RFP W912BU-17-R-0032
US Army Corps of Engineers Philadelphia District
Welch Elementary School / Dover Air Base Middle School Replacement
Dover Air Force Base Delaware
Drawings and Technical Specifications
Volume 3 of 5 (Divisions 09 – 14) JOB HAZARDS – Asbestos, Mercury, PCB’s, Lead Paint
3 January 2018
This page was intentionally left blank for duplex printing.
Main Table of Contents Page 1
MAIN TABLE OF CONTENTS
SOLICITATION PROVISIONS, CONTRACT CLAUSES AND SPECIFICATIONS FOR:
Welch Elementary School / Dover Air Base Middle School Replacement Dover Air Force Base, Dover, Delaware
Volume 1
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
Section Title
00 10 00 SF1442 SOLICITATION, OFFER, AND AWARD (PROPOSAL PRICE
BREAKOUT SCHEDULE FOUND IN APPENDIX A-5)
00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS
00 22 00 PROPOSAL SUBMSSION REQUIREMENTS, EVALUATION CRITERIA AND
BASIS OF AWARD
00 45 00 REPRESENTATIONS & CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
TECHNICAL SPECIFICATIONS
DIVISION 01 GENERAL REQUIREMENTS
Volume 2
DIVISION 02 - DIVISION 08
Volume 3
DIVISION 09 - DIVISION 14
Volume 4
DIVISION 15 - DIVISION 25
Volume 5
DIVISION 26 - DIVISION 33
APPENDICES
APPENDIX A-1 SUPPLEMENTAL GEOTECHNICAL REPORT (UNDER SEPARATE COVER)
APPENDIX A-2 3TS FOR REDUCING LEAD IN DRINKING WATER IN SCHOOLS: REVISED
TECHNICAL GUIDANCE (UNDER SEPARATE COVER)
APPENDIX A-3 SOIL GAS ASSESSMENT REPORT (UNDER SEPARATE COVER)
APPENDIX A-4 HAZARDOUS MATERIALS SURVEY (UNDER SEPARATE COVER)
APPENDIX A-5 PROPOSAL PRICE BREAKOUT SCHEDULE (UNDER SEPARATE COVER)
APPENDIX A-6 WELCH/DOVER REFERENCE DRAWINGS (UNDER SEPARATE COVER)
-- END OF MAIN TABLE OF CONTENTS --
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 11 05 DOVER AFB GENERAL REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 37 PROJECT SCHEDULE
01 32 10 SURVEY REQUIREMENTS
01 32 33 CONSTRUCTION PHOTOGRAPHY
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 33 29.00 06 LEED (TM) CERTIFICATION
01 33 29.00 37 SUSTAINABILITY
01 33 29.37 LEED (TM) DOCUMENTATION
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 40 DOVER AFB HAZARDOUS MATERIALS USAGE
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 50 10 DOVER AFB SITE MANAGEMENT
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.00 37 INDOOR AIR QUALITY (IAQ) MANAGEMENT
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 57 25 DOVER AFB ADDITIONAL ENVIRONMENTAL PROTECTION REQUIREMENTS
01 58 00 PROJECT IDENTIFICATION
01 62 00 DOVER AFB AFFIRMATIVE PROCUREMENT
01 62 35.37 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 74 19.00 37 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 76 00 STRUCTURES MONITORING
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 83 16.10 EXTERIOR ENCLOSURE PERFORMANCE REQUIREMENTS
01 91 00.00 37 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF PCBs, MERCURY, AND OTHER HAZARDOUS MATERIALS
DIVISION 03 - CONCRETE
03 01 30.71 CONCRETE REHABILITATION
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 33 00 CAST-IN-PLACE ARCHITECTURAL CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
03 45 00 PRECAST ARCHITECTURAL CONCRETE
03 52 00 LIGHTWEIGHT CONCRETE ROOF INSULATION
03 62 16 METALLIC NON-SHRINK GROUTING
PROJECT TABLE OF CONTENTS Page 1
DIVISION 04 - MASONRY
04 20 00 MASONRY
04 21 13.13 NONBEARING MASONRY VENEER
DIVISION 05 - METALS
05 05 23.13 10 ULTRASONIC INSPECTION OF WELDMENTS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 16 LONGSPAN STEEL JOIST FRAMING
05 21 19 OPEN WEB STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
05 72 00 DECORATIVE METAL SPECIALTIES
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK
06 61 16 SOLID POLYMER (QUARTZ AND SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
07 12 00 BUILT-UP BITUMINOUS WATERPROOFING
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 17 00 BENTONITE WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 27 FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR RETARDING
07 42 13 METAL WALL PANELS
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 15.00 20 ALUMINUM STANDING SEAM ROOFING
07 72 00 ROOF VENTILATORS, GRAVITY-TYPE
07 81 00 SPRAY-APPLIED FIREPROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 33 23 OVERHEAD COILING DOORS AND GRILLS
08 34 01 FORCED ENTRY RESISTANT COMPONENTS
08 34 02 BULLET-RESISTANT COMPONENTS
PROJECT TABLE OF CONTENTS Page 2
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 39 54 BLAST RESISTANT DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 51 13 ALUMINUM WINDOWS
08 51 23 STEEL WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 06 90 COLOR SCHEDULE
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 22 36 LATH
09 24 23 STUCCO
09 26 00 VENEER PLASTER
09 29 00 GYPSUM BOARD
09 30 13 CERAMIC TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 65 66 RESILIENT ATHLETIC FLOORING
09 68 00 CARPETING
09 72 00 WALLCOVERINGS
09 83 13 ACOUSTICAL WALL TREATMENT
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
