This solicitation seeks proposals for construction services for an aircraft maintenance hangar at Dover Air Force Base, Delaware. Key details include that the project scope involves construction of an 84,176 square foot single bay hangar facility with office, maintenance, and support spaces. The contract value is estimated between $25-100 million. The contract type is firm-fixed-price with options. The NAICS code is 236220 and small business size standard is $36.5 million. There is no set-aside. The basis for award is best value. Proposals are due April 5, 2019. The site visit is scheduled for March 1, 2019. Interested parties must register at FedBizOpps to access solicitation documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 18R0026_Dwgs-AM2.pdf | ||
| 18-R-0026_DAFB_AMH_Pre-proposal_Site_Visit_Attendance_Roster.pdf | ||
| 18R0026_Specs-AM1R1.pdf | ||
| D_Elec10.pdf | ||
| D_Civ2.pdf | ||
| D_Structural4.pdf | ||
| RFI_Format.pdf | ||
| D_Civ3.pdf | ||
| D_Int6.pdf | ||
| D_Fire7.pdf | ||
| D_Arch5.pdf | ||
| D_Tel11.pdf | ||
| 18R0026-SpecsVol1-RTA.pdf | ||
| D_Plum8.pdf | ||
| D_Gen1.pdf | ||
| D_Mech9.pdf | ||
| 18R0026-SpecsVol3-RTA.pdf | ||
| 18R0026-SpecsVol2-RTA.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Extend the proposal due date from 3:00 PM 5 April, 2019 until 3:00 PM on 15 April, 2019;
2. Section 00 21 00 - Remove Clauses 52.225-9 and 52.225-10, and add Clauses 52.225-11 and 52.225-12;
3. Provide responses to the industry questions.
Please indicate receipt of this amendment on Standard Form 30 (AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT) as Amendment No. 0002. Failure to acknow ledge all amendments may result in your proposal being deemed unresponsive
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BU18R0026
X 9B. DATED (SEE ITEM 11)
19-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Mar-2019
CODE
CONTR DIV-CONTRACTS BR
USACE, PHILA DISTRICT
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
e5ct9ep9 Typewritten Text e5ct9ep9 Typewritten Text x e5ct9ep9 Typewritten Text
W912BU18R0026
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by reference: 52.225-12
The following have been added by full text:
52.225-11 BUY AMERICAN--CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT
2016)
(a) Definitions. As used in this clause--
Caribbean Basin country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
14. DESCRIPTION OF AMENDMENT (continued)
4. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0002, are attached to this amendment.
a. SECTION 00 22 00 – PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION CRITERIA
b. SECTION 00 73 46 – WAGE RATES
c. TECHNICAL SPECIFICATIONS:(1) Section 07 41 13 – METAL ROOF PANELS:
(2) Section 11 24 29 – FALL PROTECTION
(3) TABLE OF CONTENTS VOLUME 2 OF 3
(4) Section 21 30 00 – FIRE PUMPS
(5) Section 26 35 43 – 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER:
(6) Section 31 62 13.28 – RAMMED AGGREGATE PIER FOUNDATIONS
(7) Section 33 16 20 – GLASS LINED FIRE SUPPRESSION WATER TANK AND APPURTENANCES
d. CONTRACT DRAWINGS:
(1) Please delete the drawings FX001, S-502, and S-503 in their entirety and substitute the revised drawings, of the same drawing numbers, with the latest revisions dates of 25 March 2019, attached hereto.
5. Delete and Replace the following Sections
6. Delete and Replace the following Clauses
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4)such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St.
Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
Least developed country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
“Free Trade Agreement country construction material” means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
“Least developed country construction material” means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that--
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate ``none'']
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that--
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1:
Foreign construction material Domestic construction material Item 2:
Foreign construction material Domestic construction material \1\ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
The following have been deleted:
52.225-10
(End of Summary of Changes)
Amendment No. 0002
RFP W912BU-18-R-0026
RFI # Discipline Dwg Sheet/ Spec Section Comment Official Response
1 General Spec 00 22 00 Please consider revising the project experience to include additional projects other than aircraft hangers such as schools, maintenance facilities, police stations, etc.
Prepare proposal per the solicitation.
