This request for proposal outlines requirements for the construction of a Special Operations Command - North Theater Operational Support Facility at Peterson Air Force Base in Colorado. Key details include the construction of a new two-story facility totaling approximately 90,255 square feet, with separate HVAC, plumbing, and electrical systems serving administrative and secured areas. The project scope also includes site work, utilities, paving, communications infrastructure, a generator set, and optional items for furniture and security equipment. Proposals are due by January 6, 2021 at 2:00 PM local time. The contract will be awarded on a best value basis according to the criteria specified in the RFP, including technical merit and price.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment No. 0008 W9128F

SOCNORTH THEATER OPERATIONAL SUPPORT FACILITY, PN TDKA 143002 (FY20), PETERSON AFB, COLORADO

See attached documentation for content of the amendment revisions to solicitation

Date for receipt of proposals is 06 JAN 2021 at 1400 hours

Government Point of Contact: Bill Rawe, Contract Specialist, William.T.Rawe@usace.army.mil

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Rocky Mountain Area Office Attn: CONTRACTING DIVISION (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

See Item 6

W9128F-20-R-0085

12/10/2020

10/06/2020

12/10/2020

Am #0008 - 1

Am #0008 - 2 (Continuation SF 30)

10 December 2020 Solicitation No. W9128F 20 R 0085

Date of Issue: 13 NOV 2020 Date of Receiving Proposals: 06 JAN 2021

SUBJECT: Amendment No. 0008 to Request for Proposal Solicitation Package for Construction of SOCNORTH THEATER OPERATIONAL SUPPORT FACILITY.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Standard Form 1442 (SF1442), Page 00 10 00-1, item 11., delete “**” for the duration and substitute “840”. Delete note “**See CLIN Schedule”.

(2) Section 00 21 00, Page 18, paragraph 1.20.1 “BIDDER INQUIRY”, delete the first sentence “Technical inquiries and questions...receipt of offers.” and substitute the following:

“Technical inquiries and questions relating to technical requirements, proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than COB on 15 DEC 2020, in order that they may be given consideration or actions taken prior to receipt of offers.”

(3) Section 00 21 00, Page 19, paragraph 1.20.1 “BIDDER INQUIRY”, delete item c in its entirety and substitute the following:

“c. The Bidder Inquiry System will be unavailable for new inquires after COB on 15 DEC 2020 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.”

(4) Section 00 73 00, Page 2, paragraph 1.1 “(FAR 52.211-10)

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)”,

delete the entire paragraph and substitute the following:

“1.1 (FAR 52.211-10) COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984)

The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the Notice to Proceed, (b) prosecute said work diligently, and (c) complete the entire work ready to use within 840 calendar days after receipt of Notice to Proceed. The time stated for completion of the project shall include final cleanup of the premises.”

b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified with highlighting, all portions of the revised specification pages apply regardless of whether changes are shown with highlighting.

Am #0008 - 3 (Continuation SF 30)

Pages or Sections Deleted Pages or Sections Substituted or Added 01 81 00 01 81 00 01 86 10 01 86 10 01 86 26 01 86 26 01 86 29 01 86 29 Appendix C – FF&E – pg. 7 Appendix C – FF&E – pg. 7

c. Drawings (Reissued). The following drawings are revised with latest revision date as shown in the drawing border and reissued with this amendment.

1. SHEET E-201, FIRST FLOOR POWER PLAN - AREA A

2. SHEET E-202, FIRST FLOOR POWER PLAN - AREA B

3. SHEET E-203, SECOND FLOOR POWER PLAN - AREA A

4. SHEET E-204, SECOND FLOOR POWER PLAN - AREA B

5. SHEET T-102A, SECOND FLOOR PLAN - AREA A – TELECOM

6. SHEET T-102B, SECOND FLOOR PLAN - AREA B – TELECOM

7. SHEET AV-000, AUDIOVISUAL SYMBOLS AND ABBREVIATIONS

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 22 00 of the Request for Proposal.

4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 06 JAN 2021.

Attachments:

00 10 00 – SF1442 and CLIN Schedule Specifications listed in 1.b., above Drawings listed in 1.c., above

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

10 DEC 2020

nep/2160

This page was intentionally left blank for duplex printing.

