This is a Governmental Safety Requirements specification (Section 01 35 26) for the Fort Randall Powerhouse Elevator Replacement project. The document outlines comprehensive safety protocols and requirements that must be implemented during construction, including fall protection, electrical safety, equipment operation, and accident prevention.
The specification requires development of an Accident Prevention Plan (APP), Activity Hazard Analysis (AHA), and various safety-specific plans including fall protection, rescue and evacuation, hazardous energy control, and site demolition plans. Key personnel requirements include a Site Safety and Health Officer (SSHO), Competent Persons for specialized work, and qualified trainers. The document details mandatory safety equipment, reporting procedures for accidents and near-misses, and specific protocols for high-risk activities such as electrical work, crane operations, and hot work. Monthly exposure reports must be submitted with billing requests, and safety meetings must be conducted regularly. The specification also addresses requirements for Load Handling Equipment (LHE), fall protection systems, and electrical safety procedures including arc flash protection and grounding requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AM0004 SF30 W9128F25R0008.pdf | ||
| 01 22 00 Am-0004.pdf | ||
| 01 35 26 Am-0004.pdf | ||
| AM_0004 Drawings.pdf | ||
| 14 21 23 Am-0004.pdf | ||
| AM0003 SF30 W9128F25R0008.pdf | ||
| AM0002 SF30 W9128F25R0008.pdf | ||
| AM_0002 Drawings.pdf | ||
| 14 21 23 Am-0002.pdf | ||
| AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG_151.pdf | ||
| AM0001 SF30 W9128F25R0008.pdf | ||
| AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG E-150.pdf | ||
| 09 90 00 Am-0001.pdf | ||
| 02 41 00 Am-0001.pdf | ||
| 14 21 23 Am-0001.pdf | ||
| Site Visit Roster.pdf | ||
| FR00108 - ADVERTISEMENT.PDF | ||
| W9128F25R0008_Fort_Randall_Elevator_Specs.pdf | ||
| W9128F25R0008.pdf | ||
| ATTACHMENT 2.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Powerhouse Passenger Elevator Replacement - Fort Randall Dam, SD FR00108
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
1.2.2 Competent Person, Fall Protection
1.2.3 Competent Person (CP) Trainer
1.2.4 High Risk Activities
1.2.5 High Visibility Accident
1.2.6 Load Handling Equipment (LHE)
1.2.7 Medical Treatment
1.2.8 Near Miss
1.2.9 Operating Envelope
1.2.10 Qualified Person (QP)
1.2.11 Qualified Person, Fall Protection (QP for FP)
1.2.12 Recordable Injuries or Illnesses
1.2.13 Government Property and Equipment
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.3 SUBMITTALS
1.4 MONTHLY EXPOSURE REPORTS
1.5 REGULATORY REQUIREMENTS
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
1.6.1.1.1 Additional Site Safety and Health Officer (SSHO)
Requirements and Duties
1.6.1.2 Competent Person Qualifications
1.6.1.2.1 Competent Person for Fall Protection
1.6.1.3 Qualified Trainer Requirements
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
1.6.3.2 Safety Meetings
1.7 ACCIDENT PREVENTION PLAN (APP)
1.7.1 ACCIDENT PREVENTION PLAN (APP)
1.7.2 Names and Qualifications
1.7.3 Plans
1.7.3.1 Standard Lift Plan (SLP)
1.7.3.2 Multi-Purpose Machines, Material Handling Equipment, and
Construction Equipment Lift Plan
1.7.3.3 Fall Protection and Prevention (FP&P) Plan
1.7.3.4 Rescue and Evacuation Plan
1.7.3.5 Hazardous Energy Control Program (HECP)
1.7.3.6 Asbestos Hazard Abatement Plan
SECTION 01 35 26 Page 1
Am-0001
1.7.3.7 Site Demolition Plan
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
1.8.1 AHA Management
1.8.2 AHA Signature Log
1.9 DISPLAY OF SAFETY INFORMATION
1.9.1 Safety Bulletin Board
1.9.2 Safety and Occupational Health (SOH) Deficiency Tracking System
1.10 SITE SAFETY REFERENCE MATERIALS
1.11 EMERGENCY MEDICAL TREATMENT
1.12 NOTIFICATIONS AND REPORTS
1.12.1 Mishap Notification
1.12.2 Accident Reports
1.12.3 LHE Inspection Reports
1.13 HOT WORK
1.13.1 Permit and Personnel Requirements
