This is Amendment 0002 to solicitation W9128F25B0005 for the Lower Brule Bank Stabilization Project at Big Bend Dam in Ft. Thompson, SD, issued by the U.S. Army Corps of Engineers, Omaha District. The amendment extends the bid due date to December 17, 2024 at 2:00 PM local time.
The amendment revises several specifications (01 41 26.01 24, 01 57 20.00 10, 01 57 20.00 10 ATT, 01 57 23, 31 00 00 ATT, and 31 11 00) and includes an updated bid schedule. The work includes placement of L-Head Breakwater Structures requiring approximately 4,000 SY of geotextile, 7,100 CY of clay layer, 7,300 CY of random fill, 32,800 tons of stone riprap, 21,400 tons of spalls and underwater fill, 59,900 CY of excavation cut, 35,500 CY of excavation fill, 24,400 CY of disposal excess material, 27,400 CY of loamy topsoil, 6,600 CY of aggregate surface course, and installation of 14 culvert pipes. The amendment also clarifies that this project is not classified as "For Native Use Only."
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is as follow s:
1. The bid due date is extended to 17 December 2024.
2. The follow ing specifications have adjustments: 00 41 26.01 24, 01 57 20.00 10, 01 57 20.00 10 Att, 01 57 23, 31 00 00, and 31 11 00.
3. Bid Schedule updated.
4. This project is not classified as "For Native Use Only".
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Dec-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F25B0005
X 9B. DATED (SEE ITEM 11)
04-Nov-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Dec-2024
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F25B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The required response date/time has changed from 12-Dec-2024 02:00 PM to 17-Dec-2024 02:00 PM.
The following have been added by full text:
AMENDMENT 0002
10 DEC 2024
Solicitation No. W9128F25B0005
Date of Issue: 04 NOV 2024 Date of Opening: 17 DEC 2024
SUBJECT: Amendment No. 0002 to Specifications and Drawings for Construction of Lower Brule Bank Stabilization Project Big Bend Dam Ft. Thompson SD.
TO: Prospective Bidders and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified by “*Am-2” in the areas of added revisions (underlining of added text and/or strikeout of deleted text.)
Pages or Sections Deleted Pages or Sections Substituted or Added 01 41 26.01 24 01 41 26.01 24 Am-0002 01 57 20.00 10 01 57 20.00 10 Am-0002 01 57 23 01 57 20.00 10 ATT Am-0002 31 00 00 ATT 01 57 23 Am-0002 31 11 00 31 00 00 ATT Am-0002 31 11 00 Am-0002
2. This amendment is a part of the bidding papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.
a. See Section 00 21 00, paragraph: GENERAL BIDDING INFORMATION, on how to submit electronic bids.
3. Electric bids will be received until 2:00 p.m., local time at place of bid opening, 17 DEC 2024.
Attachments:
Spec Pages listed in 1.a. above
U.S. Army Engineer District, Omaha
Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901
05 DEC 2024
JNS/2179
BID SCHEDULE
***Contractors shall submit the Bid Schedule below with their bid.***
BID SCHEDULE
Item Estimated No. Description Quantity Unit Price Amount
BASIC
0001 Entire work, complete, for placement of the L-Head Breakwater
Structures (placement of Geotextile (≈4,000 SY), Clay Layer (≈7,100 CY) and random fill (≈7,300 CY)) as shown on the drawings and in the specifications 1,850 LF $_________ $___________
0002 Entire work, complete, for the mobilization / demobilization of all equipment as shown on the drawings & in the specifications L.S. Job - $___________
0003 Entire work, complete, for all plant, material, and labor required for: Stone (Riprap) as shown on the drawings and in the specifications 32,800 Tons $_________ $___________
0004 Entire work, complete, for all plant, material, and labor required for: Spalls and Underwater Fill as shown on the drawings and in the specifications 21,400 Tons $_________ $___________
0005 Entire work, complete, for All plant, material, and labor required for:
Excavation Cut as shown on the drawings and in the specifications 59,900 CY $_________ $___________
0006 Entire work, complete, for All plant, material, and labor required for:
Excavation Fill as shown on the drawings and in the specifications 35,500 CY $_________ $___________
0007 Entire work, complete, for All plant, material, and labor required for:
Disposal Excess Material as shown on the drawings and in the specifications 24,400 CY $_________ $___________
0008 Entire work, complete, for All plant, material, and labor required for:
Loamy Topsoil Material as shown on the drawings and in the specifications 27,400 CY $_________ $___________
0009 Entire work, complete, for aggregate surface course as shown on the drawings and in the specifications 6,600 CY $_________ $___________
0010 Entire work, complete, for All plant, material, and labor required for:
Placement of culvert pipes as shown on the drawings and in the specifications 14 EA $_________ $___________
0011 All remaining work Except for
Items listed below L.S. Job - $___________
TOTAL AMOUNT $_______________
Notes:
1. See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of line items.
2. The quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to Contract Clauses "Variation in Estimated Quantity."
3. Bid prices must be entered for all items of the schedule. Total amount bids submitted without bid prices being entered on individual items will be rejected. Extensions will be subject to verification by the Government. In case of variation between the unit prices and the extensions, the unit prices will be considered the bid.
4. A modification to a bid which provides for a single adjustment to the total amount bid should state the application of the adjustment to each respective unit price and lump sum price affected.
If the modification is not so apportioned, the single adjustment will be applied to Item No.11.
5. See Section 01 22 00 MEASUREMENT AND PAYMENT for additional information.