clarification_to_responses-1.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Installation Operations, Maintenance, and Sustainment Federal contract opportunity
- Solicitation number
- W912D0-18-R-0002
About this file
Clarification to Responses
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Clarifications to Responses | ||||
| Reference | QUESTION | ORIGINAL RESPONSE | RESPONSE | |
| Reference question #56 | Is “Contract Start Date” the first full day of performance for the new contract, given as 1 Nov 2018 in Base Year CLINs, or is it the first day of the Phase-In Period, 1 Sep 2018? | The contract start date is 1 Sep 18. | The contract start date is 1 Sep 2018 |
Reference question #141 Please clarify which is correct and what is the actual day of the “contract start date”? The correct end date should be 31 Oct 18 and it is now corrected. The contract start date is 1 Sep 2018. 31 Oct 2018 is the end of the "Phase-In" Period
RFP W912D0-18-R-0002 Amendment 0001, Page 8, SECTION F - and Attachment J13, page 35, C.1.9.6, Quality Control Plan C.1.9.6 Quality Control Plan, states, “The plan shall be implemented and be completely in effect by Contract phase-in start date.” Since the incumbent contractor is still responsible for full performance during phase-in, should this be … by Contract start date? Yes, the contract start date is 1 Sep 2018
RFP W912D0-18-R-0002 Amendment 0001, Page 8, SECTION F - and Attachment J13, C.1.12.1 Hazardous materail and Management C.1.12.1 Hazardous Material and Waste Management, states, “The Contractor shall prepare and submit appointment orders to the COR within ten working days prior to Phase-In start date.” Should this be ten working days prior to the contract start date? Yes, 10 ten prior to contract start date which is 1 Sep 2018.
Attachment J13 PWS Amendment 1, Page 62 Page 62, defines Phase-In Period as “The period between Contract Award and Contract start date.” When will the Government issue the conformed RFP? The Government posts Amenments in the modification format to show exact changes in the solicitation. The Government does not intend to post the Conformed RFP. The definition for "Phase-In Period" in Attachment J13, PWS has been revised to clarify the definition.