Am #0008 00 10 00 - 1

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W9128F-20-R-0085

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

6 OCT 2020

PAGES OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY CODE CT 8. ADDRESS OFFER TO

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Rocky Mountain Area Office Attn: CONTRACTING DIVISION (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

See Item 7

9. FOR INFORMATION

CALL:

A. NAME

Bill Rawe

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) Use Email: William.T.Rawe@usace.army.mil

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

The offeror hereby agrees to do all work described in the documents entitled:

SOCNORTH THEATER OPERATIONAL SUPPORT FACILITY, PN TDKA 143002 (FY20)

PETERSON AFB, COLORADO

RETURN WITH OFFER: INFORMATION REQUIRED BY SECTION 00 10 00 (SF1442), SECTION 00 22 00, AND SECTION 00 45 00. ELECTRONIC COPIES OF

OFFER ARE ACCEPTABLE.

THIS SOLICITATION IS UNRESTRICTED AND IS OPEN TO BOTH LARGE AND SMALL BUSINESS PARTICIPATION

11. The Contractor shall begin performance within 10 calendar days and complete it within 840 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. [*Am-8] <text deleted> [**Am-8]

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 1400 (hour) local time 06 JAN 2021. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than ___90_____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442(REV. 4-85)

Prescribed by GSA FAR(48 CFR) 53.236-1(d)

Am #0008 00 10 00 - 2

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

DUNS Number:

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within 90 calendar days after the date offers are due.

AMOUNTS

SEE ATTACHED CLIN PRICING SCHEDULE

Contractor’s Fax No. CAGE CODE Contractor’s E-Mail address

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

U.S. Army Engineer District, Omaha 1616 Capitol Ave.

Omaha, Nebraska 68102-4901

USAED Omaha c/o USACE Finance Center 5722 Integrity Drive Millington, TN 38054-5005

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (contractor is required to sign this document and return _______ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,

(b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

STANDARD FORM 1442 BACK (REV. 4-85)

CLIN SCHEDULE 00 10 00 – 3 W9128F-20-R-0085

Am #0008

CONTRACT LINE ITEM (CLIN) PRICING SCHEDULE

ITEM

NO.

DESCRIPTION QTY UNIT AMOUNT

BASIC ITEMS

Entire work complete for Design of the SOCNORTH Theater Operational Support Facility, including all Basic and Option Items listed below. Design in compliance with all requirements contained in this RFP, its attachments, references, and appendices.

Job

Entire work complete for Construction of the SOCNORTH Theater Operational Support Facility, complete to the five-foot line (8,192 square meters), excluding items separately listed below. Scope includes construction of the design and associated systems described above and throughout this Contract.

Entire work complete for Construction of Sitework, Utilities, and Pavements from five-foot line to the limits of construction of the SOCNORTH Theater Operational Support Facility, including all required demolition, excluding items listed separately below.

Entire work complete for Procurement and Installation of Generator Sets and associated switchgear, controls and monitoring, and connections to fuel system.

Entire work complete for Construction of communications lines and ductbank from the SOCNORTH facility to Building 1038.

Entire work complete for cybersecurity documentation, and alterations to commercial equipment, devices, firmware, and software to satisfy cybersecurity requirements.

TOTAL BASIC AMOUNT $_____________________________

CLIN SCHEDULE 00 10 00 – 4 W9128F-20-R-0085

OPTION ITEMS

[Option]

Installation of FF&E. (O&M funded)

Installation of Intrusion Detection System (IDS) and Electronic Security Systems (ESS) to include facility Access Control System (ACS). (O&M funded)

Installation of audio-visual (A/V) system equipment and devices. (O&M funded)

Installation of CCTV system equipment and devices. (O&M funded)

Installation of uninterruptable power system (UPS) equipment and devices. (O&M funded)

Entire work complete to provide access control and secure area oversight as defined in 01 14 00 Work Restrictions and associated references. (O&M funded)

Entire work complete to construct south parking lot including associated landscape and lighting.

Additional cost to complete to construct parking using permeable pavers in lieu of asphalt.

TOTAL AMOUNT (BASIC PLUS OPTIONS) $_________________________________

NOTES:

1. See SECTION 00 21 00, INSTRUCTIONS TO OFFERORS for evaluation of options. The Government reserves the right to exercise option Items No. 0013 and 0014 within 90 calendar days of Notice to Proceed and remaining options within 560 calendar days of Notice to Proceed.

2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the lump-sum prices and the total amount, the lump-sum prices will be considered the price submitted. Abbreviation: Operations and Maintenance (O&M).

