Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
U0001
W912BU
The purpose of this amendment is to provide offerers with revised changes
Proposals in response to this solicitation are now due 8 March 2018 at 1100am Site visit has been changed to 26 January 2018 Other changes as included in the attachment.
All questions pertaining to this procurement must be received no later than 0400 P.M, on 16 February 2018. Responses may not be provided to request for information (RFI's) received after this cutoff date.
USACE, PHILA DISTRICT
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
See Item 6
J
W25PHS71597713
W912BU17R0032
01/12/2018
03-Jan-2018
This page was intentionally left blank for duplex printing.
W912BU17R0032
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 – SOLICITATION
The required response date/time has changed from 05-Mar-2018 11:00 AM to 08-Mar-2018 11:00 AM.
SECTION 00 21 00 – INSTRUCTIONS
The following have been modified:
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) a site visits is scheduled for:
Date: Friday, January 26, 2018 Time: 10:00 AM
Contact: Barbara Moffatt, Barbara.F.Moffatt@usace.army.mil and Tom Lavender Thomas.S.Lavender@usace.army.mil
Refer to the inside cover page included in this amendment for additional site visit information.
(End of provision)
Amendment No. 0001
RFP W912BU-17-R-0032
14. DESCRIPTION OF AMENDMENT (continued)
a. INSIDE COVER PAGE: Please delete the Inside Cover Page in its entirety and substitute the revised Inside Cover Page, annotated Amendment No. 0001, attached hereto.
b. REQUEST FOR INFORMATION PROCEDURE: Please insert the Request for Information Procedure page, annotated Amendment No. 0001, attached hereto.
c. SECTION 00 73 15 - WAGE RATES: Please delete pages 00 73 15-3 through 00 73 15-9 in their entirety and insert the revised pages 00 73 15-3 through 00 73 15-9, annotated Amendment No. 0001, attached hereto.
d. TECHNICAL SPECIFICATIONS:
(1) Section 01 11 00 – SUMMARY OF WORK: Please delete page 01 11 00-4 in its entirety and insert the revised page 01 11 00-4, annotated Amendment 0001, attached hereto.
e. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001. Failure to acknowledge all amendments may be cause for rejection of the bid.
3 JANUARY 2018
INVITATION NO. RFP W912BU-17-R-0032
REQUEST FOR PROPOSALS
FOR
WELCH ELEMENTARY SCHOOL / DOVER MIDDLE SCHOOL REPLACEMENT
DOVER AIR FORCE BASE
DELAWARE
I. NOTE THE AFFIRMATIVE ACTION REQUIREMENT OF THE EQUAL OPPORTUNITY CLAUSE
WHICH MAY APPLY TO THE CONTRACT RESULTING FROM THIS SOLICITATION.
II. OFFERERS ARE REQUIRED TO COMPLETE THE REPRESENTATION AND CERTIFICATIONS
PORTION OF SECTION 00 45 00 OF THIS SOLICITATION AND SUBMIT THIS WITH THEIR
PROPOSAL.
III. PRE-PROPOSAL SITE VISIT. PROSPECTIVE OFFERORS ARE INVITED TO VISIT THE
SITE OF THE WORK TO ACQUAINT THEMSELVES WITH THE SITE CONDITIONS AND ANY
PROBLEMS INCIDENT TO THE PROSECUTION OF THE WORK. A SITE VISIT WILL BE HELD
ON 26 JANUARY, 2018. THE SITE VISIT WILL BEGIN AT 10:00 AM FROM THE AIR
MOBILITY COMMAND MUSEUM PARKING LOT, 1301 HERITAGE ROAD, DOVER AFB, DELAWARE
19902-5301. VISITORS WILL BOARD MILITARY TRANSPORTATION TO BE ESCORTED TO THE
PROJECT SITE. TRANSPORTATION WILL DEPART PROMPTLY AT 10:00 AM. ALL THOSE
PLANNING TO ATTEND SHOULD CONTACT MR. TOM LAVENDER AND MS. BARBARA MOFFATT, NO
LATER THAN 19 JANUARY 2018, VIA EMAIL AT THOMAS.S.LAVENDER@USACE.ARMY.MIL;
BARBARA.F.MOFFATT@USACE.ARMY.MIL TO BE PLACED ON THE DOVER AFB VISITORS LIST.
INFORMATION REQUIRED: NAME, COMPANY NAME, AND PHONE NUMBER.
DIRECTIONS TO THE AIR MOBILITY COMMAND MUSEUM ARE AS FOLLOWS:
FROM DELAWARE ROUTE 1, TAKE EXIT 91 (ROUTE 9/KITTS HUMMOCK/LITTLE CREEK).
FOLLOW ROUTE 9 NORTH FOR ABOUT 0.5 MILES. TURN LEFT ONTO HERITAGE ROAD
(MUSEUM ACCESS ROAD). THE ROAD IS CLEARLY MARKED WITH SIGNS. PROCEED TO THE
MUSEUM PARKING LOT.