09 97 13.00 40 STEEL COATINGS
DIVISION 10 - SPECIALTIES
10 10 00 VISUAL COMMUNICATIONS SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 14 01 EXTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 21 23.16 CUBICLE TRACK AND HARDWARE
10 22 26.23 COILING PARTITIONS
10 22 39 FOLDING PANEL PARTITIONS
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHER CABINETS & ACCESSORIES
10 51 13 METAL LOCKERS
10 56 13 STEEL SHELVING
10 75 00.48 FLAGPOLES
DIVISION 11 - EQUIPMENT
11 05 40 COMMON WORK RESULTS FOR FOODSERVICE EQUIPMENT
11 06 40.13 FOODSERVICE EQUIPMENT SCHEDULE
11 13 10 DOCK LEVELERS AND EQUIPMENT
11 30 00 RESIDENTIAL EQUIPMENT
11 31 13 ELECTRIC KITCHEN EQUIPMENT
11 41 11 REFRIGERATED AND FROZEN FOOD STORAGE EQUIPMENT
11 42 00 FOOD PREPARATION EQUIPMENT
11 44 00 FOOD COOKING EQUIPMENT
11 46 00 FOOD DISPENSING EQUIPMENT
11 47 00 ICE MACHINES
11 48 00 CLEANING AND DISPOSAL EQUIPMENT
PROJECT TABLE OF CONTENTS Page 3
11 65 00 GYMNASIUM EQUIPMENT
11 66 23.13 BASKETBALL EQUIPMENT
11 68 13 PLAYGROUND EQUIPMENT
11 95 00 KILN
DIVISION 12 - FURNISHINGS
12 22 00 STAGE CURTAINS
12 24 13 ROLLER WINDOW SHADES
12 32 00 MANUFACTURED WOOD CASEWORK
12 35 20 FOODSERVICE CASEWORK, COUNTERTOPS, AND ACCESSORIES
12 35 39 COMMERCIAL KITCHEN CASEWORK
12 36 00 COUNTERTOPS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
12 93 00 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 20 ALUMINUM WALKWAY COVERS AND CANOPIES
13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT
13 54 00 GREEN TOUCH SCREEN SYSTEM
DIVISION 14 - CONVEYING EQUIPMENT
14 24 01 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 21 03.00 10 WET CHEMICAL FIRE EXTINGUISHING SYSTEM
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 PLUMBING PIPING INSULATION
22 33 30.00 10 SOLAR WATER HEATING EQUIPMENT
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 31 13.00 40 METAL DUCTS
23 34 23.00 40 HVAC POWER VENTILATORS
23 36 00.00 40 AIR TERMINAL UNITS
23 41 13.00 40 PANEL FILTERS
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
PROJECT TABLE OF CONTENTS Page 4
23 82 16.00 40 AIR COILS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.00 10 INSULATED WIRE AND CABLE
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 08 00 APPARATUS INSPECTION AND TESTING
26 09 13 POWER MONITORING SYSTEM
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 23 00.00 40 SWITCHBOARDS AND SWITCHGEAR
26 27 13.10 30 ELECTRIC METERS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 55 61 THEATRICAL LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 41 16 INTEGRATED AUDIO VIDEO SYSTEM
27 41 50 SOUND SYSTEM
27 51 23.10 INTERCOMMUNICATION SYSTEM
27 53 13 GPS WIRELESS CLOCK SYSTEMS
27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
28 16 00.00 20 BASIC INTRUSION DETECTION SYSTEMS (IDS)
28 20 00.00 20 ELECTRONIC SECURITY SYSTEMS (ESS), COMMERCIAL
28 23 23.00 10 CLOSED CIRCUIT TELEVISION SYSTEMS
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 25 10 DOVER AFB SEDIMENT AND EROSION CONTROL
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSE
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
PROJECT TABLE OF CONTENTS Page 5
32 17 24.00 10 PAVEMENT MARKINGS
32 18 16.13 PLAYGROUND PROTECTIVE SURFACING
32 31 13 FENCES AND GATES
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 6
SECTION 09 06 90
COLOR SCHEDULE
PART 1 GENERAL
1.1 SUMMARY
This section covers only the color of exterior and interior materials and products that are exposed to view in the finished construction. The word "color", as used herein, includes surface color and pattern. Requirements for quality, product specifications, and method of installation are covered in other appropriate sections of the specifications. Specific locations where the various materials are required are shown on the drawings if not identified in this specification. Items not designated for color in this section may be specified in other sections. When color is not designated for items, propose a color for approval.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-04 Samples
Color Schedule; G, See Drawings
PART 2 PRODUCTS
2.1 REFERENCE TO MANUFACTURER'S COLOR
Where color is shown as being specific to one manufacturer, an equivalent color by another manufacturer may be submitted for approval. Manufacturers and materials specified are not intended to limit the selection of equal colors from other manufacturers.
2.2 COLOR SCHEDULE
The color schedules information provided in the drawingas lists the colors, patterns and textures required for exterior and interior finishes, including both factory applied and field applied colors. Where color is shown as being specific to one manufacturer, an equivalent color by another manufacturer may be submitted for approval. Manufacturers and materials specified are not intended to limit the selection of equal colors from other manufacturers. In the case of difference between the drawings and specifications, colors identified in the drawings govern.