CLIN SCHEDULE 00 10 00 – 5 W9128F-20-R-0085

3. A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump-sum price affected.

[*Am-8] <text deleted> [**Am-8]

This page was intentionally left blank for duplex printing.

SOCNORTH Theater Operational Support Facility - Peterson AFB PE83

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 81 00

SUMMARY OF THE WORK

05/18

PART 1 GENERAL

1.1 REFERENCES

1.2 Building Durability

1.2.1 Site Constraints

1.2.2 Critical Fiber Communications Standoff Distance

1.2.2.1 Site Access and Work Restrictions

1.2.2.2 PROJECT DESCRIPTION

1.3 PROJECT SITE

1.4 DESIGN AND CONSTRUCTION OBJECTIVES

1.5 Site and Infrastructure Functions

1.5.1 Facility Functions

1.5.2 PROJECT SCOPE

1.6 Existing Conditions

1.6.1 Demolition

1.6.2 New Work

1.6.3 DESIGN AND CONSTRUCTION REQUIREMENTS

1.7 Codes and Criteria

1.7.1 Codes and Criteria

1.7.2 Secure Areas

1.7.3 Future Special Access Program (SAP) Spaces

1.7.3.1 Open-Storage Areas

1.7.4 Changes to RFP Criteria Requirements

1.7.5 Phasing of Work, Security, and Construction Staging

1.7.6 Sustainability

1.7.7 Life-Cycle Cost Analysis (LCCA)

1.7.7.1 Life-Cycle Cost Analysis (LCCA)

1.7.7.2 LCCA Format

1.7.7.2.1 LCCA Building-Level Analysis

1.7.7.2.2 LCCA Individual Component or System Alternatives

Analysis

1.7.7.2.3 Energy Consumption Reduction Requirement

1.7.7.3 Energy Compliance Analysis (ECA)

1.7.7.4 ECA Narrative Requirements

1.7.7.4.1 Total Building Commissioning

1.7.7.5 Cybersecurity

1.7.8 Bridging Documents

1.7.9 Design and Construction Measurement Units

1.7.10 Personnel Qualifications and Experience

1.7.11 Design and Construction Deliverables

1.7.12 Advanced Modeling and Facility Data Requirements

1.7.13 Operations and Maintenance Requirements

1.7.14 OVERVIEW OF DESIGN-BUILD PROCESS

1.8 Process

1.8.1 Process

1.8.2 DESIGN-BUILD CONTRACTOR REQUIRED A/E SERVICES

SECTION 01 81 00 Page 1Am #0008

1.9 Dimensions

1.9.1 Professional Registrations, Licenses and/or Certifications

1.9.2 Request For Proposal - Binding Information

1.9.3 Evaluation of Systems

1.9.4 Documents Requirements

1.9.5 COMMON DEFICIENCIES

1.10 PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 81 00 Page 2Am #0008

SECTION 01 81 00

SUMMARY OF THE WORK

05/18

PART 1 GENERAL

1.1 REFERENCES

The design publications listed below shall be used as sources of criteria for the design. The most current edition of the code or standard (with errata and addenda) available at the RFP proposal submission deadline shall be used as criteria for the design - unless noted otherwise. The criteria from these sources may be supplemented, but not supplanted, by applicable criteria contained in nationally recognized codes and standards.

[*Am-5]

[**Am-5]

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 8510.01 (2014; Change 1-2016; Change 2-2017) Risk Management Framework (RMF) for DoD Information Technology (IT)

DODI 8500.01 (2014) Cybersecurity

UFC 1-200-01 (2019) DoD Building Code (General Building Requirements)

UFC 1-200-02 (2016; Change 4, 2019) High Performance and Sustainable Building Requirements

UFC 3-101-01 (2011; Change 5, 2019) Architecture

UFC 3-600-01 (2016; Change [*Am-4] 5 [**Am-4], 2020) Fire Protection Engineering for Facilities

UFC 4-021-01 (2008; with Change 1, 2010) Design and O&M: Mass Notification Systems

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST SP 800-82 NIST Special Publication: Guide to Industrial Control Systems (ICS) Security

1.2 DESIGN AND CONSTRUCTION OBJECTIVES

The design and construction of the SOCNORTH facility under this Contract shall comply with specifications and requirements contained in this Request for Proposal (RFP). Requirements emphasize low maintenance exterior and interior finishes as well as high energy efficiency. This project shall be designed and constructed to achieve federal guiding principles compliance via completion of the Air Force MILCON Sustainability Requirements Scoresheet. See 01 33 29 SUSTAINABILITY REPORTING for additional information.