2 Electrical 26 35 43 Para 1.1 Does not list compliance with IEC 60947-4-1 which is a standard listed in Guide Spec UFGS 26 35 43 dtd 02/2018.
Refer to amended specification section 26 35 43.
3 Electrical 26 35 43 Para 1.1 Does not list compliance with NEMA ST20 which is a standard listed in Guide Spec UFGS 26 35 43 dtd 02/2018.
Prepare proposal per the solicitation.
4 Electrical 26 35 43 Para 1.1 Does not list compiance with UL 506 which is a standard listed in Guide Spec UFGS 26 35 43 dtd 02/2018.
Refer to amended specification section 26 35 43.
5 Electrical 26 35 43 Para 1.3 SD-07 Certificates Indicates SASO Equivolent which is a Saudi Standards Metrology and Quality Organization. Suggest reference to SASO be deleted.
Refer to amended specification section 26 35 43.
6 Electrical 26 35 43 Para 1.4.7.2
UL LISTING
Paragraph from the Guide Spec allowing "Proposed Listed Product" has ben removed even though the Guide Spec doesn't allow. Recommend reinserting Paragraph 1.4.7.2 Proposed Listed Products.
Refer to amended specification section 26 35 43.
7 Electrical
26 35 43 Para 2.1.1.16 Phase Angle Regulation
Paragraph 2.1.1.16 from the Guide Spec describing Phase Angle Regulation of the converter output is not in the job specification. Recommend it be included as it describes a performance parameter critical to the aircraft acceptance of the converter power output.
Refer to amended specification section 26 35 43.
8 Electrical
26 35 43 Para 2.1.3.3 Digital
Instrumentation THD Metering is described in the last sentence. Recommend it be deleted as it is no longer required with UFGS 26 35 43 dtd 02/2018.
Prepare proposal per the solicitation.
9 Electrical 26 35 43 Para 2.1.5 Protective Controls
Door interlock described in the Guide Specification does not appear in this job specification. Recommend the SAFETY FEATURE be included.
Refer to amended specification section 26 35 43.
10 Electrical
26 35 43 Para 2.1.6 Automative Line Drop
Compensation
The current guide spec limits automatic line drop compensation -0 to7 % adjustable internally. Considerations are being made to increase this parameter to a maximum limit of 10% but also citing concerns of impact on regulation if beyond 10% is allowed.
Recommend changing the maximum limit to 10% rather than the published 16% especially in view of an external line drop compensator being provided in the electrical lineup.
Refer to amended specification section 26 35 43.
11 Electrical 26 35 43 Para 2.1.6 a, b,c,d,e Paragraph sub-items have nothing to do with Line Drop Compensation.
Prepare proposal per the solicitation
12 Electrical
Guide Spec 26 35 43 Paragraph 2.1.10 Built
In Test Equipment Recommend inserting this requirement as it is a standard industry practice and an aid to troubleshooting procedures.
Refer to amended specification section 26 35 43.
13 Electrical
Guide Spec 26 35 43 Paragraph 2.1.12
Acoustic Noise Recommend inserting this requirement at 72 dBA which is the value being considered.
Prepare proposal per the solicitation.
14 Electrical
Guide Spec 26 35 43 Paragraph 2.1.4
Nameplates Recommend requiring OEM Nameplate data be required to ensure origin of equipment and assurance it is the same origin as the test data and submittals.
Refer to amended specification section 26 35 43.
15 Electrical Drawing E-503
Hangar 400 hertz receptacles are rated for 200v, 3 phase, 30 amp, 400 hertz however the frequency converter feeding the hangar receptacles via Panel FCPP1 is rated 90 kva providng 260 amps of power. Recommend the receptacles be upsized to match the output capacity of the frequency converter.
Prepare proposal per the solicitation.
Refer to Electrical plan sheets and E- 001 for additonal information.
16 Electrical Drawing E-503 Can you provide a source or a better description of the three 400 hertz 30 amp switch and plug assemblies and the qty one 400 hertz panel and cord assembly?
Prepare proposal per the solicitation.
Refer to Specification section 26 35 43 for 400 HZ converter requirements.
