Solicitation Amendment 0003 W9128F25BA0010003 SF 30.pdf

PDF 3 MB Posted

Attached to
Missouri River Levee R-562 Repair
Solicitation number
W9128F25BA001
Issued by

About this file

This document is a Solicitation Amendment (SF 30) for the Missouri River Levee R-562 Repair project issued by the U.S. Army Corps of Engineers, Omaha District. The amendment incorporates Project Labor Agreement (PLA) requirements into Sections 00 70 00 and 00 73 00, specifically adding FAR clauses 52.222-33 and 52.222-34 related to project labor agreements. As a result of these material changes, the Step 1 proposal due date is extended to 17 June 2025 at 2:00 PM local time, with a web meeting scheduled for 13 June 2025 at 1:00 PM to discuss PLA details.

Key modifications include changing the period of performance from 10 July 2025 - 30 June 2027 to 09 September 2025 - 30 August 2027. The amendment requires the apparent low bidder to submit a Project Labor Agreement within seven days after bid opening, with specific requirements such as binding all contractors and subcontractors, allowing open competition, providing guarantees against work disruptions, and establishing labor dispute resolution procedures. The project is a large-scale construction project estimated between $25-50 million, located in Peru, Nebraska, and is restricted to small businesses under NAICS code 237990 with a size standard of $45 million.

View the file

Other files

File Type Posted
Bid Abstract - MR562.xlsx XLSX spreadsheet
AMD 0008 R562Bid_Schedule 9.24.2025.pdf PDF
Solicitation Amendment 0008 W9128F25BA0010008 SF 30.pdf PDF
AMD 0007 - 31 35 19.16.pdf PDF
AMD 0007 - R562Volume3_3DrawingsCF600toCF920R.pdf PDF
AMD 0007 - 01 22 00.pdf PDF
AMD 0007 - 35 31 19.pdf PDF
AMD 0007 - R562Volume2of3DrawingsCF300toCF509R.pdf PDF
Solicitation Amendment 0007 W9128F25BA0010007 SF 30.pdf PDF
AMD 0007 - NE20250049 Nemaha Otoe County 9.4.2025.pdf PDF
AMD 0007 Amendment Narrative W9128F26BA001 Att 0003.docx DOCX document
AMD 0007 - Att 0001 Bid Schedule.pdf PDF
AMD 0007 - R562Volume1of3DrawingsG003_CF272.pdf PDF
Amendment 0006 SF30 W9128F25BA0010006.pdf PDF
Amendment 0005 SF30 W9128F25BA0010005.pdf PDF
R562Volume6of6DrawingsCF901_BI005.pdf PDF
R562Volume5of6DrawingsCF651_CF871.pdf PDF
R562Volume4of6DrawingsCF361_CF621A.pdf PDF
R562Volume3of6DrawingsCF300_CF352.pdf PDF
R562Volume2of6DrawingsCF256_CF272.pdf PDF
R562Volume1of6DrawingsG001_CF256.pdf PDF
Solicitation W9128F25BA0010004 Step Two.pdf PDF
Successful Step-1 Company List.docx DOCX document
W9128F25BA001 R-562 Specs Step 2.pdf PDF
Amendment 0004 SF30 W9128F25BA001.pdf PDF
Att 0001 BID SCHEDULE.pdf PDF
Site Visit Attendee List 5.6.2025.pdf PDF
W9128F25BA0010002 SF 30.pdf PDF
Solicitation Amendment W9128F25BA0010001 SF 30.pdf PDF
Solicitation Amendment - W9128F25BA0010001.pdf PDF
R562-step-1-Plans_Vol1.pdf PDF
R562-step-1-Plans_Vol3.pdf PDF
R562-step-1-Plans_Vol2.pdf PDF
Att 0002 W9128F25BA001 R-562 specs step1.pdf PDF
Att 0002 - W9128F25BA001 R-562 specs.pdf PDF
Att 0004 - NE20250049 Nemaha Otoe County 3.14.2025.pdf PDF
Att 0001 - MR-562 BID SCHEDULE.docx DOCX document
W9128F25BA001 Step 1.pdf PDF
Att 0003 - PPQ forms.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

Missouri River Levee R562 Repair, Peru, NE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): This amendment incorporates Project Labor Agreement (PLA) requirements into Section 00 73 00 and Section 00 70 00 in FAR clauses 52.222-33 'Notice of Requirement for Project Labor Agreement Alternate I" and 52.222-34 'Project Labor Agreement'.