SECTION 01 81 00 Page 3Am #0008

The floor plans and elevations provided in this RFP are conceptual and establish the general requirements for square foot area, functional arrangement of rooms and spaces, exterior treatments and the overall unit configuration. During the design stages, the contractor shall make necessary adjustments to ensure constructability and compliance with the RFP criteria and requirements. The plans and elevations do not indicate all necessary construction requirements or components; the RFP describes associated technical, performance and system requirements. Design and construction shall be in accordance with all applicable industry and Air Force criteria, and the requirements of this RFP.

Design Quality Objective: The project objective is to obtain facilities to accommodate a maximum of 8,385 SM (90,255 SF) of accredited secure and open-storage administrative and training space with complementary site development within the funds available. Design quality is achieved through the integration of the facility to the site, balancing architecture features, managing design and construction security requirements, functionality and design for low-cost maintenance and operation. The Government desires to construct facilities of such quality that the foundations, foundation walls, footings, slabs and other foundation components last for a life of 50 years without structural damage, due to expansive soils or other geologic conditions, to the foundation or structures that the foundation supports.

It is desired that all equipment and products be easy to service, maintain, repair, and replace. All products or equipment shall follow industry standards. In extenuating circumstances, the use of special designed or manufactured items may be allowed, but they shall be submitted to the government for review and written approval prior to production, order or manufacture.

Scope of Work:

The proposal documents shall include adequate information to enable the Government to adequately evaluate the proposal for understanding and compliance with the entire scope of work. See Section 00 22 00 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA AND BASIS OF AWARD for complete requirements.

Project architectural features included but are not limited to [*Am-3] <text deleted> [**Am-3]stud backup wall construction, insulation, doors, windows/curtainwall, building hardware, gypsum wallboard, paint, wall coverings, cabinets, carpets, tile, acoustical ceiling tile, toilets, lavatories and accessories. Mechanical work includes but is not limited to construction of complete HVAC system(s) for the new facility, boilers and chillers, HVAC equipment and all associated controls, plumbing, EMCS/DDC and fire protection systems, lightning protection systems, complete cathodic protection system utilizing sacrificial anodes. Interior electrical includes panel boards, lighting fixtures, and general building power requirements. Communications work includes but is not limited to fiber optic and voice/data cabling including pre-wiring keyless access, CATV, security systems infrastructure, mass notification system and paging system. Anti-terrorism and force protection design and construction will be applied on this project.

SECTION 01 81 00 Page 4Am #0008

1.2.1 Building Durability

Materials and equipment will be chosen for their durability and minimum maintenance. The building design shall conserve natural and manmade materials.

1.2.2 Site Constraints

See the bridging documents for the proposed project site(s). The site is highly constrained by a variety of factors. The contractor shall ensure the facility is designed and constructed in compliance with all site constraints including but not limited to the following:

1.2.2.1 Critical Fiber Communications Standoff Distance

A fiber communications concrete-encased duct which bisects the site shall remain undisturbed in its entirety. See the provided survey for the approximate location. Installation of foundations and utilities along the duct shall be located no closer than 5'-0" from the horizontal edge of the concrete encasement. Installation of grade beams (or other appropriate foundation feature) and utilities crossing the duct shall be located no closer than 1'-6" in any direction of the concrete encasement. Protective measures shall be taken during grading and construction activities to prevent disturbance to this concrete-encased duct.

1.2.2.2 Site Access and Work Restrictions

The various components of work fall under different levels of protection and oversight. Close coordination with the Government will be required during all phases of design and construction. See 01 14 00 WORK RESTRICTIONS and the bridging documents for requirements and restrictions related to various components of work.

1.3 PROJECT DESCRIPTION

The purpose of this project is to design and construct a new SOCNORTH Headquarters building that will serve as an administrative headquarters and command and control center. Major features include administrative office space, storage and secure areas. The secure areas provide space for Joint Operations Command (JOC), Special Technical Operations (STO), and administration space for J2, J3, and J5. Administrative functions include the Command Headquarters, J0, J1, J4, J6, and J8 staff. SOCNORTH has considerable storage requirements as various groups need to be prepared for rapid deployment.