REQUESTS FOR INFORMATION with RESPONSES Solicitation No. W912BU-18-R-0026
17 General General
In order to provide the USACE with the most competitive pricing possible, would the USACE consider allowing for Volume 2 Price Proposals to be submitted electronically via email and/or waive the requirement to provide CDs with the Volume 2 Price Proposal at time of bid? It is typical for major subcontractors to hold their pricing until the last few hours prior to the bid date and time and if we are required to submit hard copies accompanied with CDs, we will not be able to include the subcontractor pricing which comes in just prior to the bid date and time.
Prepare proposal per the solicitation.
18 General General
Would the USACE reconsider not allowing the past performance of subcontractor teaming partners? It is unlikely that any of the General Contractors who may have applicable prime past performance will be self-performing the critical work and instead will be subcontracting all critical work. As such, if a General Contractor can provide a letter of commitment from a qualified subcontractor, will that subcontractor past performance be considered for evaluation? It would seem that allowing subcontractor teaming partner performance would be preferential to the USACE as then the USACE could verify that the subcontractors who will be self-performing the work are qualified.
Prepare proposal per the solicitation.
19 General General
If a contractor receives a rating of Not-Relevant for all past performance projects submitted in the proposal, would it still be possible to be awarded the project based on favorable reviews of price and all other factors in the technical proposal?
If all past performance is determined to be "Not-Relevant", this would be considered a "deficiency" as defined in Section 00 22 00 and therefore unawardable.
20 Earthwork 31.62.13.28
Section 1.3 - states that installers be approved by a competing installer (Geopier Foundation Company, Inc) with a vested interest in who is allowed as an alternate installer. This requirement, among other requirements in the specification, make it proprietary in nature. Please provide a non-proprietary specification written without regard or preference to an individual installer or a parent or affiliated company.
Revised Specification section
31.62.13.28 issued by amendment.
21 Structural SB111 SB111, Hangar piers are designated along CL 1 at A, B, C, D and E. Pier designations are not given for columns along .9 line. Please provide.
Refer to revised S- 502 and S-503 issued by amendment.
22 Structural 09 97 13.27
Section 09 90 00, 1.10.1.2 notes that all exposed columns, girders, beams, joists and metal deck are to be painted. Section 3.2 of 09 97 13.27 notes all primary and secondary steel framing inside the aircraft maintenance bay is to follow the 3-coat high performance painting system spelled out in section 2.3. Section 2.3 also notes that the 3 coat system must be applied in the field. Drawing S-001, Note S-18.A says the structural steel is to follow the three coat painting system in Division 09, but is silent on open web joists and metal deck. 05 12 00, 2.7.2 only calls for a zinc rich shop primer on the structural steel, with all connections and erection abrasions field primed per
3.5.1. 05 21 00, 2.5 calls for shop priming the joists. 05 30 13, 2.3.4.2 references a primer for metal decks. There is substantial cost to some of the items referenced above, and we want to be perfectly clear on what the Gov'ts requirements are for painting in the Hangar Bay. Industry standard would be to have manufacturer's provide a shop applied white primer to the steel, metal joists, and metal deck. There is a very large price increase to install a 3-coat high performance system on each one of those items. Please confirm if the structural steel needs the 3-coat system in 09 97
13.27 or just the shop primer in 05 12 00. Please confirm if the open web joists need the 3-coat system in 09 97 13.27 or just the shop primer in 05 21 00. Please confirm if the metal decking needs the 3-coat system in 09 97 13.27 or just the shop primer in 05 30 13. If any of the components need the 3-coat high performance system, please confirm if the coating can be shop applied by a SSPC QP 3 shop (as this often provides better quality than shop prepping per 2.3 and then trying to field apply the 3 coats of finish paint 60-90' in the air, all while trying to administer the requirements of 3.4 and
3.8 at the top of the hangar bay). Field connections and any areas affected by erection would be touched up using SSPC SP-1 and SP-2 procedures.
Structural steel shall be coated with the 3 coat system specified in 09 97
13.27. Open web
joists are to be shop primed per specification 05 21 00 and metal decking shop primed per spec section 05 30 13.