Due to the material nature of PLA requirements, the Step 1 proposal due date is extended to 17 June 2025 at 2:00 PM local time. New interested offerors may submit Step 1 proposals for consideration.

Interested offerors who have already submitted Step 1 proposals can let their proposal stand or submit a revised proposal by the due date/time. Any proposal revision should be highlighted or annotated in some manner that shows the change from the original proposal. Interested offerors who have already submitted Step 1 proposals will not be informed of their preliminary evaluation results.

The contracting officer will host a web meeting on 13 June 2025 at 1:00 PM local time to discuss the PLA topic. Interested offerors should RSVP to Karen Caskey at karen.l.caskey@usace.army.mil and Lee McCormick at lee.m.mccormick@usace.army.mil with the email address(es) to send the meeting invite to and a list of participants.

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Response Due Date 16 May 2025 17 Jun 2025

W9128F25BA0010003

Section 00 70 00 - Conditions of the Contract

Additional Information/Notes

The following clauses were added:

FAR Clauses Incorporated by Full Text

52.222-33 Notice of Requirement for Project Labor Agreement (Alternate I) (Jan 2024)Alternate I(Jan 2024)

Alternate I . As prescribed in (a)(2), substitute the following paragraphs (b) and (e) for (Jan 2024) 22.505 paragraphs (b) and (e) of the basic provision.

(b) The apparent successful offeror shall-

(1) Negotiate or become a party to a project labor agreement with one or more labor organizations for the term of the resulting construction contract; and

(2) Require its subcontractors to become a party to the resulting project labor agreement.

(e) The apparent successful offeror shall submit to the Contracting Officer a copy of the project labor agreement prior to contract award.

52.222-34 Project Labor Agreement. (Jan 2024)

Project Labor Agreement (Jan 2024)

(a) . As used in this clause-Definitions

Construction means construction, reconstruction, rehabilitation, modernization, alteration, conversion, extension, repair, or improvement of buildings, structures, highways, or other real property.

Labor organization means a labor organization as defined in 29 U.S.C. 152(5) of which building and construction employees are members.

Large-scale construction project means a Federal construction project within the United States for which the total estimated cost of the construction contract(s) to the Federal Government is $35 million or more.

Project labor agreement means a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f).

(b) The Contractor shall maintain in a current status throughout the life of the contract the project labor agreement entered into prior to the award of the contract.

(c) . The Contractor shall include the substance of this clause, including this paragraph (c),Subcontracts in subcontracts with subcontractors engaged in construction on the construction project.

(End of clause)

Section 00 73 00 - Supplementary Conditions

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Period of Performance 10 Jul 2025 to 30 Jun 2027 09 Sep 2025 to 30 Aug 2027

Miscellaneous text in this section has been added to:

Project Labor Agreement

Within seven (7) days after bid opening, the apparent low bidder must submit a Project Labor Agreement (PLA) as required for large-scale construction projects in accordance with FAR 22.503 and FAR Clause 52.222-33 Alternate I. The Government is not a party to the PLA. If the apparent low bidder does not submit an acceptable PLA, they will not be eligible for award and the contracting officer may move on the second low bidder.

At a minimum, the proposed PLA must address the requirements in FAR 22.504(b), which states a project labor agreement shall -

(1) Bind all contractors and subcontractors engaged in construction on the construction project to comply with the project labor agreement;

(2) Allow all contractors and subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;

(3) Contain guarantees against strikes, lockouts, and similar job disruptions;

(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;

(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and

(6) Include any additional requirements as the agency deems necessary to satisfy its needs.

IDCode: J
Page: 1
Pages: 6
AmendNo: 0003
EffDate: 09 JUN 2025
ReqNo:
ProjNo: 11110
IssCode: W9128F
AdmCode:
IssuedBy: W071 ENDIST OMAHA

KO CONTRACTING OFFICE, 1616 CAPITOL AVENUE

OMAHA, NE 68102-4901

UNITED STATES

KAREN CASKEY, EMAIL: KAREN.L.CASKEY@USACE.ARMY.MIL TELEPHONE: 402-995-2047

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W9128F25BA001
SolDate: 25 APR 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: SEE SCHEDULE
ContNameTitle:
CoNameTitle:
ContDate:
CODate:

File details come from the government source that posted it. Updated .