The new SOCNORTH facility is a two-story building. Certain functions such as major storage, and mechanical, fire riser, and primary electrical service rooms will be located on the first floor as they require visitor access, vehicular access, loading/unloading of materials, and/or access by base maintenance personnel. A lobby is adjacent to the main entry and will include space for reception with a waiting area in order to process security badges and facilitate access to the rest of the building through controlled access.

Project architectural features include but are not limited to construction of steel stud and masonry walls, concrete slabs, insulation, doors, windows/storefronts/curtainwall, building hardware, gypsum wallboard, paint, wall coverings, cabinets, carpets, tile, acoustical ceiling tile, toilets, lavatories and accessories.

SECTION 01 81 00 Page 5Am #0008

Mechanical features include but are not limited to new HVAC system(s), utility service connections, HVAC equipment and all associated controls, plumbing, EMCS/DDC and fire protection/sprinkler systems. For additional information regarding mechanical requirements see Specification Section 01

86 10 MECHANICAL REQUIREMENTS.

Interior electrical includes panel boards, lighting fixtures, and general building power requirements. Communications work includes but is not limited to fiber optic and voice/data cabling, including pre-wiring keyless access, CCTV, CATV, and security systems infrastructure. (For additional information regarding electrical requirements see Specification Section 01 86 26 ELECTRICAL REQUIREMENTS.)

A fire alarm and mass notification system shall be installed throughout the facility in accordance with UFC 3-600-01 and UFC 4-021-01. A fire sprinkler system shall be installed throughout the facility in accordance with UFC 3-600-01.

See all discipline requirements sections of this RFP, combined with the bridging documents for the full technical scope of work relating to this project.

1.4 PROJECT SITE

The project is located at Peterson AFB, Colorado, within the Command Character area on the installation. Vicinity and location maps are included in the bridging documents provided with this RFP.

1.5 DESIGN AND CONSTRUCTION OBJECTIVES

The primary purpose of this project is to create interior spaces tailored to occupying unit operational needs, with a facility functional life of 50 years. See the bridging documents for floor plans, as well as space-by-space requirements for the new facility.

Among the features of work are the following. See individual discipline requirements specifications for additional requirements:

a. Design and installation of an air barrier system for the building to meet UFC 3-101-01 and the standards set forth in it.

b. Entire work complete for Procurement and Installation of Generator Set and Switchgear, associated controls and monitoring, and connections to fuel system.

c. Entire work complete for construction of communications lines and ductbank from the SOCNORTH facility to Building 1038.

d. Entire work complete for cybersecurity documentation and alterations to commercial equipment, devices, firmware, and software to satisfy cybersecurity requirements.

e. (Bid Option) Procurement and installation of furniture, furnishings, and equipment (FF&E).

f. (Bid Option) Procurement and installation of Intrusion Detection System (IDS) and Electronic Security Systems (ESS) to include facility Access Control System (ACS).

SECTION 01 81 00 Page 6Am #0008

g. (Bid Option) Procurement and installation of CCTV system equipment and devices.

h. (Bid Option) Procurement and installation of audio-visual (A/V) system equipment and devices.

i. (Bid Option) Entire work complete for procurement and installation of uninterruptable power system (UPS) equipment and devices.

j. (Bid Option) Entire work complete to provide access control and secure area oversight as defined in 01 14 00 Work Restrictions and associated references.

k. (Bid Option) Entire work complete to construct south parking lot including associated landscape and lighting.

l. (Bid Option) Additional cost complete to construct parking using permeable pavers in lieu of asphalt pavement.

See 00 10 00 SF 1442 AND CONTRACT LINE ITEM PRICING SCHEDULE for a bid schedule including basic bid items as well as bid options.

1.5.1 Site and Infrastructure Functions

Significant site work is required by this project, including building earthwork, parking lots, drives, sidewalks and landscaping, as indicated in the briding documents. Coordinate laydown and staging areas with the Government after contract award; tenative staging areas are indicated in the bridging documents.

1.5.2 Facility Functions

The facility is intended to serve multiple SOCNORTH companies, yielding a requirement for a somewhat compartmentalized floor plan, as indicated in the briding documents. Building systems, door hardware, access control systems, and other building components shall be configured in a manner that preserves that compartmentalization. See the bridging documents for primary points of entry for each of those compartments. Those systems shall be configured to allowed shared access of spaces and resources when the units desire to do so.