Submit 3 sets of color boards, 120 days after the Contractor is given Notice to Proceed, complying with the following requriements.
a. Color boards shall reflect all actual finish textures, patterns, and colors required for this contract.
b. Materials shall be labeled with the finish type, manufacturer's name, pattern, and color reference.
Section 09 06 90 Page 1
c. Samples shall be on size 8-1/2 by 11 inch boards with a maximum spread of size 25-1/2 by 33 inches for foldouts.
d. Samples for this color board are required in addition to samples requested in other specification sections.
e. Color boards shall be submitted to the following address:
Zyscovich, Inc.
100 North Biscayne Boulevard, 27th Floor Miami, Florida 33132.
2.3 EXTERIOR FINISHES
Reference drawings for manufacturer and color information.
2.4 INTERIOR FINISHES2.4.1 Interior Wall Finishes
Apply interior wall color to the entire wall surface, including reveals, vertical furred spaces and columns, grilles, diffusers, electrical and access panels, and piping and conduit adjacent to wall surfaces unless otherwise specified. Paint items not specified in other paragraphs to match adjacent wall surface. Provide wall materials to match the colors listed below.
2.4.2 Interior Ceiling Finishes
Apply ceiling colors to ceiling surfaces including soffits, furred down areas, grilles, diffusers, registers, and access panels. In addition, apply ceiling color to joists, underside of roof deck, and conduit and piping where joists and deck are exposed and required to be painted.
Provide ceiling materials to match the colors listed below.
2.4.3 Interior Trim
Provide interior trim to match the colors listed below.
2.5 PLACEMENT SCHEDULE
Placement of color to be in accordance with the schedule provided in the drawings.
PART 3 EXECUTION
Not Used
-- End of Section --
Section 09 06 90 Page 2
SECTION 09 22 00
SUPPORTS FOR PLASTER AND GYPSUM BOARD
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A463/A463M (2010; R 2015) Standard Specification for Steel Sheet, Aluminum-Coated, by the Hot-Dip Process
ASTM A653/A653M (2015; E 2016) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM C645 (2014; E 2015) Nonstructural Steel Framing Members
ASTM C754 (2015) Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products
ASTM C841 (2003; R 2013) Installation of Interior Lathing and Furring
ASTM C847 (2014a) Standard Specification for Metal Lath
NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS (NAAMM)
NAAMM EMLA 920 (2009) Guide Specifications for Metal Lathing and Furring
UNDERWRITERS LABORATORIES (UL)
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Section 09 22 00 Page 1
Metal support systems; G
Submit for the erection of metal framing, furring, and ceiling suspension systems. Indicate materials, sizes, thicknesses, and fastenings.
All assemblies are to be provided with tested assembly ratings for fire resistance and/or acoustic rating as applicable.
1.3 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the job site and store in ventilated dry locations.
Storage area shall permit easy access for inspection and handling. If materials are stored outdoors, stack materials off the ground, supported on a level platform, and fully protected from the weather. Handle materials carefully to prevent damage. Remove damaged items and provide new items.
PART 2 PRODUCTS
2.1 MATERIALS
Provide steel materials for metal support systems with galvanized coating ASTM A653/A653M, G-60; aluminum coating ASTM A463/A463M, T1-25; or a 55-percent aluminum-zinc coating. Provide support systems and attachments per UFC 3-310-04, "Seismic Design for Buildings" in seismic zones.
Acceptable Manufacturers:
1. ClarkDietrich Building Systems;
2. Marino/WARE;
3. Craco Manufactureing, Inc.;
4. Steelform Building Products, Inc.;
5. Southeastern Stud and Components;
6. MRI Steel Framing, LLC;
7. MBA Metal Framing;
8. or approved equal.
2.1.1 Materials for Attachment of Lath
2.1.1.1 Suspended and Furred Ceiling Systems and Wall Furring
ASTM C841, and ASTM C847.
2.1.1.1.1 Sound Isolation Ceiling Hangars
1. Model ICC (Basis of design) from Kinetics Noise Control, Inc., Dublin, Ohio 614-889-0480
2. Similar sound isolation ceiling hangers from Kinetics Noise Control,Inc., or Mason Industries, Inc.
(Hauppauge, New York 631-348-0282) that meet the static deflection and natural frequency requirements described in this specification may be submitted for approval.
3. Sound isolation ceiling hangers shall have sufficient capacity to sustain continuously applied ceiling weight without settling after initial deflection.
4. Sound isolation ceiling hanger shall consist of a high-deflection steel spring seated in a molded neoprene cup.
The steel spring and neoprene cup shall be incorporated into a stamped steel hanger assembly that resiliently supports the isolated gypsum board ceiling.
Section 09 22 00 Page 2
5. The hanger assembly bracket shall be designed to allow fifteen (15) degrees of vertical alignment of the suspension member without making metal-to-metal contact between the suspension and hanger assembly members.
The hanger bracket shall be designed with an integral spring pre-load bracket selected to minimize change in elevation once a load is applied to the hanger and to hold the isolator assembly steady during attachment of gypsum board. The hanger assembly bracket shall consist of a leveling rod with an attached channel carrier designed to accept 1-1/2" x 1/2", 16-gauge cold-rolled steel.