23 Contracting Contract Clauses
The solicitation contains FAR 52.225-9/10, Buy American - Construction Materials. We regularly see FAR 52.225-11/12, Buy American - Construction Materials Under Trade Agreements allowed on similar procurements, including recent solicitations at Dover AFB. Please confirm that FAR 52.225-11/12 can be incorporated into this solicitation.
Revised per amendment.
24 Contracting 00 73 46
The Davis-Bacon wage decision included in the specifications is DE10, which is for Heavy Civil work. Please confirm if this wage table should be DE07, which is for Building work in Kent County, DE?
Revised wage rates issued by amendment.
25 Contracting Warranty
Specification 07 41 13, 1.8.3 calls for a 5 year contractor warranty; but the attachment in the back of the spec is asking for a 20 year no penal sum warranty on the metal roof from the Contractor and Manf. It is industry standard to get a 20 year manufacturer's warranty on the roof, but not from the Contractor as well. If the Contractor has to co-sign, they will ask their bonding company to procure the warranty, and most bonding companies will only co-sign up to 5 years, at an added expense to the project. Please confirm the Contractor is only responsible for a 5 year warranty per 1.8.3 (and the Gov't will still get a 20 year warranty from the MFR per 1.8.1 and 1.8.2)
Revised per amended specification section 07 41 13.
26 General General We request a bid date extension of two weeks. We need more time soliciting, finding, and convincing small businesses to bid the project.
Refer to amendment for current proposal due date.
27 General General
We request a RFI due date extension of two weeks. Subcontractors will not look at project and get into the details until about 10 days before the bid date. Extending the RFI due date will help in limiting the amount of change orders during the construction of the project.
Refer to amendment for current proposal due date.
28 Civil N/A Please provide clarification regarding where excess dirt and topsoil should be hauled and stockpiled on base.
Per Section 31 00 00 paragraph 3.19 excess soil shall be disposed of on the project iste at location determined by the Contracting Officer.
29 Civil N/A Please confirm that waste such as asphalt and concrete are to be hauled off base.
Confirmed. Refer to Section 01 11 05 para 1.7 and Section 01 74 19 in the original solicitation.
30 Civil N/A Please confirm there is no requirement for undercutting and replacing any subgrades.
Prepare proposals in accordance with the solicitation.
Refer to specification section 31 00 00 and the Geotech Report.
31 Civil 33 40 00
The drainage utility specs list ADS / HDPE as a material in addition to the RCP. Profiles on drawings show RCP. Please confirm ADS or HDPE is an approved material we can use.
Prepare proposals in accordance with the soliciation.
32 Civil C-003 Existing Condition - Note 7 states: "Testing is required for all excess soil to be removed from the base." Please clarify what type of testing is required.
Testing of excess soil to be in accordance with Specifications 01 57 25 and 02 61 10
33 Civil C-003
Utility Structure - Note 1 states: "All utility structures are to be H-20 rated unless indicated otherwise. All airside utility structures are to be aircraft rated for single wheel loading of 45,000 pounds." Please confirm this is a requirement of this project.
Confirmed.Prepare proposals in accordance with the soliciation.
34 Civil VD-100
There are two structures pointed out that state: "Building outline of previous hangar.
Foundations and other building remains may be encountered." Please clarify what we are to assume needs to be demoed here. Without clarification this note will lead to great variance in pricing from each general contractor.
Per the solicitation, the proposal shall assume that remains of foundations may be encountered.
35 Civil CS-101 There is "Post and Cable Fence" shown. Is this fencing suppose to be K-Rated? If so, what K-rating should it be?
Post and cable fence to be constructed according to drawings and specifcations provided.
36 Structural S-001
Structural Steel - Note S-18, Part A states: "Structural Steel unless indicated otherwise, to be shop cleaned per SSPC SP3 and painted one shop coat of primer…" Please confirm that shop primer is acceptable. Please confirm that SSPC SP3 shop cleaning is acceptable.
Shop Primer is acceptable. SSPC SP3 Shop cleaning is acceptable.
37 Structural SB-111 Is the trench drain grating aircraft rated? If so, what is the rating?
Per detail 10/P-501 grate has a DIN rating of F.
38 Structural A-503
Detail 5/A-503 shows 3 1/2" rigid insulation at the exterior wall condition. This is not shown on the structural drawings. Please clarify if this is required. If so, how far back on the slab on grade does it go?