The facility shall accomodate personnel at workstations and personnel's equipment storage lockers as shown on the bridging documents.

1.6 PROJECT SCOPE

This project requires design and construction of the new SOCNORTH facility as described within this RFP.

The design shall include all work for the new SOCNORTH facility, including bid options. See Section 01 33 00.32 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES for additional requirements.

1.6.1 Existing Conditions

The existing site is an open site with no existing structures. The site is adjacent to the base perimeter in the northeast corner of Peterson AFB in the Command Character area.

SECTION 01 81 00 Page 7Am #0008

1.6.2 Demolition

Conduct all demolition necessary to meet all requirements as described in this RFP. See 02 41 00 DEMOLITION for additional requirements. Demolition shall include, but is not limited to the following:

a. Site materials at new SOCNORTH facility location.

1.6.3 New Work

Provide all work neccessary to construct the SOCNORTH facility in full compliance with the bridging documents, and all portions of this RFP -including but not limited to the following:

a. Provide walls, substrates, and finishes as indicated by the room finish schedule.

b. Provide a fire sprinkler system and sprinkler heads per accommodate floor plan layout per 01 86 13 FIRE PROTECTION REQUIREMENTS.

c. Provide fire alarm and mass notification per 01 86 13 FIRE

PROTECTION REQUIREMENTS.

d. Provide lighting (fixtures, switches, and wiring) per 01 86 26

ELECTRICAL REQUIREMENTS.

e. Provide ceilings where indicated in rooms per 01 82 00

ARCHITECTURAL REQUIREMENTS.

f. Provide communications infrastructure, equipment, and wiring per

01 86 26 ELECTRICAL REQUIREMENTS.

g. Provide building power, equipment, conduit, wiring, and receptacles per 01 86 26 ELECTRICAL REQUIREMENTS.

h. Provide HVAC equipment, diffusers, grilles, and associated ductwork per 01 86 10 MECHANICAL REQUIREMENTS.

i. Provide plumbing fixtures, supply lines, vent and waste lines per

01 86 10 MECHANICAL REQUIREMENTS.

j. Install an air barrier system on the exterior walls per 01 82 00

ARCHITECTURAL REQUIREMENTS.

k. Provide interior and exterior doors, frames, and door hardware as indicated in the bridging documents and per 01 82 00 ARCHITECTURAL

REQUIREMENTS.

l. Provide storage lockers/cages where indicated in the bridging documents per 01 82 00 ARCHITECTURAL REQUIREMENTS.

m. Provide Intrusion Detection System (IDS), Electronic Security System (ESS) and facility Access Control System (ACS) infrastructure, conduit, and wiring for new IDS and ESS systems (infrastructure/wiring in base bid, IDS, ESS and ACS equipment and systems in bid option).

n. Provide closed-circuit television (CCTV) infrastructure, conduit and wiring for new CCTV system (infrastructure/wiring in base bid, SECTION 01 81 00 Page 8Am #0008

CCTV equipment and system in bid option).

o. Provide A/V system infrastructure, conduit, and wiring for A/V system (infrastructure/wiring in base bid, A/V equipment and system in bid option).

1.7 DESIGN AND CONSTRUCTION REQUIREMENTS

1.7.1 Changes to RFP Criteria Requirements

This Request for Proposal provides requirements expected of the Design-Build Contractor during the design and construction of this project.

The RFP bridging documents present an overall design concept of the project; provide useful project information; establish some definition of the systems to be used; and incorporate requirements expected by the Using Service.

It shall be the responsibility of the Design-Build Contractor to assemble the best-value-priced construction systems for this project that meet or exceed all provisions of the RFPand referenced criteria set forth herein.

Offerors should not consider changes to RFP criteria requirements during proposal preparation. After contract award, any changes to the RFP criteria requirements require approval by the Contracting Officer.

See Section 01 33 00.32 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES for additional requirements.

1.7.2 Codes and Criteria

All pertinent building codes, life safety codes, and reference criteria shall be met or exceeded. This project utilizes the DoD Building Code, as defined by UFC 1-200-01 and its references.