The isolation hanger deflection shall be selected by the manufacturer to provide a maximum natural frequency of 3.4 Hz. The steel spring element shall have a minimum Kx to Ky of 1 at its 1" rated deflection and shall have an additional travel to solid of 50% of its rated static deflection.
Perimeter Isolation Material:
1. Model SRP (Basis of design) from Kinetics Noise Control, Inc., Dublin, Ohio 614-889-0480 or approved equal.
Sound Isolation Ceiling Clips:
1. Model GenieClip (Basis of design) from Pliteq, Inc., Dublin, Ohio 614-889-0480
2. Similar sound isolation clips: Isomax Resilient Sound Isolation Clips from Kinetics Noise Control, Inc., or RSIC-1 Clips from PAC International, Inc. that meet the requirements described in this specification may be submitted for approval.
3. The rubber isolator of the sound isolation clips shall be manufactured to ASTM D 2000, M2 AA 510 A13, which includes the following:
a) Hardness, ASTM D 2240, Shore A: 47.
b) Modulus 300 Percent, ASTM D 412, Die C: 5.3 MPa.
c) Tensile Strength, ASTM D 412, Die C: 11.2 MPa.
d) Elongation at Break, ASTM D 573: 454 percent.
4. The clip shall be manufactured with galvanized steel with aluminum-zinc coating that is shaped to receive drywall furring channels.
5. The minimum pull out and shear shall be 108 lbs.
6. The minimum design load capacity per clip shall be 36 lbs.
Wall Isolation (Resilient Sway Brace) Material:
1. Model PSB (Basis of Design) from Kinetics Noise Control, Inc. or approved equal.
2.1.1.2 Non-loadbearing Wall Framing
NAAMM EMLA 920.
2.1.2 Materials for Attachment of Gypsum Wallboard
2.1.2.1 Suspended and Furred Ceiling Systems
ASTM C645.
2.1.2.2 Nonload-Bearing Wall Framing and Furring
ASTM C645, but not thinner than 0.0179 inch thickness, with 0.0329 inch minimum thickness supporting wall hung items such as cabinetwork, equipment
Section 09 22 00 Page 3 and fixtures or use thickness appropriate for length of framing member per manufacturer's recommendations.
2.1.2.3 Furring Structural Steel Columns
ASTM C645. Steel (furring) clips and support angles listed in UL Fire Resistance may be provided in lieu of steel studs for erection of gypsum wallboard around structural steel columns.
2.1.2.4 Z-Furring Channels with Wall Insulation
Not lighter than 26 gage galvanized steel (G-90), Z-shaped, with 1-1/4 inch and 3/4 inch flanges and depth as required by the insulation thickness provided.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Systems for Attachment of Lath
3.1.1.1 Suspended and Furred Ceiling Systems and Wall Furring
ASTM C841, except as indicated otherwise.
3.1.1.2 Non-loadbearing Wall Framing
NAAMM EMLA 920, except provide framing members 16 inches o.c. unless indicated otherwise.
3.1.2 Systems for Attachment of Gypsum Wallboard
3.1.2.1 Suspended and Furred Ceiling Systems
ASTM C754, except provide framing members 16 inches o.c. unless indicated otherwise.
3.1.2.2 Non-loadbearing Wall Framing and Furring
ASTM C754, except as indicated otherwise.
3.1.2.3 Furring Structural Steel Columns
Install studs or galvanized steel clips and support angles for erection of gypsum wallboard around structural steel columns in accordance with the UL Fire Resistance, design number(s) indicated .
3.1.2.4 Z-Furring Channels with Wall Insulation
Install Z-furring channels vertically spaced not more than 24 inches o.c.
Locate Z-furring channels at interior and exterior corners in accordance with manufacturer's printed erection instructions. Fasten furring channels to masonry and concrete walls with powder-driven fasteners or hardened concrete steel nails through narrow flange of channel. Space fasteners not more than 24 inches o.c.
3.2 ERECTION TOLERANCES
Provide framing members which will be covered by finish materials such as
Section 09 22 00 Page 4 wallboard, plaster, or ceramic tile set in a mortar setting bed, within the following limits:
a. Layout of walls and partitions: 1/4 inch from intended position;
b. Plates and runners: 1/4 inch in 8 feet from a straight line;
c. Studs: 1/4 inch in 8 feet out of plumb, not cumulative; and
d. Face of framing members: 1/4 inch in 8 feet from a true plane.
Provide framing members which will be covered by ceramic tile set in dry-set mortar, latex-portland cement mortar, or organic adhesive within the following limits:
a. Layout of walls and partitions: 1/4 inch from intended position;
b. Plates and runners: 1/8 inch in 8 feet from a straight line;
c. Studs: 1/8 inch in 8 feet out of plumb, not cumulative; and
d. Face of framing members: 1/8 inch in 8 feet from a true plane.
Section 09 22 00 Page 5
SECTION 09 22 36
LATH
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1063 (2017) Standard Specification for Installation of Lathing and Furring to Receive Interior and Exterior Portland Cement-Based Plaster
ASTM C841 (2003; R 2013) Installation of Interior Lathing and Furring
GYPSUM ASSOCIATION (GA)
GA 600 (2009) Fire Resistance Design Manual
UNDERWRITERS LABORATORIES (UL)
UL Fire Resistance (2014) Fire Resistance Directory
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Lath Accessories Access panels Materials; G
1.3 DELIVERY AND STORAGE
Deliver materials in the manufacturer's original unbroken packages or containers that are labeled plainly with the manufacturer's names and brands. Store materials in dry locations with adequate ventilation, free from water, and in such a manner to permit easy access for inspection and handling. Stack gypsum lath flat to avoid sagging or damage to edges, ends, or surfaces, and protect from exposure to direct sunlight.