Per detail 5/A-503, extend 3-1/2" Rigid insulation 4'-0" into slab area.
39 Fire Protection FX001 / 213000.2.2
The specifications call out the pump sizing of 1500 GPM at 260 PSI. Fire protection Drawing FX001 calls out the sizing to be 2500 GPM at 215 psi. Please confirm the desired size of the fire pumps.
Provide an appropriately sized fire pump for a fully functioning foam system based on contractor performed calculations, that meet the requirements outlined by the design drawings and specifications.
40 Fire Protection
FX001/211313.2.5/211
317.2.4.1
Are pressure reducing valves acceptable on the sprinkler systems to alleviate the excess pressure so that standard fittings and sprinkler heads can be used if the water supply is adequate?
Pressure reducing valves are permitted on the sprinkler system.
41 Fire Protection C-512
Due to the fact that the feed from the water storage tanks runs underground (minimum of 4’0” cover), a portion of the water supply will not be able to be used.
Example, If the pipe is buried 4’0” below grade the bottom 4’ of water depth will not be used. If the pipe is buried 5’ below grade, the bottom 5’ of water depth will not be usable, etc. The fire pumps are not suction pumps and must have positive head to achieve flow. Once the level in the tank reaches a level above grade equal to what the pipe is buried below grade the pumps will not be receiving positive head and will not be able to supply water any longer. Please confirm the sizing of the water storage tanks as shown on Drawing C-512 has taken this fact into consideration.
Prepare proposal in accordance with the solicitation.
42 Fire Protection 213000.2.2
The fire protection specifications call out the motor speed for the fire pumps to be 2100 RPM. Diesel fire pumps are only available in this motor speed. The specifications call out electric fire pumps. They are only available in 1850RPM and 3500RPM motor.
Refer to amended specificaiton section 21 30 00.
43 Fire Protection FX401
The Civil plans size the incoming fire water pipes as 16”. The Fire Pump Room plans (FX401) appear to show 10” or 12” pipe coming into the building, but it is not labeled.
Please confirm the incoming sizing of fire protection pipe.
Per the civil plans in the solicitation, the incoming fire water lines are confirmed to be 16".
44 Fire Protection 20 13 20.00 20 -2.10.1 Does the site have the availability to replenish the foam tanks within 24 hours or will the contractor be responsible for providing a reserve supply on site?
Fire water tanks shall be refilled within 24 hours from existing base water supply. Refer to CU-series of drawings.
45 Fire Protection 20 13 20.00 20 -3.5.7 Please confirm that the contract will not be required to retain and removal the discharged foam solution.
Concur - No containment infrastructure or pumping is required. Foam discharge clean up is achieved via evaporation and rinsing of the hangar bay to industrial or sanitary waste.
46 Fire Protection FA111 through FA115
The FA series drawings depict the locations and quantities of the proposed flame detectors. The manufacturer of the flame detectors (Det-tronics) has provided a conflicting layout and quatity of detectors. Typically the manufacturer's design supercedes the contract drawings. Please clarify how you would like us to proceed.
Prepare proposal in accordance with the solicitation. The successful offeror will be required to submit manufacturer's design for acceptance.
47 Technical 00 22 00
Please confirm 3 projects for Volume I - Factor I – Management, Sub-Factor D - Experience (5.4.1) and 3 projects for Volume I - Factor II – Past Performance (6.1) are a minimum requirement.
Provide 3 projects per the RFP.
Additional projects will not be evaluated.
48 Technical 00 22 00
Please confirm that projects submitted under Volume I - Factor I- Management, Sub- Factor D – Experience (5.4.1) shall be the same projects submitted under Volume I – Factor II Past Performance (6.1).
The same project may be submitted for both Experience and Past Performance. Refer to amended Section 00 22 00.
49 Technical 00 22 00
If projects submitted under Volume I - Factor II - Past Performance (6.1) are the same projects utilized under Volume I - Factor I -Management, Subfactor D - Experience (5.4.1) please confirm that information for projects submitted under Volume I - Factor II, Past Performance can be incorporated by reference rather than submitting duplicate Project Detail Sheets included in Section 00 22 00 Attachments.
Yes as long as all information required in the RFP is provided. Refer to amendment.
