Amendment_0006_-_Specification_Section_Revisions.pdf

PDF 119 KB Posted

Attached to
Floating Plant Electrical and Electronic System Support IDIQ Federal contract opportunity
Solicitation number
W912BU19R0002
Issued by
Department of the Army Corps of Engineers Engineering District Philadeplhia

About this file

Revised Spec Sections

View the file

Other files for this federal contract opportunity

Other files attached to Floating Plant Electrical and Electronic System Support IDIQ, newest first.
File Type Posted
Amendment_0008.pdf PDF
Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
361-M150-A001_-_Jadwin_-_Machinery_Arrangement_-_Pump_and_Winch_Rooms.pdf PDF
Dredge_JADWIN_Hauling_Winch.pdf PDF
Dredge_JADWIN_Hoist_Winch_Arrangement.pdf PDF
Amendment_0002.pdf PDF
361-H240-C006 - Hoist and Hauling Winch Fdn.pdf PDF
Hoisting Winch Retrofit Dredge JADWIN Prints.pdf PDF
Dredge JADWIN IO Points List.pdf PDF
361-G255-02 - DREDGE_CONSOLE ARRT.pdf PDF
Dredge JADWIN Hauling Winch Manual.pdf PDF
Amendment_0001.pdf PDF
Dredge JADWIN Ladder Hoist Winch Rigging Block System.pdf PDF
361-M700-C002 - Electrical Cable Schedule.pdf PDF
C1026 - MDC # 2101 - Jadwin - Pneumatic Brake & Clutch Control - Hull# 361.tif TIF image
Dredge Jadwin Arc Flash Hazard Analysis.pdf PDF
Dredge JADWIN Monitoring System Retrofit.pdf PDF
361-M710-C001 - Machinery Space Electrical Power Deck Plans.pdf PDF
361-M700-C001 - Electrical One-Line Diagram.pdf PDF
Hauling Winch DV 300 Retrofit Dredge JADWIN.pdf PDF
Dredge JADWIN Pilothouse Upgrade Electrical.pdf PDF
703-B725-01 REV-2 AC VOLTAGE DROP & CABLE SCHEDULE.xlsx XLSX spreadsheet
W912BU19R0002.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C001A.B.4 – AC ELECTRIC MOTOR

The new ladder hoist winch motor shall be suitable for marine application and sized and designed for continuous operation at rated capacity. The motor shall be designed, constructed, and installed in accordance with ABS Rules and shall be ABS approved. The motor shall be provided with grease fittings and shall have positive means for preventing grease from being forced out upon the motor windings.

The motor will be exposed to the weather and therefore shall have IP-56 (watertight or weather tight) protection. The motor shall have class “H” insulation with a class “F” temperature rise rating based on a 50 degree C ambient temperature.

Anti-condensation space heaters shall be provided for the motor. Motor space heaters shall be powered from 120-VAC control power of the drive and shall be energized whenever the motor is secured and de-energized whenever the motor is operating. All space heaters shall be provided with an “ON”-“OFF”-

“AUTO” selector switch and indicating light on the drive.

C001A.B.13.b - FACTORY ACCEPTANCE TESTING

The Contractor shall perform factory acceptance testing (FAT) for the complete winch system (motor, drive, gearbox, and winch) at the manufacturer’s facility. The Contractor shall perform testing to demonstrate the winches rated capacity at rated line speed at the outermost layer of the winch drum, and a brake test to demonstrate the operation of the braking system at rated capacity. The Contractor shall also demonstrate the full safety braking capacity of the dynamic braking feature with power loss to the winch.

The Contracting Officer shall have the option of witnessing the FAT. The Contracting Officer or his

Representative shall be notified at least 10 (ten) working days prior to the scheduled test date.

C001A.C.4 – AC ELECTRIC MOTOR

The motors will be exposed to the weather and therefore shall have IP-56 (watertight or weather tight) protection. The motors shall have class “H” insulation with a class “F” temperature rise rating based on a

50 degree C ambient temperature.

Anti-condensation space heaters shall be provided for both motors. Motor space heaters shall be powered from 120-VAC control power of the motor controller and shall be energized whenever the motor is secured and de-energized whenever the motor is operating. All space heaters shall be provided with an “ON”-

“OFF”-“AUTO” selector switch and indicating light on the drive.

The Contractor shall provide all engineering and materials required to adapt and install the new motors to the existing hauling winches.

The vessel crew will perform all work to install the new motors on to the existing hauling winches.

L.2 – Proposal Submission Requirements

a. Each volume shall be submitted in a separate binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page.

The revised pages shall be dated. Each binder shall be clearly labeled with its Title and a copy number (e.g., copy 1 of 5).

b. The following volumes of material shall be submitted:

PRINTED DIGITAL MAXIMUM

VOLUME TITLE COPIES COPIES PAGES

I – Technical/Risk Original 1 70

II - Past Performance Original 1 N/A

III – Price Original 1 N/A

NOTE: Pages that exceed the required page limitations will not be evaluated. Additional pages over the maximum allowed will be removed or not read and will not be evaluated by the Government. All pages will be counted except for the abridged sample of a testing plan and Operations & Maintenance Manual provided for a similar project which is required in Volume I, Tab 4b.

File details come from the government source that posted it.