Section 09 22 36 Page 1
PART 2 PRODUCTS
2.1 LATH
2.1.1 Metal Plastering Base (Lath)
Provide the type(s) and weight(s) required for the type and spacing of supports shown for the kind of plaster indicated and specified. Do not use rib lath for ceramic tile scratch coat.
2.1.1.1 For Portland Cement-Based Plaster (Stucco)
ASTM C1063, self-furring diamond mesh 3/8 inch rib metal lath .
2.1.1.2 For Gypsum Plaster2.1.1.3 Paper Backing (Waterproofed Kraft Building Paper)
Provide metal plastering base with paper backing, for exterior plastering work.
2.1.1.4 Galvanized Metal Plastering Base
Provide for exterior plastering work and for plastering room(s) in all locations.
2.1.2 Accessories
Provide only zinc alloy r.
2.2 ACCESS PANELS
Prefabricated steel units, size(s)as indicated. Fabricate frame of preformed angle or channel with welded joints. Perforate wide leg or flange of frame section or extend frame section into expanded metal wings to provide a key for the plaster. Cover shall be hinged or snap-on type with turn-latch or spring catch. Fabricate access panels not larger than 24 by 36 inches from 14 gage steel with frames not lighter than 16 gage.
Fabricate access panels larger than 24 by 36 inches as indicated.
Factory-prime panels with rust-inhibitive paint.
PART 3 EXECUTION
3.1 INSPECTION
Verify that framing, furring and accessories are securely attached and of proper sizes and spacing necessary to provide a suitable substrate to receive lath. Do not proceed with work until framing, furring and accessories are acceptable to the Contracting Officer for application of lath.
3.2 INSTALLATION
3.2.1 Lathing Materials and Accessories
Install in accordance with ASTM C1063 for portland cement-based plaster work and ASTM C841 for gypsum plaster work, except where indicated or specified otherwise herein.
Section 09 22 36 Page 2
3.2.1.1 Metal Plastering Base
Install where indicated and surfaces to receive plaster.
3.2.1.2 Metal Plaster Base with Paper Backing
Where used, lap joints to provide backing on backing and metal-on-metal.
Lap backing not less than one inch. Lap backing so that water will flow to the exterior.
3.2.1.3 Control (Expansion and Contraction) Joints
a. For portland cement-based plaster (ceilings and walls), install to create panels no larger than l00 square feet with no dimension exceeding 10 feet.
b. For unrestrained gypsum plaster ceilings install to create panels no larger than 2,500 square feet with no dimension exceeding 50 feet. For gypsum plaster walls, partitions and ceilings without perimeter relief install not more than 30 feet on centers in either direction.
c. Install where expansion joints occur in the structural walls and ceilings and where ceiling framing or furring changes direction.
Terminate lath at each side of joint and fasten joints securely to lath.
3.2.1.4 Unrestrained Ceilings
Furred or suspended ceilings constructed with gypsum plaster and larger than 2,500 square feet in area or with any dimension exceeding 50 feet or portland cement-based plaster must be unrestrained. Isolate ceiling lath and plaster from ceiling intersecting vertical surfaces with casing beads, control joints, or similar devices designed to keep the ceiling isolated from the adjacent vertical surfaces (walls, partitions, beams, and columns). Do not use corner reinforcement at the internal angle between the ceiling and the vertical surfaces.
3.2.1.5 Plastering Beads
Install edge trim (casing bead)at the edges of plaster which abuts or adjoins an unplastered surface, Fill voids formed in corners with sealant.
Install corner beads at all vertical external corners of plaster walls.
3.2.2 Fire-Resistant Assemblies
Wherever fire-resistant construction is indicated, provide all materials and application methods, including types and spacing of fasteners, in accordance with the specifications contained in the UL Fire Resistance for the Design Number(s) indicated or GA 600 for the File Number(s) indicated.
3.2.3 Access Panels
Install in suspended ceilings and plastered walls at locations indicated.
Section 09 22 36 Page 3
SECTION 09 24 23
STUCCO
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A1064/A1064M (2017) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM C1032 (2014) Standard Specification for Woven Wire Plaster Base
ASTM C1063 (2017) Standard Specification for Installation of Lathing and Furring to Receive Interior and Exterior Portland Cement-Based Plaster
ASTM C150/C150M (2017) Standard Specification for Portland Cement
ASTM C206 (2014) Standard Specification for Finishing Hydrated Lime
ASTM C841 (2003; R 2013) Installation of Interior Lathing and Furring
ASTM C847 (2014a) Standard Specification for Metal Lath
ASTM C897 (2015) Aggregate for Job-Mixed Portland Cement-Based Plasters
ASTM C926 (2016b) Standard Specification for Application of Portland Cement-Based Plaster
ASTM C933 (2014) Welded Wire Lath
ASTM D1784 (2011) Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED BD+C (2009; R 2010) Leadership in Energy and
Section 09 24 23 Page 1
Environmental Design(tm) Building Design and Construction (LEED-NC)
1.2 SUSTAINABILITY REPORTING
Materials in this technical specification may contribute towards contract compliance with sustainability requirements. See Section 01 33 29 SUSTAINABILITY REPORTING for project LEED BD+C and LEED documentation requirements.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Lath
SD-03 Product Data
Proportions and Mixing Material; G
SD-04 Samples
Sample Panel Samples; G
SD-11 Closeout Submittals
LEED Documentation
1.4 QUALITY ASSURANCE
Submit, if required, a SAMPLE PANEL as follows: A sample panel of stucco, constructed at the jobsite, and located as directed, to demonstrate installation procedures, texture and color, prior to proceeding with any stucco work; panel size shall be a minimum of 4 feet wide x 8 feet high;
containing each type accessory proposed for use and constructed in the vertical position. Sample panel shall have exposed reinforcement at the edges. Each phase of installation such as framing, scratch coat, brown coat, finish coat and curing procedures shall be demonstrated in the construction of the panel. Submit one 12 inch square of reinforcement and one 12 inch length of each accessory proposed for use, prior to constructing the sample panel.