1.13.2 Work Around Flammable Materials
1.14 SEVERE STORM PLAN
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Hazardous Material Exclusions
3.1.3 Unforeseen Hazardous Material
3.2 FALL PROTECTION PROGRAM
3.2.1 Training
3.2.2 Fall Protection Equipment and Systems
3.2.2.1 Additional Personal Fall Protection Measures
3.2.2.2 Personal Fall Protection Equipment
3.2.3 Horizontal Lifelines (HLL)
3.2.4 Guardrails and Safety Nets
3.2.5 Rescue and Evacuation Plan and Procedures
3.3 EQUIPMENT
3.3.1 Material Handling Equipment (MHE)
3.3.2 Load Handling Equipment (LHE)
3.3.3 Machinery and Mechanized Equipment
3.3.4 Use of Explosives
3.4 ELECTRICAL
3.4.1 Conduct of Electrical Work
3.4.2 Qualifications
3.4.3 Arc Flash
3.4.4 Grounding
3.4.5 Testing
-- End of Section Table of Contents --
SECTION 01 35 26 Page 2
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B30.3 (2020) Tower Cranes
ASME B30.5 (2021) Mobile and Locomotive Cranes
ASME B30.8 (2020) Floating Cranes and Floating Derricks
ASME B30.9 (2018) Slings
ASME B30.20 (2018) Below-the-Hook Lifting Devices
ASME B30.22 (2016) Articulating Boom Cranes
ASME B30.26 (2015; R 2020) Rigging Hardware
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.34 (2021) Protection of the Public on or Adjacent to Construction Sites
ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations
ASSP Z244.1 (2016) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods
ASSP Z359.0 (2018) Definitions and Nomenclature Used for Fall Protection and Fall Arrest
ASSP Z359.1 (2020) The Fall Protection Code
ASSP Z359.2 (2017) Minimum Requirements for a Comprehensive Managed Fall Protection Program
ASSP Z359.3 (2019) Safety Requirements for Lanyards and Positioning Lanyards
ASSP Z359.4 (2013) Safety Requirements for Assisted-Rescue and Self-Rescue Systems, Subsystems and Components
SECTION 01 35 26 Page 3
ASSP Z359.6 (2016) Specifications and Design Requirements for Active Fall Protection Systems
ASSP Z359.7 (2019) Qualification and Verification Testing of Fall Protection Products
ASSP Z359.11 (2014) Safety Requirements for Full Body Harnesses
ASSP Z359.12 (2019) Connecting Components for Personal Fall Arrest Systems
ASSP Z359.13 (2013) Personal Energy Absorbers and Energy Absorbing Lanyards
ASSP Z359.14 (2014) Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems
ASSP Z359.15 (2014) Safety Requirements for Single Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems
ASSP Z359.16 (2016) Safety Requirements for Climbing Ladder Fall Arrest Systems
ASSP Z359.18 (2017) Safety Requirements for Anchorage Connectors for Active Fall Protection Systems
ASTM INTERNATIONAL (ASTM)
ASTM F855 (2019) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 1048 (2016) Guide for Protective Grounding of Power Lines
IEEE C2 (2023) National Electrical Safety Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers
NFPA 51B (2024) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2023) National Electrical Code
NFPA 70E (2024) Standard for Electrical Safety in the Workplace
SECTION 01 35 26 Page 4
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Occupational Health Requirements
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1910.333 Selection and Use of Work Practices
29 CFR 1910.1000 Air Contaminants
29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.16 Rules of Construction
29 CFR 1926.450 Scaffolds
29 CFR 1926.500 Fall Protection
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
1.2.2 Competent Person, Fall Protection
The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 *Am-1 Appendix Q **Am-1 and in accordance with ASSP Z359.0 , who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person (CP) Trainer
A competent person trainer as defined in EM 385-1-1 *Am-1 Appendix Q **Am-1 , who is qualified in the training material presented, and who possesses a working knowledge of applicable technical regulations, standards, SECTION 01 35 26 Page 5 equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.
1.2.4 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.
1.2.5 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.6 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.7 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even when provided by a physician or registered personnel.
1.2.8 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.9 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.10 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
SECTION 01 35 26 Page 6
1.2.11 Qualified Person, Fall Protection (QP for FP)
A QP for FP is a person meeting the definition requirements of EM 385-1-1 *Am-1 Appendix Q, **Am-1 and ASSP Z359.2 standard, having a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.
1.2.12 Recordable Injuries or Illnesses
Recordable Injuries or Illnesses are any work-related injury or illness that results in:
a. Death, regardless of the time between the injury and death, or the length of the illness;
b. Days away from work (any time lost after day of injury/illness onset);
c. Restricted work;
d. Transfer to another job;
e. Medical treatment beyond first aid;
f. Loss of consciousness; or
g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above
1.2.13 Government Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;
two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document an LHE mishap using the Crane High Hazard working group mishap reporting form (Available at local USACE Safety Office).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office
SECTION 01 35 26 Page 7 that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
ACCIDENT PREVENTION PLAN (APP); G, AO
SD-06 Test Reports
Monthly Exposure Reports
Notifications and Reports
Accident Reports; G, AO
LHE Inspection Reports
SD-07 Certificates
Standard Lift Plan; G, AO
Activity Hazard Analysis (AHA)
Hot Work Permit
1.4 MONTHLY EXPOSURE REPORTS
Provide a Monthly Exposure Report and attach to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this Contract, comply with the most recent edition of USACE EM 385-1-1 , and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
*Am-1
Provide an SSHO that meets the requirements of EM 385-1-1 Section 1 . The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and
SECTION 01 35 26 Page 8 qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs.
**Am-1
If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed.
Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
1.6.1.1.1 Additional Site Safety and Health Officer (SSHO) Requirements and Duties
The SSHO may also serve as the Quality Control Manager. The SSHO may not serve as the Superintendent. *Am-1 The Superintendent may also serve as Installation Supervisor. **Am-1
1.6.1.2 Competent Person Qualifications
Provide Competent Persons in accordance with EM 385-1-1 *Am-1 , Appendix Q **Am-1 and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e.
competent person, fall protection).
The Competent Person identified in the Contractor's Safety and Health Program and accepted Accident Prevention Plan, must be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for information in consultation with the Safety Office.
1.6.1.2.1 Competent Person for Fall Protection
Provide a Competent Person for Fall Protection who meets the requirements of EM 385-1-1 *Am-1 , Section 21.C.04, 21.B.03, **Am-1 and herein.
1.6.1.3 Qualified Trainer Requirements
Individuals qualified to instruct the 40 hour contract safety awareness course, or portions thereof, must meet the definition of a Competent Person Trainer, and, at a minimum, possess a working knowledge of the following subject areas: EM 385-1-1 , Electrical Standards, Lockout/Tagout, Fall Protection, Confined Space Entry for Construction;
Excavation, Trenching and Soil Mechanics, and Scaffolds in accordance with 29 CFR 1926.450 , Subpart L.
Instructors are required to:
a. Prepare class presentations that cover construction-related safety requirements.
b. Ensure that all attendees attend all sessions by using a class roster signed daily by each attendee. Maintain copies of the roster for at
SECTION 01 35 26 Page 9 least five years. This is a certification class and must be attended 100 percent. In cases of emergency where an attendee cannot make it to a session, the attendee can make it up in another class session for the same subject.
c. Update training course materials whenever an update of the EM 385-1-1 becomes available.
d. Provide a written exam of at least 50 questions. Students are required to answer 80 percent correctly to pass.
e. Request, review and incorporate student feedback into a continuous course improvement program.
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
The SSHO must:
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily production report.
b. Conduct mishap investigations and complete required accident reports.
Report mishaps and near misses.
c. Use and maintain OSHA's Form 300 to log work-related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors, and make available to the Contracting Officer upon request. Post and maintain the Form 300A on the site Safety Bulletin Board.
d. Maintain applicable safety reference material on the job site.
e. Attend the pre-construction conference , pre-work meetings including preparatory meetings, and periodic in-progress meetings.
f. Review the APP and AHAs for compliance with EM 385-1-1 , and approve, sign, implement and enforce them.
g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking System that lists and monitors outstanding deficiencies until resolution.
h. Ensure subcontractor compliance with safety and health requirements.
i. Maintain a list of hazardous chemicals on site and their material Safety Data Sheets (SDS).
j. Maintain a weekly list of high hazard activities involving energy, equipment, excavation, entry into confined space, and elevation, and be prepared to discuss details during QC Meetings.
k. Provide and keep a record of site safety orientation and indoctrination for Contractor employees, subcontractor employees, and site visitors.
SECTION 01 35 26 Page 10
Superintendent, QC Manager, and SSHO are subject to dismissal if the above or any other required duties are not being effectively carried out. If either the Superintendent, QC Manager, or SSHO is dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project must attend the preconstruction conference . This includes the project superintendent, Site Safety and Occupational Health Officer, quality control manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the Contract. This list of proposed AHAs will be reviewed and an agreement will be reached between the Contractor and the Contracting Officer as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, and Government review of AHAs to preclude project delays.
c. Deficiencies in the submitted APP, identified during the Contracting Officer's review, must be corrected, and the APP re-submitted for review prior to the start of construction. Work is not permitted to begin until an APP is established that is acceptable to the Contracting Officer.
1.6.3.2 Safety Meetings
Conduct safety meetings to review past activities, plan for new or changed operations, review pertinent aspects of appropriate AHA (by trade), establish safe working procedures for anticipated hazards, and provide pertinent Safety and Occupational Health (SOH) training and motivation.
Conduct meetings at least once a month for all supervisors at the project location. The SSHO, supervisors, foremen, or CDSOs must conduct meetings at least once a week for the trade workers. Document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the Contracting Officer of all scheduled meetings 7 calendar days in advance.
1.7 ACCIDENT PREVENTION PLAN (APP)
1.7.1 ACCIDENT PREVENTION PLAN (APP)
A qualified person must prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of EM 385-1-1 *Am-1 , Appendix A, and as supplemented herein. Cover all paragraph and subparagraph elements in EM 385-1-1 , Appendix A **Am-1 . The APP must be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP must interface with the
SECTION 01 35 26 Page 11
Contractor's overall safety and health program referenced in the APP in the applicable APP element, and made site-specific. Describe the methods to evaluate past safety performance of potential subcontractors in the selection process. Also, describe innovative methods used to ensure and monitor safe work practices of subcontractors. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the Contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
The APP must be signed by an officer of the firm (Prime Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated SSHO, the Contractor Quality Control Manager, and any designated Certified Safety Professional (CSP) or Certified Health Physicist (CIH). The SSHO must provide and maintain the APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor must provide an interpreter.
Submit the APP to the Contracting Officer 15calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. Once reviewed and accepted by the Contracting Officer, the APP and attachments will be enforced as part of the Contract. Disregarding the provisions of this Contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Continuously review and amend the APP, as necessary, throughout the life of the Contract. Changes to the accepted APP must be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and Quality Control Manager. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered. Should any severe hazard exposure (i.e. imminent danger) become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate and remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSP A10.34 ), and the environment.
1.7.2 Names and Qualifications
Provide plans in accordance with the requirements outlined in *Am-1 Appendix A of **Am-1 EM 385-1-1 , including the following:
a. Names and qualifications (resumes including education, training, experience and certifications) of site safety and health personnel designated to perform work on this project to include the designated Site Safety and Health Officer and other competent and qualified personnel to be used. Specify the duties of each position.
b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection;
hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents;
and personal protective equipment and clothing to include selection, SECTION 01 35 26 Page 12 use and maintenance.
1.7.3 Plans
Provide plans in the APP in accordance with the requirements outlined in *Am-1 Appendix A of **Am-1 EM 385-1-1 , including the following:
1.7.3.1 Standard Lift Plan (SLP)
Plan lifts to avoid situations where the operator cannot maintain safe control of the lift. Prepare a written SLP in accordance with EM 385-1-1 *Am-1 , Section 16.A.03, using Form 16-2 **Am-1 for every lift or series of lifts (if duty cycle or routine lifts are being performed). The SLP must be developed, reviewed and accepted by all personnel involved in the lift in conjunction with the associated AHA. Signature on the AHA constitutes acceptance of the plan. Maintain the SLP on the LHE for the current lift(s) being made. Maintain historical SLPs for a minimum of three months.
1.7.3.2 Multi-Purpose Machines, Material Handling Equipment, and Construction Equipment Lift Plan
Multi-purpose machines, material handling equipment, and construction equipment used to lift loads that are suspended by rigging gear, require proof of authorization from the machine OEM that the machine is capable of making lifts of loads suspended by rigging equipment. Written approval from a qualified registered professional engineer, after a safety analysis is performed, is allowed in lieu of the OEM's approval. Demonstrate that the operator is properly trained and that the equipment is properly configured to make such lifts and is equipped with a load chart.
1.7.3.3 Fall Protection and Prevention (FP&P) Plan
The plan must be in accordance with the requirements of EM 385-1-1 *Am-1 , Section 21.D **Am-1 and ASSP Z359.2 , be site specific, and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A competent person or qualified person for fall protection must prepare and sign the plan documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Review and revise, as necessary, the Fall Protection and Prevention Plan documentation as conditions change, but at a minimum every six months, for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Plan documentation at the job site for the duration of the project. Include the Fall Protection and Prevention Plan documentation in the Accident Prevention Plan (APP).
1.7.3.4 Rescue and Evacuation Plan
Provide a Rescue and Evacuation Plan in accordance with EM 385-1-1 *Am-1 Section 21.N **Am-1 and ASSP Z359.2 , and include in the FP&P Plan and as part of the APP. Include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used; training requirement;
specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility.
SECTION 01 35 26 Page 13
1.7.3.5 Hazardous Energy Control Program (HECP)
Develop a HECP in accordance with EM 385-1-1 *Am-1 Section 12 **Am-1 , 29 CFR 1910.147 , 29 CFR 1910.333 , 29 CFR 1915.89 , ASSP Z244.1 , and ASSP A10.44 . Submit this HECP as part of the Accident Prevention Plan (APP). Conduct a preparatory meeting and inspection with all effected personnel to coordinate all HECP activities. Document this meeting and inspection in accordance with EM 385-1-1 *Am-1 , Section 12.A.02 **Am-1 .
Ensure that each employee is familiar with and complies with these procedures.
1.7.3.6 Asbestos Hazard Abatement Plan
Identify the safety and health aspects of asbestos work, and prepare in accordance with Section 02 82 00 ASBESTOS REMEDIATION.
1.7.3.7 Site Demolition Plan
Identify the safety and health aspects, and prepare in accordance with Section 02 41 00 DEMOLITION AND DECONSTRUCTION and referenced sources.
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1 *Am-1 , Section 1 **Am-1 or as directed by the Contracting Officer. Submit the AHA for review at least 15 working days prior to the start of each activity task, or DFOW. The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.
AHAs must identify competent persons required for phases involving high risk activities, including confined entry, crane and rigging, excavations, trenching, electrical work, fall protection, and scaffolding.
1.8.1 AHA Management
Review the AHA list periodically (at least monthly) at the Contractor supervisory safety meeting, and update as necessary when procedures, scheduling, or hazards change. Use the AHA during daily inspections by the SSHO to ensure the implementation and effectiveness of the required safety and health controls for that work activity.
1.8.2 AHA Signature Log
Each employee performing work as part of an activity, task or DFOW must review the AHA for that work and sign a signature log specifically maintained for that AHA prior to starting work on that activity. The SSHO must maintain a signature log on site for every AHA. Provide employees
SECTION 01 35 26 Page 14 whose primary language is other than English, with an interpreter to ensure a clear understanding of the AHA and its contents.
1.9 DISPLAY OF SAFETY INFORMATION
1.9.1 Safety Bulletin Board
Prior to commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, may be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1 *Am-1 , Section 01.A.07 **Am-1 . Additional items required to be posted include:
a. Hot work permit.
1.9.2 Safety and Occupational Health (SOH) Deficiency Tracking System
Establish a SOH deficiency tracking system that lists and monitors the status of SOH deficiencies in chronological order. Use the tracking system to evaluate the effectiveness of the APP. A monthly evaluation of the data must be discussed in the QC or SOH meeting with everyone on the project. The list must be posted on the project bulletin board and updated daily, and provide the following information:
a. Date deficiency identified;
b. Description of deficiency;
c. Name of person responsible for correcting deficiency;
d. Projected resolution date;
e. Date actually resolved.
1.10 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in paragraph REFERENCES. Maintain applicable equipment manufacturer's manuals.
1.11 EMERGENCY MEDICAL TREATMENT
Contractors must arrange for their own emergency medical treatment in accordance with EM 385-1-1 . Government has no responsibility to provide emergency medical treatment.
1.12 NOTIFICATIONS AND REPORTS
1.12.1 Mishap Notification
Notify the Contracting Officer as soon as practical, but no more than twenty-four hours, after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 *Am-1 Appendix Q **Am-1 , any report of injury, illness, or any property damage. For LHE or rigging mishaps, notify the Contracting Officer as soon as practical but not more than four hours after mishap. The Contractor is responsible
SECTION 01 35 26 Page 15 for obtaining appropriate medical and emergency assistance and for notifying fire, law enforcement, and regulatory agencies. Immediate reporting is required for electrical mishaps, to include Arc Flash; shock;
uncontrolled release of hazardous energy (includes electrical and non-electrical); load handling equipment or rigging; fall from height (any level other than same surface); and underwater diving. These mishaps must be investigated in depth to identify all causes and to recommend hazard control measures.
Within notification include Contractor name; Contractt title; type of Contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (for example, type of construction equipment used and PPE used). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted. Assist and cooperate fully with the Government's investigation(s) of any mishap.
1.12.2 Accident Reports
a. Conduct an accident investigation for recordable injuries and illnesses, property damage, and near misses as defined in EM 385-1-1 , to establish the root cause(s) of the accident. Complete the applicable USACE Accident Report ENG Form 3394, and provide the report to the Contracting Officer within 5 calendar days of the accident.
The Contracting Officer will provide copies of any required or special forms.
b. Near Misses: For Army projects, report all "Near Misses" to the GDA, using local mishap reporting procedures, within 24 hrs. The Contracting Officer will provide the Contractor the required forms.
Near miss reports are considered positive and proactive Contractor safety management actions.
c. Conduct an accident investigation for any load handling equipment accident (including rigging accidents) to establish the root cause(s) of the accident. Complete the LHE Accident Report (Crane and Rigging Accident Report) form and provide the report to the Contracting Officer within 30 calendar days of the accident. Do not proceed with crane operations until cause is determined and corrective actions have been implemented to the satisfaction of the Contracting Officer. The Contracting Officer will provide a blank copy of the accident report form.
1.12.3 LHE Inspection Reports
Submit LHE inspection reports required in accordance with EM 385-1-1 and as specified herein with Daily Reports of Inspections.
1.13 HOT WORK
1.13.1 Permit and Personnel Requirements
Submit and obtain a written permit prior to performing "Hot Work" (i.e.
welding or cutting) or operating other flame-producing/spark producing devices, from the Contracting Officer's representative. Provide at least two 20 pound 4A:20 BC rated extinguishers for normal "Hot Work". The extinguishers must be current inspection tagged, and contain an approved
SECTION 01 35 26 Page 16 safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch must be trained in accordance with NFPA 51B and remain on-site for a minimum of one hour after completion of the task or as specified on the hot work permit.
When starting work in the facility, require personnel to familiarize themselves with the location of the nearest fire alarm boxes, the emergency response plan, and the location of emergency phone numbers/contacts. REPORT ANY FIRE, NO MATTER HOW SMALL, TO THE
RESPONSIBLE FIRE DEPARTMENT OR CONTRACTING OFFICER IMMEDIATELY.
1.13.2 Work Around Flammable Materials
Obtain permit approval from a NFPA Certified Marine Chemist, or Certified Industrial Hygienist for "HOT WORK" within or around flammable materials (such as fuel systems or welding/cutting on fuel pipes) or confined spaces (such as sewer wet wells, manholes, or vaults) that have the potential for flammable or explosive atmospheres.
Whenever these materials, except beryllium and chromium (VI), are encountered in indoor operations, local mechanical exhaust ventilation systems that are sufficient to reduce and maintain personal exposures to within acceptable limits must be used and maintained in accordance with manufacturer's instruction and supplemented by exceptions noted in EM 385-1-1 *Am-1 , Section 06.H **Am-1
1.14 SEVERE STORM PLAN
In the event of a severe storm warning, the Contractor must comply with the applicable Storm Plan and:
a. Secure outside equipment and materials and place materials that could be damaged in protected areas.
b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.
c. Ensure that temporary erosion controls are adequate.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
Comply with EM 385-1-1 , NFPA 70 , NFPA 70E, NFPA 241 , the APP, the AHA, Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
PPE is governed in all areas by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous areas or when performing noise hazardous tasks. Safety glasses must be worn or carried/available on each person. Mandatory PPE includes:
SECTION 01 35 26 Page 17
a. Hard Hat
b. Long Pants
c. Appropriate Safety Shoes
d. Appropriate Class Reflective Vests
3.1.1 Worksite Communication
Employees working alone in a remote location or away from other workers must be provided an effective means of emergency communications (i.e., cellular phone, two-way radios, land-line telephones or other acceptable means). The selected communication must be readily available (easily within the immediate reach) of the employee and must be tested prior to the start of work to verify that it effectively operates in the area/environment. Develop an employee check-in/check-out communication procedure to ensure employee safety.
3.1.2 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this Contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocyanates, lead-based paint, and hexavalent chromium, are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. Low mercury lamps used within fluorescent lighting fixtures are allowed as an exception without further Contracting Officer approval. Notify the Radiation Safety Officer (RSO) prior to excepted items of radioactive material and devices being brought on base.
3.1.3 Unforeseen Hazardous Material
Contract documents identify materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e.
29 CFR 1910.1000 ). If material(s) that may be hazardous to human health upon disturbance is/are encountered during construction operations, stop that portion of work, notify the Contracting Officer immediately and determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4 Changes and FAR 52.236-2 Differing Site Conditions.
3.2 FALL PROTECTION PROGRAM
*Am-1
Establish a fall protection program, for the protection of all employees exposed to fall hazards. Within the program include company policy, identify roles and responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, SECTION 01 35 26 Page 18 storage, care and maintenance of fall protection equipment and rescue and evacuation procedures in accordance with ASSP Z359.2 and EM 385-1-1 , Sections 21.A and 21.D .
3.2.1 Training
Institute a fall protection training program. As part of the Fall Protection Program, provide training for each employee who might be exposed to fall hazards and using personal fall protection equipment.
Provide training by a competent person for fall protection in accordance with EM 385-1-1 , Section 21.C . Document training and practical application of the competent person in accordance with EM 385-1-1 , Section 21.C.04 and ASSP Z359.2 in the AHA.
3.2.2 Fall Protection Equipment and Systems
Enforce use of personal fall protection equipment and systems designated (to include fall arrest, restraint, and positioning) for each specific work activity in the Site Specific Fall Protection and Prevention Plan and AHA at all times when an employee is exposed to a fall hazard. Protect employees from fall hazards as specified in EM 385-1-1 , Section 21 .
Provide personal fall protection equipment, systems, subsystems, and components that comply with EM 385-1-1 Section 21.I , 29 CFR 1926.500 Subpart M, ASSP Z359.0 , ASSP Z359.1 , ASSP Z359.2 , ASSP Z359.3 , ASSP Z359.4 , ASSP Z359.6 , ASSP Z359.7 , ASSP Z359.11 , ASSP Z359.12 , ASSP Z359.13 , ASSP Z359.14 , ASSP Z359.15 , ASSP Z359.16 and ASSP Z359.18 .
3.2.2.1 Additional Personal Fall Protection Measures
In addition to the required fall protection systems, other protective measures such as safety skiffs, personal floatation devices, and life rings, are required when working above or next to water in accordance with EM 385-1-1 , Sections 21.O through 21.O.06 . Personal fall protection systems and equipment are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall protection systems are required when operating other equipment such as scissor lifts. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, travel, or while performing work.
3.2.2.2 Personal Fall Protection Equipment
Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. The use of body belts is not acceptable. Harnesses must have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system. Snap hooks and carabineers must be self-closing and self-locking, capable of being opened only by at least two consecutive deliberate actions and have a minimum gate strength of 3,600 lbs in all directions. Use webbing, straps, and ropes made of synthetic fiber. The maximum free fall distance when using fall arrest equipment must not exceed 6 feet, unless the proper energy absorbing lanyard is used. Always take into consideration the total fall distance and any swinging of the worker (pendulum-like motion), that can occur during a fall, when attaching a person to a fall arrest system. Equip all full body harnesses with Suspension Trauma Preventers such as stirrups, relief steps, or similar in order to provide short-term relief from the effects of orthostatic intolerance in accordance with
SECTION 01 35 26 Page 19
EM 385-1-1 , Section 21.I.06 .
3.2.3 Horizontal Lifelines (HLL)
Provide HLL in accordance with EM 385-1-1 , Section 21.I.08.d.2 .
Commercially manufactured horizontal lifelines (HLL) must be designed, installed, certified and used, under the supervision of a qualified person, for fall protection as part of a complete fall arrest system which maintains a safety factor of 2 ( 29 CFR 1926.500 ). The competent person for fall protection may (if deemed appropriate by the qualified person) supervise the assembly, disassembly, use and inspection of the HLL system under the direction of the qualified person. Locally manufactured HLLs are not acceptable unless they are custom designed for limited or site specific applications by a Registered Professional Engineer who is qualified in designing HLL systems.
3.2.4 Guardrails and Safety Nets
Design, install and use guardrails and safety nets in accordance with EM 385-1-1 , Section 21.F.01 and 29 CFR 1926 Subpart M.
3.2.5 Rescue and Evacuation Plan and Procedures
When personal fall arrest systems are used, ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. Prepare a Rescue and Evacuation Plan and include a detailed discussion of the following: methods of rescue; methods of self-rescue or assisted-rescue;
equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility. Include the Rescue and Evacuation Plan within the Activity Hazard Analysis (AHA) for the phase of work, in the Fall Protection and Prevention (FP&P) Plan, and the Accident Prevention Plan (APP). The plan must be in accordance with the requirements of EM 385-1-1 , ASSP Z359.2 , and ASSP Z359.4 .
**Am-1
3.3 EQUIPMENT
3.3.1 Material Handling Equipment (MHE)
a. Material handling equipment such as forklifts must not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions. Material handling equipment fitted with personnel work platform attachments are prohibited from traveling or positioning while personnel are working on the platform.
b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions. Material Handling Equipment Operators must be trained in accordance with OSHA 29 CFR 1910 , Subpart N.
c. Operators of forklifts or power industrial trucks must be licensed in accordance with OSHA.
3.3.2 Load Handling Equipment (LHE)
The following requirements apply. In exception, these requirements do not
SECTION 01 35 26 Page 20 apply to commercial truck mounted and articulating boom cranes used solely to deliver material and supplies (not prefabricated components, structural steel, or components of a systems-engineered metal building) where the lift consists of moving materials and supplies from a truck or trailer to the ground; to cranes installed on mechanics trucks that are used solely in the repair of shore-based equipment; to crane that enter the activity but are not used for lifting; nor to other machines not used to lift loads suspended by rigging equipment. However, LHE accidents occurring during such operations must be reported. Fort Randall equipment or personnel will not be available for Contractor material unloading.
*Am-1
a. Equip cranes and derricks as specified in EM 385-1-1 , Section 16 .
b. Notify the Contracting Officer 15 working days in advance of any LHE entering the activity, in accordance with EM 385-1-1 , Section 16.A.02, so that necessary quality assurance spot checks can be coordinated.
Contractor's operator must remain with the crane during the spot check. Rigging gear must be in accordance with OSHA, ASME B30.9 Standards and federal, state, and local safety standards.
c. Comply with the LHE manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work.