LOWER BRULE ELEMENT 1 SIte Visit Agenda.pdf
PDF 156 KB Posted
- Attached to
- Big Bend Lower Brule Bank Stabilization Federal contract opportunity
- Solicitation number
- W9128F25B0005
About this file
This document is a meeting agenda for a pre-bid site visit for a federal construction project. The project, titled "Lower Brule Bank Stabilization Element 1", is being solicited by the U.S. Army Corps of Engineers, Omaha District under Solicitation Number W9128F25B0005.
The key details are:
- This is a single-step sealed bid procurement using FAR Part 14 procedures. Bids will be evaluated on price and price-related factors without discussions.
- The project consists of 11 contract line items (CLINs) for work such as placement of geotextile, clay layer, riprap, excavation, fill, and aggregate surface course.
- The period of performance is 420 days from notice to proceed, with $1,931 per day in liquidated damages for late completion.
- Technical inquiries must be submitted via ProjNet by 3pm Central on November 22, 2024.
- Bidders must email their proposals to the Contracting Officer and Specialist by the due date stated in the solicitation.
- Davis-Bacon labor rates and Buy American requirements apply.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
MEETING AGENDA
PRE-BID MEETING / SITE VISIT
A. Introductions:
CD/PM
B. Project Goals
1. Safety
2. Quality
3. Performance of finished product
C. Contract Items
1. Contracting Officer: Nadine Catania, Omaha
2. Contracting POC: Wayne Weidenhamer, Omaha
3. Contracting Officer Representative: Orlando Maldonado, Fort Randall
4. Govt. Quality Assurance Representative: Orlando Maldonado, Fort Randall
5. Local Onsite Representative:
6. Communication during Solicitation: The solicitation documents and amendments will be posted to https://www.sam.gov/ and will be available by internet access only. The bidder is responsible for checking the website for any amendments.
7. Instruction for Procurement: This solicitation and resulting contract are utilizing a
Single Step Sealed Bidding procurement method as described in FAR Part 14. In accordance with 52.214-19 Contract Award-Sealed Bidding-Construction in
Section 00 21 00 (Instructions), the Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to
Government, considering only price and the price-related factors specified elsewhere in the solicitation.
NAME OF PROJECT:
MEETING LOCATION:
DATE & TIME:
SOLICITATION NO:
Lower Brule Bank Stabilization Element 1
Lower Brule Rec/Boat Ramp
November 15, at 9:00 AM (CST)
W9128F25B0005 http://www.sam.gov/
2 | P a g e
8. Technical Inquiries: Technical inquiries and questions relating to technical requirements, bidding procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than 3pm
Central Time on 22 November 2024
9. Bonding: Performance and Payment bonding are required for this contract. Bid bonds shall be submitted on Standard Form 24 (SF24).
10. Insurance: Spec 01 30 00.24 part 1.11 lists the minimum required insurance that a contractor must have for this project.
11. Period of Performance: The Contractor will be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives Notice to Proceed, (b) prosecute work diligently, and (c) complete the entire work ready for use no later than 420 days after receipt of Notice to
Proceed. Time stated for completion shall include final cleanup. The period of performance is mandatory.
12. Liquidated Damages: Liquated damages for this project are 1,931.00 for each calendar day of delay until the work is completed or accepted. (Clause 52.211-
12).
13.
14. Contractor Allowed Working Hours: The Contractor can work Monday through
Friday, 0700 to 1700 hours. Working outside of these hours will need written permission from the COR at least 14 days in advance of need and is not guaranteed. The Contractor will not be allowed to work on Federal holidays
(Spec 01 12 00 part 1.16).
15. Security Requirements: Antiterrorism (AT)/Operations Security (OPSEC)
Provisions
AT Level 1 – Online training certificate required by all proposed workers iWATCH Training – Certificate required for Superintendent. All other workers are to be briefed by the Superintendent on the iWATCH program.
OPSEC Training – Online training certificate required by all proposed workers.
E-Verify – Online verification for all proposed workers to be onsite
Contractor Cybersecurity Compliance (Spec 01 30 00.24 1.2)
16. Davis Bacon: Davis Bacon rules will apply to this project. See spec 01 30 00.24
1.18 for more information. Contractor must pay in accordance with listed wage rates (refer to wage determination in specs).
3 | P a g e
17. Buy American: Contractor is to obtain materials in compliance with the Buy
American statute per the requirements in spec 01 33 00
18. Submittals: Submittals are to be completed in accordance with specification 01
33 00. The Submittal Register, located at end of specification 01 33 00, lists the required submittals; please note that some administrative submittals may not show up in submittal register. Review plans and specs for all required submittals.