50 Technical 00 22 00
Volume I - Factor II – Past Performance (6.1) requires two references and also identifies inclusion of any ratings, letters, awards, and PPQs. All of our relevant Federal Aircraft Hangar projects have a CPARS evaluation. Please confirm submitting the CPARS is acceptable in lieu of references and will not be included in the page count. (Typically CPARS are 4 pages in length and with at least 6 projects this would be 20 of the 75 pages.)
Refer to amendment. Overall page count is eliminated.
51 Technical 00 22 00
Please confirm that information submitted under Volume I - Factor III Small Business Participation Plan (7.1) is not included in the 75 pg. limit for the Technical Volume.
(Inclusive of the narrative and forms this plan can be nearly 20 pages in length.)
Refer to amendment. Overall page count is eliminated, however per 00 22 00 para
2.1 a concise proposal is required.
52 Technical 00 22 00
Please confirm that resumes submitted as part of Volume I - Factor I – Management, Sub-Factor A - Management Plan (5.1.1) are not included in the 75 pg. limit for the Technical Volume. (At a minimum 5 resumes are required which are typically 2 pages each and will equate to at least 10 pages of the 75 page limit.)
Refer to amendment. Overall page count is eliminated, however per 00 22 00 para
2.1 a concise proposal is required.
53 Technical 00 22 00
Please confirm that the bar chart schedule as part of Volume I – Factor I – Management, Sub-Factor C – Schedule (5.3.1) is not included in the 75 pg. limit for the Technical Volume. (A full schedule for a hangar project of this magnitude could be as many as 16 pages of the 75 page limit.)
Refer to amendment. Overall page count is eliminated, however per 00 22 00 para
2.1 a concise proposal is required.
Price and Performa
Information 00 22 00
Please confirm what Tabs are included an not included in the 25 page limit for Volume II – Price and Performa Information. Items such as the TAB B - Small Business Subcontracting Plan, TAB C – Joint Venture & Mentor-Protégé Agreements, and Tab D
– Financial Statements will easily exceed the page limit on their own.
Refer to amendment. Overall page count is eliminated, however per 00 22 00 para
2.1 a concise proposal is required.
Price and Performa
Information 00 22 00
Section 00 10 00 included FAR 52.228-1 which requires a Bid Guarantee. Volume II – Price and Performa Information TAB D Evidence of Ability to Obtain Bonding and Proof of Financial Ability, only identifies information showing the Offeror’s ability to be bonded. Please confirm that a Bid Bond is sufficient information showing Offeror’s ability to be bonded and should be included in Volume II TAB D.
Refer to amendment for clarification.
56 Architectural 09 67 23.15
Section 2.3 and 3.7 are calling for a 3-coat thin film flooring system with a total thickness between 13 and 20 mils (primer and two top coats). Drawing IN001 calls for EF1 to be Stonhard Stontec TRF, which is a 5 mm flooring system (3 mm Urethane mortar coating, undercoat, and urethane sealer). This is similar to the product listed in Table II of 09 67 23.15, under Stonhard. Stontec TRF is 197 mils (5 mm), which is almost 10x thicker than the thin coat system in 09 67 23.15, and is usually specified for existing floors with uneven surfaces (the thick coating allows for leveling the rough/uneven surfaces). On brand new construction, it is common to use the thin-coat system as specified in 09 67 23.15. Please confirm the 13 - 20 mil system specified in sections 2.3 and 3.7 is allowed in lieu of the Stontec TRF (as long as it meets the requirements of Tables Ib, Ic, and Id).
Confirmed. Products meeting the technical specifications in section 09 67 23.15 are considered acceptable. Also refer to Table II of the specification.
57 Technical 00 22 00
Volume I – Factor II – Past Performance is clear that projects performed by contractors other than the offeror, such as teaming partners or subcontractors will not be considered.
Please confirm that Past Performance and Experience by affiliate/subsidiaries/parent company (name not exactly as stated on the SF1442) will be acceptable as long as the proposal clearly demonstrates that the affiliate/subsidiary/parent company will have a meaningful involvement in the performance of the contract such as a commitment letter.