1.5 DELIVERY, STORAGE, AND HANDLING
Deliver packaged materials to the site in the original packages and containers with labels intact and seals unbroken. Keep cementitious materials dry and stored off the ground, under cover and away from damp surfaces until ready to be used. Aggregate shall be covered to prevent the absorption or loss of moisture.
Section 09 24 23 Page 2
1.6 ENVIRONMENTAL REQUIREMENTS
Do not apply stucco when the ambient temperature is 40 degrees F or lower, or when a drop in temperature below 40 degrees F is expected within 48 hours after application.
PART 2 PRODUCTS
2.1 PORTLAND CEMENT
Portland cement shall conform to ASTM C150/C150M, white portland cement, Type I.
2.2 LIME
Lime shall conform to ASTM C206, Type S.
2.3 SAND
Sand aggregate for job-mixed base coat and job-mixed finish coat stucco shall conform to ASTM C897.
2.4 ACCESSORIES
Accessories shall be roll formed galvanized steel, or rigid polyvinyl chloride PVC or zinc, except that cornerite and striplath shall be formed from steel sheets with manufacturer's standard galvanized coating. Vinyl members shall be in accordance with ASTM D1784. Welded wire corner reinforcements shall be zinc coated, galvanized 17 gauge steel wire conforming to ASTM A1064/A1064M. Furring shall include hangers, bolts, inserts, clips, fastenings, and attachments of number, size, and design to develop the full strength of the members.
2.5 STEEL FRAMING
Steel framing shall be as shown and shall be manufacturers standard products with shop applied protective coating.
2.6 METAL LATH
Metal lath shall conform to ASTM C847, types and weights in accordance with the various spacing shown in ASTM C841. Lath for vertical application on steel and wood framing supports shall be self furring expanded metal or welded or woven wire and shall have paper backing with a minimum vapor permeance of 5 perms. Woven wire lath shall be a maximum 1-1/2 x 1-1/2 inch mesh wire of not less than 0.0540 inch nominal diameter and shall conform to ASTM C1032. Welded wire lath shall conform to ASTM C933, with openings not to exceed 2 x 2 inches. Expanded metal or wire lath shall be fabricated in a manner to provide not less than 1/4 inch keying between wire and paper backing and keying shall be obtained by a uniform series of slots in a perforated face paper woven between the wires.
2.7 WATER
Provide clean, fresh, potable water, free from amounts of oils, acids, alkalis and organic matter that would be injurious to the stucco.
Section 09 24 23 Page 3
PART 3 EXECUTION
3.1 FRAMING
Framing shall be installed as indicated.
3.2 CONTROL JOINTS
Control joints shall be located as indicated on the drawings.
Prefabricated control joint members shall be installed prior to the application of the stucco. Control joints shall be cleared of all stucco within the control area after stucco application and prior to final stucco set.
3.3 LATH
Install lath in accordance with ASTM C841 or ASTM C1063 except as otherwise specified. Metal and wire lath shall be applied straight, without buckles and with joints staggered. End laps of metal lath shall be not less than 1 inch. When paper-backed lath is used, the paper shall be split from the lath at all lap areas to provide a paper to paper and lath to lath lap.
Horizontal joints shall be shiplapped. Lath shall be interrupted at all control joints. Submit drawings showing details of construction for reinforcement, furring, and grounds; including manufacturer's installation instructions for stucco materials, and locations where each mix and coating thickness will be used.
3.3.1 Steel and Wood Supports
Apply metal lath over vertical open or solid wood and steel backing frame construction only after sheathing and air barrier has been applied to the area to receive the stucco. Fasten lath every 8 inches vertically and every 16 inches horizontally; and where sheets of lath are lapped. Drive fasteners to hold both lapped edges securely in place.
3.3.2 On Concrete and Masonry
Fasten lath every 8 inches vertically and every 16 inches horizontally.
Where wood supports adjoin masonry or concrete in the same direction, provide casing bead, control joints, or reinforcement as indicated.
3.3.3 Over Metal Lintels and Flashings
Lath over metal lintels shall be extended vertically over the angles to a height of not less than 6 inches and horizontally across the underside of the lintels and shall be secured in an approved manner. Lath over metal flashings shall lap the flashings not less than 2 inches and shall be extended vertically for a height of not less than 6 inches.
3.3.4 Special Shapes, Profiles, and Contours
Special shapes, profiles, and contours shall be formed with wood, metal or aluminum furring and reinforcing.