19. RMS: The Government will use the RMS system to process submittals, requests for information (RFI’s), serial letters, daily reports, and progress payments. See spec 01 45 00.15 10 for more information.
20. CQC / Superintendent / SSHO Requirements: The CQC System Manager, Project
Superintendent, and Site Safety and Health Officer must be assigned a minimum of two qualified personnel (one individual cannot serve all three positions). If an individual is assigned responsibilities of multiple positions, they must meet all the required qualifications of both positions.
1. Contractor Quality Control (CQC) System Manager – Refer to spec
01 45 00.00 10
2. Site Safety & Health Officer (SSHO) – Refer to spec 01
35 26
3. Project Superintendent – Refer to spec 01 45 00.00
21. Bid Schedule This contract consists of a basic bid section (three base bid items) and an option bid section (five option bid items). Contractors are highly encouraged to review the project plan sheets and as they prepare their bid proposals. Overall, the work under this contract includes the following:
CLIN 0001 – Entire work, complete, for placement of the L-Head
Breakwater Structures (placement of Geotextile (≈4,000 SY), Clay Layer
(≈7,100 CY) and random fill (≈7,300 CY)) as shown on the drawings and in the specifications.
CLIN 0002 – Entire work, complete, for all plant, material, and labor required for: Stone (Riprap) as shown on the drawings and in the specifications
CLIN 0003 – Entire work, complete, for all plant, material, and labor required for: Spalls and Underwater Fill as shown on the drawings and in the specifications
4 | P a g e
CLIN 0004 – Entire work, complete, for aggregate surface course as shown on the drawings and in the specifications
CLIN 0005 Entire work, complete, for All plant, material, and labor required for: Excavation Cut as shown on the drawings and in the
CLIN 0006 Entire work, complete, for All plant, material, and labor required for: Excavation Fill as shown on the drawings and in the
CLIN 0007 Entire work, complete, for All plant, material, and labor required for: Disposal Excess Material as shown on the drawings and in the specifications
CLIN 0008 Entire work, complete, for All plant, material, and labor required for: Loamy Topsoil Material as shown on the drawings and in the
CLIN 0009 Entire work, complete, for All plant, material, and labor required for: Placement of culvert pipes as shown on the drawings and in the specifications
CLIN 0010 Entire work, complete, for the mobilization/ demobilization of all equipment as shown on the drawings & in the specifications
CLIN 0011 All remaining work
22. CONSTRUCTION GENERAL SECTION 01 12 00
CONSTRUCTION RIGHT-OF-WAY: The Contractor will be assigned working areas or working right-of-way limits for use in the prosecution of work under this contract.
PROTECTION OF EXISTING FACILITIES AND WORKS: The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started.
CARE OF WATER: Full responsibility for care of water shall be borne by the
Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate construction and to protect the work from damage by water.
5 | P a g e
Access Roads: Access roads as required for the prosecution of the work shall be maintained (including sprinkling for dust control, safety personnel, and traffic control) within the work areas assigned to the Contractor.
Haul Roads: The Contractor shall construct haul roads as may be necessary for the conduct of the work without additional cost to the Government.
Erosion and Sediment Controls: Providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations is the Contractor's responsibility. The erosion and sediment controls selected and maintained by the
Contractor shall be such that water quality standards are not violated as a result of construction activities.
PLANTING
All planting and maintenance of trees and shrubs shall be conducted under the supervision of a qualified forester or nurseryman. The supervisor must be a graduate from an accredited college or university in the field of forestry and have a minimum three years of tree planting experience or have equivalent experience in the field of forestry and nursery planting.
GENERAL BIDDING INFORMATION
Bidders shall e-mail bids to the below individuals no later than the date and time established in Block 13 of the Standard Form (SF) 1442, or Block 14 of the most recent SF 30, as applicable:
Nadine Catania, Contracting Officer Nadine.L.Catania@usace.army.mil
Wayne Weidenhamer, Contract Specialist: wayne.c.weidenhamer@usace.army.mil
Each email shall contain the following information:
a. Solicitation No: W9128F25B0005
b. Bid Due Date and Time: See Section SF1442 (00 10 00 page 1)
c. Bid Validity Date: 60 Days
Bidders shall submit all questions via Bidder Inquiry in ProjNet, at https://www.projnet.org/projnet/.
23. The Solicitation Number is: W9128F25B0005
24. The Bidder Inquiry Key # is: QNZ5QN-D8HZ5N
25. All timely questions and approved answers will be made available through
ProjNet.
mailto:Nadine.L.Catania@usace.army.mil https://www.projnet.org/projnet/