Chart 2 Revised 10-26-10.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
MAES Set-Aside for 8(a), HUBZone and SDVOSB Business Classes Federal contract opportunity
Solicitation number
W912DR-10-R-0107
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

Amendment 10 - Attachment G-1

View the file

Other files for this federal contract opportunity

Other files attached to MAES Set-Aside for 8(a), HUBZone and SDVOSB Business Classes, newest first.
File Type Posted
Amendment 10 - Cost.pdf PDF
Amendment 0009 Clarification.pdf PDF
Attachment C Hypothetical Scenario revised 9-7-10.docx DOCX document
Attachment E Chart 1A revised 09-07-10 keb.docx DOCX document
Attachment A Schedule B revised 8-31-10.docx DOCX document
Attachment D Service Contractor Data Information Sheet 9-7-10 kEB.docx DOCX document
Amendment 0008 9-10-10.pdf PDF
Attachment A Continuation of Schedule B revised 09-07-10 keb.xls XLS spreadsheet
Attachment F CHART 1b revised 09-07-10 keb.docx DOCX document
Attachment G Chart 2 revised 09-07-10 keb.docx DOCX document
Attachment K- 2 Questions and Answers 09-07-2010.docx DOCX document
W912DR-10-R-0107 0007.pdf PDF
Attachment D Pre-Award Survey 8-13-10.docx DOCX document
Amendment 0006 8-20-10.pdf PDF
Attachment J - Questions and Answers 8-13-10.doc DOC document
Attachment J Questions and Answers for MAES SDVOSB 7-7-10.docx DOCX document
Amendment 0005 Conformed RFP 8-17-10.pdf PDF
Amendment 0005 Modification 8-17-10.pdf PDF
Attachment E Chart 1A.docx DOCX document
Attachment D Pre-Award Survey.docx DOCX document
Attachment A Continuation of Schedule B.xls XLS spreadsheet
Attachment F CHART 1b.docx DOCX document
Attachment A Schedule B.docx DOCX document
Attachment I ACH EFT form.docx DOCX document
Attachment B PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
Attachment C Hypothetical Scenario.docx DOCX document
Attachment H Lobbying Form.pdf PDF
Attachment G Chart 2.docx DOCX document
Amendmenrt No 4 8-03-10.pdf PDF
10-R-1017 Amendment 0003 7-1-10.pdf PDF
10-R-0107 Amendment 2 6-22-10.pdf PDF
09-R-0107 Amendment 0001.pdf PDF
10-R-0107 RFP 6-7-10 FBO.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chart 2 Chart 2

Multiple Award Environmental Services
Direct Labor by Job ClassificationPrime/JV (1)% UTIL (2)SUB #1 (1)% UTIL (2)SUB #2 (1)% UTIL (2)Project Composite Rate
1Principal
2Senior PM
3Junior PM
4Senior Engineer
5Junior Engineer
6Safety Engineer
7Senior Mechanical Engineer
8Junior Mechanical Engineer
9Senior Electrical Engineer
10Junior Electrical Engineer
11Senior Civil Engineer
12Junior Civil Engineer
13Senior Sanitary Engineer
14Junior Sanitary Engineer
15Senior Structural Engineer
16Junior Structural Engineer
17Chemical Engineer
18Geotechnical Engineer
19Environmental Engineer
20Architect
21Soil Engineer
22Construction Manager
23Engineering Technician
24Laborer
25Landscape Architect
26Cost Estimator
27Cost Accountant
28Budget Analyst
29Safety and Health Manager
30Industrial Hygienist (certified)
31Senior Geologist
32Junior Geologist
33Senior Geophysicist
34Junior Geophysicist
35Senior Scientist
36Junior Scientist
37Senior Hydrogeologist
38Junior Hydrogeologist
39Senior Geochemist
40Junior Geochemist
41Senior Chemist
42Junior Chemist
43Certified Lab Technician
44Lab Technician
45Analytical Chemist
46Professional Planner
47Spec Writer
48Senior Biologist
49Junior Biologist
50Senior Environmental Scientist
51Junior Environmental Scientist
52Certified Health Physicist
53Health Physicist
54Regulatory Specialist
55Site Safety & Health Officer
56Senior UXO Supervisor(SUXOS)
57UXO Safety Officer (UXOSO)
58UXO Quality Control Specialist (UXOQCS)
59UXO Technician III
60UXO Technician II
61UXO Technician I
62UXO Sweep Personnel
63UXO Project Manager
64Quality Control Manager
65Illustrator/Draftsperson
66Computer Scientist/Operator
67Technician (General)
68Computer Technician
69Administrative Assistant
70Secretary
71Clerical

&"Times New Roman,Regular"&12Solicitation W912DR-10-R-0098, Attachment G-1, Continuation of Schedule B, 10-26-10

&P

Instructions for Chart 2

The Composite Rates are intended to represent the anticipated hourly cost to the Government for each discipline listed below. The Composite Rate represents a combination of the fully burdened prime and subcontractor rates that the offeror anticipates using for each labor category over the life of the contract. The Composite Rates included in Schedule B will be the binding burdened labor rates for the life of the contract, exclusive of profit. Profit should NOT be included in the Composite Rates. Profit will be negotiated on a task order basis

Offerors will provide fully burdened hourly labor rates for the prime and all team/key subcontractors.

The fully burdened hourly labor rates for the prime contractor shall be provided for each discipline identified in Chart 2 and should be entered in the column labeled “Prime/JV (1).” This rate should include the base hourly labor rate, overhead, G&A, all payroll taxes, insurance, fringe benefits, and all markups, exclusive of profit. Profit will be negotiated on a task order basis.

The fully burdened hourly labor rates for all team/key subcontractors shall be provided for each discipline identified in Chart 2 and should be entered in the column labeled “SUB #1” and “SUB #2” (if more than one team/key subcontractor is proposed). This rate should include the base hourly labor rate, overhead, G&A, all payroll taxes, insurance, fringe benefits, and all markups (including the prime contractors anticipated markup on the labor rate),but exclusive of profit. Profit will be negotiated on a task order basis.

For each labor category listed in Chart 2, the offeror must estimate the percentage of anticipated utilization of employees from the prime contractor and all team/key subcontractors. These estimates should be included in the “%UTIL” columns as appropriate. For example, if the offeror anticipates that it will use its own Principle on about 40% of the task orders awarded under this contact and will use its subcontractor’s Principle on about 60% of the task orders awarded under this contract, those values should be identified in the “%UTIL” column as appropriate.

Show the percentages using its % format instead of a decimal format. Round all percentages to the nearest three decimal places.

Do not round to the next even dollar. Round only to the nearest cent.

To calculate the Composite Rate for each for discipline identified, the offeror shall calculate the sum of the following:

(Prime (1) x %UTIL anticipated) + (SUB#(1) x %UTIL anticipated) = Composite Rate

Example:

Principle Labor Category

Rate for Prime/JV Contractor for Principle - $150.00
Rate for Team/Key Subcontractor #1 for Principle - $125.00
Anticipated Utilization of Principle from Prime -30%
Anticipated Utilization of Principle from Subcontractor - 70%

($150.00 x .30) + ($125.00 x .70) = $132.50 = Composite Rate for Principle

The Composite Rates as calculated in Chart 2 will be entered into Schedule B and escalated for the four additional performance years. These rates will serve as the binding rates for the life of the contract.