3.4 FURRING
Furring shall be installed to true lines and surfaces and shall be rigidly supported and secured in place.
Section 09 24 23 Page 4
3.5 PREPARATION OF SURFACES
Preparation of surfaces for application of stucco to solid bases such as stone, masonry or concrete shall conform to the applicable requirements of
ASTM C926.
3.6 PROPORTIONS AND MIXING
Proportions and mixing for job-mixed base coat and finish coat shall conform to the applicable requirements of ASTM C926. Mixing of mill-mixed finish coat shall be in accordance with the manufacturer's directions.
Submit detailed description of the proposed job-mix proportions for base and finish coats; including identification of thickness of coats.
3.7 STUCCO APPLICATION
Stucco shall be applied in three coats to a thickness of not less than 1 inch as measured from the back plane of metal reinforcement, exclusive of ribs or dimples or from the face of solid backing or support, with or without metal reinforcement, to the finished stucco surface, including moderate texture variations. Stucco application shall conform to the applicable requirements of ASTM C926 and the following:
3.7.1 Workmanship
Items or features of the work in connection with or adjoining the stucco shall be in place, plumb, straight, and true prior to beginning the stucco work. Metal and wire lath, where required, shall be in place and positioned to provide a good key at back of lath. Where lath is applied over copper, the copper shall be given a heavy coat of bituminous paint.
Masonry surfaces to receive stucco shall be evenly dampened immediately prior to application of stucco. Each stucco coat shall be applied continuously in one general direction, without allowing mortar to dry at edges. Where it is impossible to work the full dimension of a wall surface in a continuous operation, jointing shall be made at a break, opening, or other natural division of the surface. Edges to be joined shall be dampened slightly to produce a smooth confluence. Exterior corners of stucco shall be slightly rounded. Stucco on soffit surfaces shall be pitched forward to form a drip.
3.7.2 Scratch Coat
Apply scratch coat not less than 3/8 inch thick under sufficient pressure to form good keys and to completely embed the reinforcement. Before the scratch coat has set, it shall be lightly scratched in one direction and vertical surfaces shall be scratched in the horizontal direction only. The scratch coat shall be fog cured for a minimum of 72 hours.
3.7.3 Brown Coat
Evenly dampen the scratch coat to obtain uniform suction before the brown coat is applied. There shall be no visible water on the surface when the brown coat is applied. The brown coat shall be applied to the scratch coat with sufficient pressure to force the stucco into the scratches and shall be brought to a plumb, true, even plane with rod or straightedge. When set sufficiently, the brown coat shall be uniformly floated with a dry float to promote densification of the coat and to provide a surface receptive to bonding of the finish coat. Brown coat shall be fog cured for a minimum of 72 hours.
Section 09 24 23 Page 5
3.7.4 Finish Coat
Dampen surfaces of the brown coat not more than 1 hour before the finish coat is to be applied to a uniform wetness with no free-standing water on the surface. The finish coat shall have a smooth float finish and shall conform to the approved sample. Fog cure the finish coat for a minimum of 48 hours. Take care to prevent staining.
3.7.5 Surface Tolerance
When a 10 foot straightedge is placed at any location on the finished surface of the stucco, excluding rough-textured finish, the surface shall not vary more than 1/8 inch from the straightedge.
3.8 CURING AND PROTECTION
Perform fog curing by applying a fine mist of water to the stucco.
Exercise care during fog curing to avoid erosion damage of the stucco surfaces. Do not use a solid stream of water. Fognot less than three times daily. Protect the stucco from the direct rays of the sun during severe drying conditions using canvas, cloth or other approved sheet material.
3.9 PATCHING AND POINTING
Replace or patch loose, cracked, damaged or defective work as directed.
Patching shall match existing work in texture and color and shall be finished flush.
Section 09 24 23 Page 6
SECTION 09 26 00
VENEER PLASTER
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1002 (2014) Standard Specification for Steel Self-Piercing Tapping Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Wood Studs or Steel Studs
ASTM C1047 (2014a) Standard Specification for Accessories for Gypsum Wallboard and Gypsum Veneer Base
ASTM C1396/C1396M (2014a) Standard Specification for Gypsum Board
ASTM C475/C475M (2015) Joint Compound and Joint Tape for Finishing Gypsum Board
ASTM C514 (2004; R 2014) Standard Specification for Nails for the Application of Gypsum Board
ASTM C587 (2004; R 2014) Gypsum Veneer Plaster
ASTM C631 (2009; R 2014) Bonding Compounds for Interior Gypsum Plastering
ASTM C645 (2014; E 2015) Nonstructural Steel Framing Members
ASTM C754 (2015) Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products
ASTM C843 (2017) Standard Specification for Application of Gypsum Veneer Plaster
ASTM C844 (2015) Application of Gypsum Base to Receive Gypsum Veneer Plaster
ASTM C954 (2015) Steel Drill Screws for the Application of Gypsum Panel Products or Metal Plaster Bases to Steel Studs from
0.033 in. (0.84 mm) to 0.112 in. (2.84 mm) in Thickness
Section 09 26 00 Page 1
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS)Indoor Advantage
UL ENVIRONMENT (ULE)
ULE Greenguard UL Greenguard Certification Program
UNDERWRITERS LABORATORIES (UL)
UL Fire Resistance (2014) Fire Resistance Directory
1.2 GENERAL REQUIREMENTS
Except where otherwise indicated or specified, conform to ASTM C754, ASTM C843, and ASTM C844. Apply the gypsum veneer plaster as a system over a special gypsum base. The veneer plaster, gypsum base, and joint reinforcement shall be products of the same manufacturer. The extent and location of veneer plaster shall be as shown on the drawings, and shall at a minimum be provided at all locations where wall graphics and custom signage and exhibtry are to be provided. Metal framing is specified herein.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Gypsum base Gypsum veneer plaster
Descriptive data and installation instructions.
Certification
Material; G
1.4 SUSTAINABLE DESIGN CERTIFICATION
Product shall be third party certified in accordance with ULE GreenguardGold, SCS Scientific Certification Systems Indoor Advantage Gold or equal.
Certification shall be performed annually and shall be current.
1.5 DELIVERY AND STORAGE
Deliver and store plaster materials in the manufacturer's original uopened
Section 09 26 00 Page 2 containers. Store materials off the ground within a completely enclosed structure or enclosed within a weathertight covering. Store gypsum base and gypsum backing board flat to prevent warping and protect from excessive exposure to sunlight.
1.6 SCHEDULING
Commence application only after the area scheduled for veneer plaster work is completely weathertight. The heating, ventilating, and air-conditioning systems should be complete and in operation prior to application of the plaster. If the mechanical system cannot be activated before veneer plastering is begun, the plastering may proceed in accordance with an approved plan to maintain the environmental conditions specified below.
Apply plaster prior to the installation of finish flooring and acoustic ceiling.
1.7 ENVIRONMENTAL REQUIREMENTS
Do not expose the gypsum base to excessive sunlight prior to plaster application, as bond failure of the plaster may result. Maintain a continuous uniform temperature of not less than 50 degrees F and not more than 80 degrees F for at least one week prior to the application of veneer plaster, while the plastering is being done, and for at least one week after the plaster is set. Shield air supply and distribution devices to prevent any uneven flow of air across the plastered surfaces. Provide ventilation to exhaust moist air to the outside during plaster application and set, and until plaster is dry. In glazed areas, keep windows open top and bottom or side to side 3 to 4 inches. Openings can be reduced in cold weather. For enclosed areas lacking natural ventilation, provide temporary mechanical means for ventilation. In unglazed areas subjected to hot, dry winds or temperature differentials from day to night of 20 degrees F or more, screen openings with cheesecloth or similar materials. Avoid rapid drying. During periods of low indoor humidity, provide minimum air circulation following plastering and until plaster is dry.
1.8 FIRE RESISTIVE CONSTRUCTION
Build partitions and ceilings indicated to be of fire resistive construction in compliance with the drawings. For fire-rated assembly comply with the specifications contained in UL Fire Resistance, or FM APP GUIDEfor the Design Numbers indicated.
PART 2 PRODUCTS
2.1 MATERIALS
Conform to the requirements specified below. Miscellaneous items not otherwise specified shall be as recommended by the veneer plaster system manufacturer and approved prior to use. Powder driven fasteners may be used only when approved in writing.
2.1.1 Steel Framing, Furring, and Related Items
ASTM C645.
2.1.2 Vapor Retarder
Foil-backed gypsum base or gypsum backing board, or 4-mil polyethylene.
Section 09 26 00 Page 3
2.1.3 Gypsum Backing Board
ASTM C1396/C1396M, Type X. Provide boards with square edges as the first ply in two-ply application. Provide 48 inches wide boards, thickness as shown except that board used for liner panels and core plies of shaftwall construction shall be the size and thickness recommended by the system manufacturer.
2.1.4 Gypsum Base
ASTM C1396/C1396M, Type X, 48 inches wide, thickness as shown. Provide square edges, rounded, or tapered as recommended by the veneer plaster manufacturer.
2.1.5 Gypsum Veneer Plaster
ASTM C587. Minimum compressive strength of finish coat plaster shall be 2500 psi.
2.1.6 Joint Reinforcement
ASTM C475/C475M, Mesh reinforcing strip or paper tape as recommended by the veneer plaster manufacturer.
2.1.7 Joint Compound
ASTM C475/C475M.
2.1.8 Screws
ASTM C1002or ASTM C954, type appropriate to use.
2.1.9 Nails
ASTM C514, with corrosion-resistant treatment.
2.1.10 Corner Bead, Casing Bead, and Control Joints
ASTM C1047 , Corrosion protective-coated steel, vinyl or clear anodized aluminum as recommended by the veneer plaster manufacturer. Provide flanges free of any material that would adversely affect bonding of the plaster.
PART 3 EXECUTION
3.1 STEEL FRAMING
ASTM C754. Space framing at 16 inches on center maximum. Partitions shall support applied loads such as cabinets and counters without exceeding the permitted deflection.
3.1.1 Partition Framing System
Metal non-load bearing framing and furring system shall be capable of carrying a transverse load of 5 psf without exceeding either the allowable stress or a deflection of L/240. Provide studs of 0.0179 inch minimum thickness for partitions having the same material and the same material thickness on both sides. For partitions using 0.0l79 inch thick studs, the surfacing material shall cover the full height of the partition on both
Section 09 26 00 Page 4 sides, or the stud flange shall be otherwise supported to insure rigidity.
Provide studs of 0.0329 inch minimum thickness for partitions having different materials or different material thickness on the two sides. At partition ends, corners, and intersections, and at jambs of openings, fasten studs to runners with screws.
3.1.2…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.