IV. ALL QUESTIONS PERTAINING TO THIS PROCUREMENT MUST BE RECEIVED NO LATER
THAN 04:00 P.M., ON 16 FEBRUARY 2018. RESPONSES MAY NOT BE PROVIDED TO REQUEST
FOR INFORMATION (RFI'S) RECEIVED AFTER THIS CUTOFF DATE.
RFI – Page 1 of 1
Requests for Information (RFI) Procedure
The Philadelphia District requests that all Offerors follow the instructions below when submitting Requests for Information (RFI’s).
Requests for information will be answered by an Amendment so all Offerors are given the same information. Individual replies will not be issued.
RFI responses that affect the specifications will be issued as an Amendment to the specifications. If an RFI response conflicts with the Contract plans or specs, the Contract plans and/or specs will govern.
RFI responses may indicate that a resolution to an issue may be found in a Specific Amendment; however Offerors should always check all amendments to the plans and specs and prepare their bid accordingly. RFI responses that become invalid or inaccurate as the result of changes to the plans or specs issued by subsequent Amendments will not be revised.
Please do not submit an RFI more than once. Do not add subsequent questions to the list and resubmit your entire set of questions.
The following is the preferred format for submitting RFI’s. Questions submitted in this standard format will enable the Government to generate responses in a timelier manner.
Requests for information shall be submitted using a spreadsheet style method as shown below. A file with this format may also be downloaded from www.fbo.gov along with the plans and specs files for this project. Please attach the spreadsheet file as an attachment to an email message to Jamaal.A.Edwards@usace.army.mil. Please include the Solicitation Number (W912BU-17-R-0032) in the subject line.
The spreadsheet shall contain the following columns: 1) RFI Number, 2) Reference to applicable Spec Section or Drawing Sheet Number, 3) applicable discipline involved (Mechanical, Electrical, Civil, etc…), and 4) a Clear and concise statement of the problem or clarification requested.
Example:
RFI# Discipline
Spec Sect/ Drawing Description
1 Mechanical 15 22 00 Para. 2.5.1 specifies 4-inch pipe, however Dwg P2.01 shows piping is 8-inch in size.
2 Architectural A5.1.2 Unable to locate the specifications for the Grab Bars shown in the Toilet rooms.
Section 00 73 15 Page 3
General Decision Number: DE180013 01/05/2018 DE13
Superseded General Decision Number: DE20170013
State: Delaware
Construction Type: Building
County: Kent County in Delaware.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018
BOIL0013-009 01/01/2016
Rates Fringes
BOILERMAKER......................$ 42.26 37.02
BRDE0001-001 05/01/2017
Rates Fringes
BRICKLAYER
Brick Refractory/Brick Placement Worker............$ 32.51 22.41 Bricklayer..................$ 30.63 22.66
* CARP0173-009 05/01/2017
Rates Fringes
CARPENTER (Includes
Section 00 73 15 Page 4
Acoustical Ceiling Installation, Drywall Hanging, Form Work, Metal Stud Installation, Scaffold Building, Excludes Masonry/Brick, and Excludes Soft Floor Layer)................$ 31.62 22.44
CARP0251-008 05/01/2016
Rates Fringes
SOFT FLOOR LAYER.................$ 29.96 21.04
CARP1906-003 07/01/2015
Rates Fringes
MILLWRIGHT.......................$ 36.05 30.63
ELEC0313-002 06/01/2016
Rates Fringes
ELECTRICIAN (Includes Low Voltage Wiring and Installation of Alarms, HVAC/Temperature Controls and Sound and Communication Systems).........................$ 37.61 28.83
ELEV0005-003 01/01/2016
Rates Fringes
ELEVATOR MECHANIC................$ 52.79 29.985+A&B
FOOTNOTES FOR ELEVATOR MECHANICS:
A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of service.
B. Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day;
Labor Day; Veteran's Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day.
ENGI0542-003 05/01/2017
Rates Fringes
POWER EQUIPMENT OPERATOR
(Forklift).......................$ 39.08 24.88+A
Section 00 73 15 Page 5
FOOTNOTE: A. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day (provided the employee works the scheduled work day following the holiday.)
IRON0451-003 07/01/2017
Rates Fringes
IRONWORKER (Ornamental and Reinforcing).....................$ 33.60 30.10
The following holidays shall be observed, and when work is performed thereon it shall be paid for at twice the base wage rate: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABO0199-005 05/01/2016
Rates Fringes
LABORER
Backfiller, Common or General, Jack Hammer, Mason Tender - Brick, Pipelayer, Scaffold Builder (Brick and Masonry), Tamper (Hand Held).......................$ 24.55 19.30 Mason Tender - Cement/Concrete.............$ 24.80 19.30
PAIN0252-002 05/01/2017
Rates Fringes
GLAZIER..........................$ 41.30 28.06
PLAS0008-006 05/01/2017
Rates Fringes
PLASTERER (Fireproofer)..........$ 37.42 28.83
PLAS0592-009 05/01/2017
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 30.79 24.58
PLUM0074-002 06/13/2016
Rates Fringes
PIPEFITTER (Includes HVAC
Section 00 73 15 Page 6
Pipe Installation and Excludes Industrial Work)........$ 48.83 33.30
FOOTNOTE A: PAID HOLIDAYS: New Year's Day, Memorial Day,Independence Day, Thanksgiving Day,Labor Day, Christmas Day, and General Election Day.