Prepare proposal in accordance with the solicitation documents. Per RFP requirements for proposal Volume I – Factor II, the subsidiary cannot utilize the past performance of a parent company unless said parent company is listed as a joint venture and the proposal is submitted as a joint venture.
58 Architectural
Structural steel shall be provided with 3 coat high performance system per Prepare proposal based on manufacturer standard color.
Prepare proposal based on manufacturer standard color.
59 Civil 31 00 00 - 3.19
The Earthwork specifications state that soil material not required or suitable for filling or backfilling shall be disposed of on project site at locations determined by the Contracting Officer. Please identify where the location that this material will be disposed of.
Per Section 31 00 00 paragraph 3.19 excess soil shall be disposed of on the project site at location determined by the Contracting Officer.
60 Civil 31 00 00 - 3.19
Spec 31 00 00 says that soil materials shall be disposed of on site, while any brush, refuse, trees, and vegetation need to be disposed of off Government property and into an approved landfill. Please confirm pavement materials being removed such as asphalt and concrete waste shall be disposed on site at a location determined by the Contracting Officer.
Per Section 31 00 00 paragraph 3.19 excess soil shall be disposed of on the project site at location determined by the Contracting Officer.
61 Civil 31 00 00 / C-501
Specs are clear that the existing fill beneath the proposed hangar is to removed in it’s entirety. Please confirm that a depth of an average of 2.5' across the entire building pad be removed. However on plan sheet C-501 all of the paving details call of a section for 12" Compacted Subgrade. Please confirm that there is no requirement to undercut and replace paving area subgrades.
Bid per original solicitations.
Subgrade preperations shall be in accordance with Specification section 31 00 00 and the Geotech Report.
62 Civil 33 40 00
Drainage Utility specs list ADS / HDPE as a material in addition to the RCP. The storm profiles call for RCP, but can you clarify whether the Base will allow ADS / HDPE in lieu of RCP?
Bid per original solicitation. HDPE is acceptable for use in specific locations indicated on drawings.
63 Water Tank 33 16 20
After reviewing the specifications and drawings, we find no information on Fire Suppression Tank insulation or heaters. If the tanks are to follow NFPA 22 guidelines these tanks should have provisions for insulation and emersion tank heaters. Please clarify.
Refer to revised section 33 16 20 included in amendment.
64 Architectural 11 24 29
Specification Section 11 24 29 Fall Protection, Paragraph 1.6 Warranty states to provide a lifetime manufacturers warranty. A lifetime manufacturers warranty does not exist among the four major fall protection manufacturers. What is selectively offered is a Limited Lifetime Warranty that excludes wear and tear and misuse and is subject to periodic inspection. Please clarify if this is the design intent.
Refer to amended Section 11 24 29 for clarification.
W912BU-18-R-0026 00 21 00 - 1
Section 00 21 00 - Instructions
52.204-6 DATA UNIVERSAL NUMBERING SYSTEM NUMBER (JULY 2013)
(a) Definition. Data Universal Numbering System (DUNS) number, as used in this provision, means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities, which is used as the identification number for Federal Contractors.
(b)The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS number or “DUNS+4” that identifies the offeror's name and address exactly as stated in the offer. The DUNS number is a nine-digit number assigned by Dun and Bradstreet, Inc. The DUNS+4 is the DUNS number plus a 4-character suffix that may be assigned at the discretion of the offeror to establish additional System for Award Management records for identifying alternative Electronic Funds Transfer (EFT) accounts (see Subpart 32.11) for the same concern.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number--
(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(End of provision)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 1989)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) Bidders shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the
W912BU-18-R-0026 00 21 00 - 2
amendment, (2) by identifying the amendment number and date in the space provided for this purpose on the form for submitting a bid, (3) by letter or telegram, or (4) by facsimile, if facsimile bids are authorized in the solicitation.
The Government must receive the acknowledgment by the time and at the place specified for receipt of bids.
(End of provision)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
(End of provision)
52.214-5 SUBMISSION OF BIDS (MAR 1997)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Telegraphic bids will not be considered unless authorized by the solicitation; however, bids may be modified or withdrawn by written or telegraphic notice.
(d) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(e) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of provision)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
(End of provision)
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
W912BU-18-R-0026 00 21 00 - 3
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids.