AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
J
PAGE OF PAGES
1 1
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
US ARMY ENGINEER DISTRICT, PHILADELPHIA
POC ROBERT W. HUTCHEON
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
W912BU-17-R-0010
9B. DATED (SEE ITEM 11)
05/19/2017
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
0003 06/13/2017
6. ISSUED BY CODE W912BU 7. ADMINISTERED BY (If other than Item 6) CODE W912BU
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Answers to Questions received
Closing of the Request for Proposal will not be extended
Final questions have been received
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
QUESTIONS AND ANSWERS
FOR CONSTRUCTION INDUSTRIAL
W912BU-17-R-0010 SATOC
FOR CONSTRUCTION INDUSTRIAL SUPPORT SERVICES AT THE NAVAL
SURFACE WARFARE CENTER LAND BASED TEST SITES
QUESTION:
Could the Government please clarify the page limit requirements contained in Section 00 22 00 Page 4, Section 1.9. Specifically, do the page limit requirements only apply to Volume I, or do they apply to Volumes I and II combined? If Volume II counts towards the page limitations, are there any sections listed in Section 00 22 00 Page 3 of Volume II (Pro-Forma) that do not count towards that page limit?
RESPONSE:
The page limit requirements contained in Section 00 22 00 Page 4, Section 1.9 apply to Volume I, only. Volume II has no restriction on page count.
QUESTION:
In the Proposal Submission Requirements, it states that the offerors must submit the “Binding Labor Rate” sheet (Attachment 3). Does the Government intend that only the Base Wage rate be listed or should the offeror include Overhead, Fringes and G&A? If Indirect Costs are also included in the rates to be listed in Attachment 3, should the offeror include the Fee in that rate as well?
RESPONSE:
The labor rates the offerors submit on "Attachment 3" shall reflect the base wage rate plus standard labor burden (fringe benefits, unemployment compensation, social security, etc.), but shall not include overhead, general and administrative expense, or fee.