 100ft with a top of concrete elevation of 145.4 ft at the north end of the clearwell and a top of concrete elevation of 146.5 ft at the south end of the clearwell. Note 4 describes the 2 ft maximum backfill height limit for the entire clearwell roof. Existing and proposed grade elevations are provided on sheet C-103. Note to be added via upcoming Amendment. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.)
- Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. No additional drawings will be provided. The clearwell roof slopes approximately 3" per 100ft with a top of concrete elevation of 145.4 ft at the north end of the clearwell and a top of concrete elevation of 146.5 ft at the south end of the clearwell. Note 4 describes the 2 ft maximum backfill height limit for the entire clearwell roof. Existing and proposed grade elevations are provided on sheet C-103. Note to be added via upcoming Amendment. By: Mark Andrews; Contracting Division;
(4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864278 Structural M-104 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
M-104 references crack repair – approximately how much crack repair is required and what types of repairs are needed?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. It is approximated that 10 gallons of crack injection epoxy is required to repair cracks in the walls and slab of the drainage chamber. The size and extent of cracks could not be confirmed due to the depth of water level at the time of inspection, but will need to be assessed prior to installation. Note will be added via upcoming Amendment. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.)
- Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. It is approximated that 10 gallons of crack injection epoxy is required to repair cracks in the walls and slab of the drainage chamber. The size and extent of cracks could not be confirmed due to the depth of water level at the time of inspection, but will need to be assessed prior to installation. Note will be added via upcoming Amendment. By: Mark Andrews; Contracting Division;
(4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864279 Mechanical M-106 & M-108 n/a n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Can you provide detail drawings for the metal conduit extension shown on M-106 and M-108?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. No additional detail drawings exist for the Existing metal conduit extension that is to be removed. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 14 2020
1-1 Government Response. No additional detail drawings exist for the Existing metal conduit extension that is to be removed. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864280 Mechanical H-102 Note 3 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Page 8 of 10ProjNet: Logged In User
How thick is the insulation on the existing ductwork that is to be replaced?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. Site investigation has revealed the existing insulation to be 2" thick, nominal. Replacement insulation thickness shall be in accordance with Section 23 07 00. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 13 2020
1-1 Government Response. Site investigation has revealed the existing insulation to be 2" thick, nominal.
Replacement insulation thickness shall be in accordance with Section 23 07 00. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864281 Structural S-121 Note 7 & 8 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
How much drywall is to be installed/replaced based on notes 7 and 8 on S-121?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. It is estimated that a total of 200 sq.ft. is required to be replaced.
By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. It is estimated that a total of 200 sq.ft. is required to be replaced. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864282 Structural S-121 Note 4 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
How much underslab is to be repaired with repair mortar per note 4 on S-121?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. Approximately 5 cu.ft. is required. Additional specification information has been provided within Section 03 01 00, REHABILITATION OF CONCRETE, via addendum for further clarification related to repair mortars. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA;
(7705697038) On: Oct 14 2020
1-1 Government Response. Approximately 5 cu.ft. is required. Additional specification information has been provided within Section 03 01 00, REHABILITATION OF CONCRETE, via addendum for further clarification related to repair mortars. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864283 Structural s-122 Note 1 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
How many conduit penetrations are there to be repaired per Note 1 on S-122?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. Approximately 20 conduit penetrations (+/- 3" conduits) through the walls need epoxy. Repairing around the conduit through the wall and floor with approximately 5 cu.ft. of mortar repair material. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On:
Oct 14 2020
1-1 Government Response. Approximately 20 conduit penetrations (+/- 3" conduits) through the walls need epoxy. Repairing around the conduit through the wall and floor with approximately 5 cu.ft. of mortar repair material. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864284 Structural S-121 & S-122 Section A n/a
Page 9 of 10ProjNet: Logged In User
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
How much replacement of the chase wall is there per Section A on S-122/121?
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. It is estimated that a total of 200 sq.ft. is required to be replaced.
By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. It is estimated that a total of 200 sq.ft. is required to be replaced. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
8864285 Electrical C-102 & E-001 Note 11 & Note 13 n/a Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Note 11 on C-102 is requiring the 2" sample line to be insulated but not heat traced. Note 13 on E-001 calls for exposed lines 2" and below to be heat traced but there are no circuit details for this. Is this line to be heat traced? If so, please provide details.
By: Brandon Lumm; American Contracting & Environmental Services, Inc.; (4433671624). On: Oct 12 2020.
Forward request by email.
1-0 Evaluation For Information Only. No heat tracing is required for the 2" sample line indicated on C-102 as this flow stream is continuous at all times. The line shall be insulated as required. By: Andy Rankin; River to Tap, Inc. (R2T, Inc.) - Atlanta, GA; (7705697038) On: Oct 14 2020
1-1 Government Response. No heat tracing is required for the 2" sample line indicated on C-102 as this flow stream is continuous at all times. The line shall be insulated as required. By: Mark Andrews; Contracting Division; (4435258229) On: Oct 16 2020 Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete