This is a Measurement and Payment specification section (01 22 00) for the Fort Randall Powerhouse Elevator Replacement project that details how work will be measured and paid across 8 Contract Line Item Numbers (CLINs). The document outlines the scope and payment terms for: mobilization/demobilization (CLIN 0001), fire-rated shaftwall construction (CLIN 0002), plumbing and HVAC improvements (CLIN 0003), electrical improvements (CLIN 0004), elevator improvements (CLIN 0005), fire system improvements (CLIN 0006), other structural work (CLIN 0007), and optional asbestos abatement (CLIN 0008).
The specification establishes that payments will be made on a progressive basis according to percentage of work completed for each CLIN. Key work elements include: elevator equipment replacement, cab interior refinishing, fire barrier systems, sprinkler modifications, HVAC installations, electrical upgrades, smoke detector installations, and structural improvements like ladder replacement. The document specifies that all work must comply with contract drawings and specifications to provide a fully functioning elevator system meeting current life safety standards. Training, as-built documentation, and O&M manuals are included under CLIN 0007.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AM_0004 Drawings.pdf | ||
| 14 21 23 Am-0004.pdf | ||
| AM0004 SF30 W9128F25R0008.pdf | ||
| 01 35 26 Am-0004.pdf | ||
| AM0003 SF30 W9128F25R0008.pdf | ||
| AM0002 SF30 W9128F25R0008.pdf | ||
| AM_0002 Drawings.pdf | ||
| 14 21 23 Am-0002.pdf | ||
| AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG_151.pdf | ||
| 01 35 26 Am-0001.pdf | ||
| AM0001_W9128F25R0008_Fort_Randall_Elevator_DRWG E-150.pdf | ||
| 09 90 00 Am-0001.pdf | ||
| 02 41 00 Am-0001.pdf | ||
| 14 21 23 Am-0001.pdf | ||
| AM0001 SF30 W9128F25R0008.pdf | ||
| Site Visit Roster.pdf | ||
| ATTACHMENT 2.pdf | ||
| FR00108 - ADVERTISEMENT.PDF | ||
| W9128F25R0008_Fort_Randall_Elevator_Specs.pdf | ||
| W9128F25R0008.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Powerhouse Passenger Elevator Replacement - Fort Randall Dam, SD FR00108
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 CLIN 0001: Mobilization and Demobilization
1.1 Work Included
1.2 Measurement
1.3 Payment
PART 2 CLIN 0002: Fire Rated Shaftwall Construction
2.1 Work Included
2.2 Measurement
2.3 Payment
PART 3 CLIN 0003: Plumbing and HVAC Improvements
3.1 Work Included
3.2 Measurement
3.3 Payment
PART 4 CLIN 0004: Electrical Improvements
4.1 Work Included
4.2 Measurement
4.3 Payment
PART 5 CLIN 0005: Elevator Improvements
5.1 Work Included
5.2 Measurement
5.3 Payment
PART 6 CLIN 0006: Fire System Improvements
6.1 Work Included
6.2 Measurement
6.3 Payment
PART 7 CLIN 0007: All Other Work
7.1 Work Included
7.2 Measurement
7.3 Payment
PART 8 CLIN 0008: Additional Asbestos Abatement Work
8.1 Work Included
8.2 Measurement
SECTION 01 22 00 Page 1
Am-0004
8.3 Payment
-- End of Section Table of Contents --
SECTION 01 22 00 Page 2
SECTION 01 22 00
MEASUREMENT AND PAYMENT
SCOPE: This section covers the methods and procedures which will be used to measure the Contractor's work and to effect payment.
GENERAL: The general outline of the principal features of each item as listed does not in any way limit the responsibility of the Contractor for making a thorough investigation of the Drawings and Specifications to determine the scope of work under the entire Contract. Payment to the Contractor of the amounts based on the quantities of work as measured in accordance with the specified methods of measurement and the prices stipulated in the accepted proposal will constitute complete compensation for all work shown on the Drawings, provided in the specifications or other Contract Documents and all costs of accepting the general risks, liabilities and obligations expressed or implied. Payment under all items shall include, but not necessarily be limited to, compensation for furnishing all supervision, labor, equipment, and materials and services (including overhead and profit), as well as performing all work required to accomplish and complete the work specified under each item and all other work required.
JOB ITEMS
Quantities: The quantities under Job items will not be measured except for the purpose of determining reasonable interim payments.
Interim Payments (or Progressive Payments): Interim payments will be made in accordance with the estimated value of work done as determined by the Contracting Officer Representative (COR) or as specified in this section, and in accordance with contract clause for payments.
UNIT PRICE ITEMS
Payments to Contractor: For unit priced items, payments will be made to the Contractor and approved by the COR in accordance with measurements for the unit prices entered in the proposal schedule.
Interim Measurement/Payments: Interim measurements and/or payments maybe adjusted to take account of partially completed work.
BASE ITEMS
PART 1 CLIN 0001: Mobilization and Demobilization
1.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed for operations necessary to move personnel, equipment, supplies and incidentals to the project site; to perform all other work and operations,including costs incurred, before beginning work on the project; and to complete similar demobilization activities.
SECTION 01 22 00 Page 3
1.2 Measurement
Job.
1.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0001 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 2 CLIN 0002: Fire Rated Shaftwall Construction
2.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed for constructing the fire rated shaft wall and barrier system, door frame, and door as in accordance with contract requirements as demonstrated by formal approval of a firestopping inspection.
2.2 Measurement
Job.
2.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0002 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 3 CLIN 0003: Plumbing and HVAC Improvements
3.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed for sealing of hoistway penetrations, concrete cutting for duct installation, demo, removal, and reinstallation of existing heating/cooling equipment, installation of heaters, fans, ducts, motorized dampers, roof penthouse (including any required roofing work per requirements found in 01 12 00 paragraph 1.10k), and all other materials required to install the hoistway pressurization system and machine room heating/cooling equipment.
3.2 Measurement
Job.
3.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0003 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 4 CLIN 0004: Electrical Improvements
4.1 Work Included
*Am-4
The work of this item shall include but not be limited to labor and
SECTION 01 22 00 Page 4 equipment needed for demo of existing materials and equipment, removal and reinstallation of existing equipment, and installation of cables, conduits, wiring, light fixtures, receptacles, switches, and power feeds to miscellaneous equipment in accordance with contract requirements.
The work of this item shall include but not be limited to labor and equipment needed for demo of existing materials and equipment, removal of asbestos containing wiring and reinstallation of existing equipment, and installation of cables, conduits, wiring, light fixtures, receptacles, switches, and power feeds to miscellaneous equipment in accordance with contract requirements.
**Am-4
4.2 Measurement
Job.
4.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0004 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 5 CLIN 0005: Elevator Improvements
5.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed for demo, salvage, reinstallation, and replacement of elevator equipment in accordance with contract requirements. This will include but not be limited to refinishing the interior of the elevator cab, repainting the existing elevator landing doors and thresholds, and replacing all elevator signage, replacement of elevator equipment, elevator controller, elevator governor, and hoisting machines.
5.2 Measurement
Job.
5.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0005 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 6 CLIN 0006: Fire System Improvements
6.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed to modify an existing sprinkler system including the addition of pipe, fittings, flow switch, sprinkler heads, fire alarm warning device, water valve tamper switch, heat detector, shunt trip panel, replacement existing and installation of new photoelectric smoke detectors, and programming of the elevator fire alarm system.
SECTION 01 22 00 Page 5
6.2 Measurement
Job.
6.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0006 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
PART 7 CLIN 0007: All Other Work
7.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed to complete structural work items including but not limited to replace the existing ladder at ELE. 1244.0 in compliance with EM 385-1-1 as shown on the contract drawings. This CLIN also includes but is not limited to providing work to bring elevator system up to existing life safety and elevator standards; and any other incidental and customarily performed work needed to complete work as required by this contract but not covered by other CLINS including assurance of coordination between all contractors and subcontractors to ensure interrelated work items are coordinated and tested to provide a fully functioning system as described by the contract plans and specifications.
All training, asbuilts, and O&M manual related activities are to be covered under this CLIN.
7.2 Measurement
Job.
7.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0007 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
OPTIONAL ITEMS
PART 8 CLIN 0008: Additional Asbestos Abatement Work
8.1 Work Included
The work of this item shall include but not be limited to labor and equipment needed to complete additional asbestos abatement for lighting circuit at elevation 1307.
8.2 Measurement
Job.
8.3 Payment
Payment for this item shall be the Job amount indicated for item No. 0008 on the pricing schedule, made on a progressive basis, based on the percentage of work completed.
-- End of Section --