This is Section 02 41 00 (Demolition and Deconstruction) of the technical specifications for the Fort Randall Powerhouse Elevator Replacement project. The section outlines detailed requirements for demolition and removal work associated with replacing the passenger elevator, including specific procedures for utilities disconnection, material disposal, and worker protection.

The specification requires the contractor to prepare and submit both a Demolition/Deconstruction Plan and Core Plan before beginning work. Key requirements include: protecting existing facilities and utilities that are to remain in place; maintaining dust and debris control through temporary enclosures; proper disposal of removed materials off government property with no on-site storage or burning permitted; salvaging and recycling materials where possible; and patching/repairing surfaces damaged during removal work. Specific procedures are provided for removing mechanical equipment, utilities, masonry, concrete, structural steel, and the existing elevator/hoist equipment. All work must comply with safety requirements per EM 385-1-1 and ASSE/SAFE A10.6 standards, with continuous evaluation of structural conditions during demolition to prevent collapse.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Randall Powerhouse Elevator Replacement, newest first.
File Type Posted
AM_0004 Drawings.pdf PDF
14 21 23 Am-0004.pdf PDF
AM0004 SF30 W9128F25R0008.pdf PDF
01 22 00 Am-0004.pdf PDF
01 35 26 Am-0004.pdf PDF
AM0003 SF30 W9128F25R0008.pdf PDF
AM0002 SF30 W9128F25R0008.pdf PDF
AM_0002 Drawings.pdf PDF
14 21 23 Am-0002.pdf PDF
AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG_151.pdf PDF
01 35 26 Am-0001.pdf PDF
AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG E-150.pdf PDF
09 90 00 Am-0001.pdf PDF
14 21 23 Am-0001.pdf PDF
AM0001 SF30 W9128F25R0008.pdf PDF
Site Visit Roster.pdf PDF
ATTACHMENT 2.pdf PDF
FR00108 - ADVERTISEMENT.PDF PDF
W9128F25R0008_Fort_Randall_Elevator_Specs.pdf PDF
W9128F25R0008.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Powerhouse Passenger Elevator Replacement - Fort Randall Dam, SD FR00108

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 41 00

DEMOLITION AND DECONSTRUCTION

PART 1 GENERAL

1.1 REFERENCES

1.2 PROJECT DESCRIPTION

1.2.1 Demolition/Deconstruction Plan

1.2.2 Core Plan

1.2.3 General Requirements

1.3 ITEMS TO REMAIN IN PLACE

1.3.1 Existing Construction Limits and Protection

1.3.2 Utility Service

1.3.3 Facilities

1.4 BURNING

1.5 AVAILABILITY OF WORK AREAS

1.6 SUBMITTALS

1.7 QUALITY ASSURANCE

1.7.1 Dust and Debris Control

1.8 PROTECTION

1.8.1 Traffic Control Signs

1.8.2 Protection of Personnel

1.9 RELOCATIONS

1.10 EXISTING CONDITIONS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

3.1.1 Utilities and Related Equipment

3.1.1.1 General Requirements

3.1.1.2 Disconnecting Existing Utilities

3.1.2 Masonry

3.1.3 Concrete

3.1.4 Structural Steel

3.1.5 Miscellaneous Metal

3.1.6 Patching

3.1.7 Mechanical Equipment and Fixtures

3.1.8 Elevators and Hoists

3.2 DISPOSITION OF MATERIAL

3.2.1 Title to Materials

3.2.2 Reuse of Materials and Equipment

3.2.3 Transportation Guidance

3.2.4 Unsalvageable and Non-Recyclable Material

3.3 CLEANUP

3.4 DISPOSAL OF REMOVED MATERIALS

3.4.1 Regulation of Removed Materials

SECTION 02 41 00 Page 1

Am-0001

3.4.2 Burning on Government Property

3.4.3 Removal from Government Property

-- End of Section Table of Contents --

SECTION 02 41 00 Page 2

SECTION 02 41 00

DEMOLITION AND DECONSTRUCTION

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSE/SAFE A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations

ASTM INTERNATIONAL (ASTM)

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety and Occupational Health Requirements

U.S. DEFENSE LOGISTICS AGENCY (DLA)

DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviationengineering/HazInfo/

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures

MIL-STD-129 (2014; Rev R; Change 1 2018; Change 2 2019; Change 3 2023) Military Marking for Shipment and Storage

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels

SECTION 02 41 00 Page 3

1.2 PROJECT DESCRIPTION

1.2.1 Demolition/Deconstruction Plan

Prepare a Demolition/Deconstruction Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Coordinate with Waste Management Plan.

Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.

1.2.2 Core Plan

Prepare a Core Plan and submit for approval before work is started. Use GPR procedures before coring to avoid cutting the existing slab reinformcement. Include in the plan procedures for careful removal and disposition of materials, coordination with other work in progress, Provide procedures for safe conduct of the work in accordance with

EM 385-1-1 .

1.2.3 General Requirements

Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the building . The work includes demolition, deconstruction, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed.

Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , *Am-1 Section 23, **Am-1 Demolition, and other applicable Sections.

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.

Coordinate the work of this section with all other work indicated.

Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal deconstruction, or demolition work performed under this contract. Do not overload structural elements . Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, SECTION 02 41 00 Page 4 and debris from work areas daily.

1.3.2 Utility Service

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations.

1.3.3 Facilities

Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer.

Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted .

1.5 AVAILABILITY OF WORK AREAS

Areas in which the work is to be accomplished will be available in accordance with the project schedule.

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition/Deconstruction Plan; G -RO Core Plan; G -RO

Existing Conditions

SD-07 Certificates

Notification;

1.7 QUALITY ASSURANCE

Submit timely notification of demolition, and renovation projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M. Notify the State's environmental protection agency

SECTION 02 41 00 Page 5 and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.

1.7.1 Dust and Debris Control

Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.

Temporary enclosures shall be erected to contain all dust and dirt associated with removal and new construction work. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Vacuum and dust the work area daily .

1.8 PROTECTION

1.8.1 Traffic Control Signs

a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind blast. Notify the Contracting Officer prior to beginning such work.

1.8.2 Protection of Personnel

Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and deconstructed and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.

1.9 RELOCATIONS

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.

1.10 EXISTING CONDITIONS

Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.

SECTION 02 41 00 Page 6

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.

3.1.1 Utilities and Related Equipment

3.1.1.1 General Requirements

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition work until all utility disconnections have been made.

3.1.1.2 Disconnecting Existing Utilities

Remove existing utilities as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.

3.1.2 Masonry

Sawcut and remove masonry so as to prevent damage to surfaces to remain and to facilitate the installation of new work. Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as indicated and as specified for the new work. Provide square, straight edges and corners where existing masonry adjoins new work and other locations.

3.1.3 Concrete

Saw concrete if required along straight lines . Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face.

3.1.4 Structural Steel

Dismantle structural steel at field connections and in a manner that will prevent bending or damage.

3.1.5 Miscellaneous Metal

Scrap metal shall become the Contractor's property. Recycle scrap metal as part of demolition and deconstruction operations.

3.1.6 Patching

Where removals leave holes and damaged surfaces exposed in the finished

SECTION 02 41 00 Page 7 work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish.

3.1.7 Mechanical Equipment and Fixtures

Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse; provide to recycling service for disassembly and recycling of parts.

3.1.8 Elevators and Hoists

Remove elevators, hoists, and similar conveying equipment that will not be re-used as whole units, to the most practical extent.

3.2 DISPOSITION OF MATERIAL

3.2.1 Title to Materials

Except for salvaged items specified in drawings, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.

3.2.2 Reuse of Materials and Equipment

Remove and store materials and equipment indicated to be reused or relocated to prevent damage, and reinstall as the work progresses.

3.2.3 Transportation Guidance

Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .

3.2.4 Unsalvageable and Non-Recyclable Material

Dispose of unsalvageable and non-recyclable noncombustible material in the appropriate disposal area. Dispose of unsalvageable and non-recyclable combustible material in the sanitary fill area located off the site .

3.3 CLEANUP

Remove debris and rubbish from basement and similar excavations. Remove

SECTION 02 41 00 Page 8 and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

3.4 DISPOSAL OF REMOVED MATERIALS

3.4.1 Regulation of Removed Materials

Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified off the site . Storage of removed materials on the project site is prohibited.

3.4.2 Burning on Government Property

Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property .

3.4.3 Removal from Government Property

Transport waste materials removed from demolished and deconstructed structures from Government property for legal disposal.

-- End of Section --