PLUM0074-003 06/13/2016
Rates Fringes
PIPEFITTER (INDUSTRIAL)..........$ 48.83 33.30
FOOTNOTE A: PAID HOLIDAYS: New Year's Day, Memorial Day,Independence Day, Thanksgiving Day,Labor Day, Christmas Day, and General Election Day.
SFDE0669-002 04/01/2017
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 35.35 21.69
SHEE0019-021 07/01/2017
Rates Fringes
SHEET METAL WORKER (Includes HVAC Duct Installation)..........$ 31.31 36.01
SUDE2014-004 01/20/2016
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 37.42 15.04
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 47.71 8.41
OPERATOR: Bulldozer.............$ 25.89 0.00
OPERATOR: Crane.................$ 31.59 16.83
PAINTER (Brush and Roller).......$ 40.57 0.94
PLUMBER..........................$ 45.40 16.23
ROOFER (Installation of Metal Roofs Only)......................$ 39.09 30.77
ROOFER, Excludes Installation of Metal Roofs...................$ 27.98 27.90
TILE FINISHER....................$ 35.40 4.31
Section 00 73 15 Page 7
TILE SETTER......................$ 57.98 1.11
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing
Section 00 73 15 Page 8 the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on
Section 00 73 15 Page 9 a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notice
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.6 GOVERNMENT-INSTALLED WORK
Government to furnish and install all furniture, fixture and equipment noted as such in drawings. All other items to be provided in contract for a fully functioning school with all systems.
1.7 NO ASBESTOS CONTAINING MATERIAL CERTIFICATION LETTER FROM CONTRACTOR
A No ACM Certification from the Construction Contractor that no asbestos containing materials were installed is required to be provided at project completion with close out submittals.
Before final payment to the contractor, the contractor's project engineer/manager shall sign and submit to the government, on the prime construction contractor company letterhead, a dated copy of the following statement:
"In accordance with 40 CFR Part 763.99, to the best of my knowledge no asbestos containing building materials (ACBM) were used in the construction of the Welch Elementary School and Dover Air Base Middle School."
The letter shall be addressed to the designated DoDEA PM with copy furnished to the CAPM and the DoDEA Design Center TM.
1.8 POTABLE WATER TESTING
In accordance with EPA standards for water quality and testing, the contractor shall develop and submit a domestic water sampling plan for government review and approval. Contractor shall secure through an independent testing lab, confirmation that at the final turn over of the facility the domestic water served at each fixture and device is in compliance with all applicable water quality standards. The contractor shall test all water service locations in accordance with the EPA Technical Guidance (Revised) for Reducing Lead in Drinking Water in Schools. The sampling and analysis shall be performed by a certified drinking water lab (not self-performed). The initial and follow up samples cannot be taken at the same time. Ten days minimum advanced notification shall be provided to the government following approval. All sampling and testing shall be performed in the presence of the COR.
Contractor shall utilize all forms and protocols noted in the technical guidance (appendices) and all applicable federal, state and local standards. 20 ppb shall be used as a threshold for notification of the COR.
1.9 Software and Hardware System Approval - DoDEA
System software and all network connected hardware systems must be either on the DoDEA Approved Software/Hardware List or follow DoDEA requirements and become an approved software. In addition to software approval, and
Section 01 11 00 Page 3 prior to connecting the system to DoDEA Network, the contractor must obtain IT hardware/architecture approval by submitting a wiring-cabling riser diagram depicting; the wiring/cabling type proposed and the make/model of each device to be connected to that system along with product data. This submittal is to be sent thru USACE, thru the DoDEA PM, to DoDEA IT Department for approval. Submittal must include a PDF format sketch/drawing of the system. Contractor to coordinate with DoDEA PM for full submission requirements.
At minimum the following requirements shall be provided:
1. Software title: Identical name of the software title:
2. Version: Exact version number or designation of the software.
3. Software publisher: Name of software publisher.
4. ISBN: Identify the ISBN (non-mandatory field - this is usually located on the cover of the CD over the bar code or the publisher website).
5. Publisher Web site: Web address / URL (i.e. http://www...).
6. Software description: (What does the software do?)
7. CD, DVD, or download link (with User ID and password if required) of the proposed software to the address to be used for DoDEA testing.
1.10 BRAND NAMES
Items listed throughout the specifications by manufacturer name only, or by basis of design, shall be considered as manufacturer name or equal.
Where 'acceptable manufacturers' are listed throughout the specifications, the products to be used by the Contractor shall meet the salient characteristics specified and as shown.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
Section 01 11 00 Page 4
| SF30 |
| SF30 SUMMARY OF CHANGES |
| AMENDMENT DESCRIPTION |
| REVISED INSIDE PAGE |
| REQUEST FOR INFORMATION PROCEDURE |
| REVISED 00 73 15 WAGE RATES |
| REVISED 01 11 00 PAGE 4 |