If there is a conflict in requirements, order of precedence shall be as follows, in order of decreasing precedence:

a. Life Safety, as defined by DoD Building Code UFC 1-200-01 and its references;

b. RFP Specifications;

c. RFP Drawings;

d. Non-life safety criteria, as defined by DoD Building Code UFC 1-200-01 and its references;

e. Peterson AFB Construction Standards (5.12.20) and Peterson AFB Installation Facilities Standards (IFS) - 7.31.18;

f. Other criteria as listed herein.

***Note that some appendices, such as the Peterson AFB Installation Facilities Standards (IFS) and Peterson AFB Construction Standards are provided for reference and/or refinement of referenced critera and RFP requirements. These items are labelled as such, and contain disclaimers and caveats as such on their respective cover sheets. The contents of these appendices shall not supercede any codes, criteria, or requirements

SECTION 01 81 00 Page 9Am #0008 indicated above except as specifically outlined above.

1.7.3 Secure Areas

Areas identified in the RFP and bridging documents as "secure area" shall be designed, constructed, and accredited to the criteria listed below. The contractor shall design and construct the perimeter and all spaces within the boundary in compliance with the following criteria:

The listed criteria carries impacts to all building systems within the designated boundary. Use the most current version of the referenced criteria available at the RFP proposal submission deadline:

a. ICD/ICS 705 - Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities.

b. ICS 705-1 - Physical and Technical Security Standards for Sensitive Compartmented Information Facilities.

c. ICS 705-2 - Standards for the Accreditation and Reciprocal Use of Sensitive Compartmented Information.

d. UFC 4-010-05 - Sensitive compartmented Information Facility Planning, Design and Construction.

The following factors shall be used when applying criteria described above:

e. Facility is being constructed within the Continental United States

(CONUS).

f. Amplified sound is present in some of the occupied spaces within the secure area, as shown in the bridging documents.

g. Facility shall be treated as having moderate threat level per TEMPEST risk assessment.

h. RF shielding is required at the secure area perimeter.

i. All open and private offices shall be constructed to "open storage" requirements per secure area criteria.

j. Spaces and/or space groups shall be constructed to compartmented areas when indicated in the bridging documents. See secure area criteria for requirements.

1.7.3.1 Future Special Access Program (SAP) Spaces

Areas identified in the RFP and bridging documents as "SAP spaces" shall be designed, constructed but not separately accredited as individual secure areas within the secure area (s) that they occur. The contractor shall design and construct the perimeter and all spaces within the boundary in compliance with the secure area criteria listed above, but with the following assumptions:

a. Facility is being constructed within the Continental United States

(CONUS).

b. Amplified sound is present within all SAP spaces.

SECTION 01 81 00 Page 10Am #0008

c. Facility shall be treated as having moderate threat level per TEMPEST risk assessment.

d. RF shielding is not required at each SAP perimeter.

1.7.4 Open-Storage Areas

The secure training area and boundary indicated in the bridging documents shall be classified and accredited as secure "open-storage" space in compliance with the following criteria. See the bridging documents for the approximate perimeter of "open-storage" spaces from otherwise designated functions. The contractor shall design and construct the perimeter and all spaces within the boundary in compliance with the following criteria. The listed criteria carries impacts to many building systems within the designated boundary. Use the most current version of the referenced criteria available at the time of contract award:

a. AFI 31-101 - Integrated Defense.

b. DODM 5200.01 - (Volumes 1-3) DOD Information Security Program.

c. AFI 16-1404 - Air Force Information Security Program.

d. AFI 16-1406 - Air Force Industrial Security Program.

e. AFM 33-221 - Communications Security: Protected Distribution Systems

(PDS)

[*Am-6] <text deleted> [**Am-6]

1.7.5 Changes to RFP Criteria Requirements

This Request for Proposal provides requirements expected of the Design-Build Contractor during the design and construction of this project. The RFP drawings present an overall design concept of the project, provide useful project information, establish some definition of the systems to be used, and incorporate requirements expected by the Using Service.

It shall be the responsibility of the design-build Contractor to assemble the best-valued-priced construction systems for this project that meet or exceed the design criteria set forth herein.

Offerors shall not consider changes to RFP criteria requirements during proposal preparation. After contract award, any changes to the RFP criteria requirements require approval by the Contracting Officer.

See Section 01 33 00.32 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES for additional requirements.

NOTE: If there is a conflict between the Peterson Air Force Base Installation Facilities Standards, Peterson Air Force Base Construction Standards and the RFP criteria, the RFP criteria governs with questions being directed to the Contracting Officer before proceeding.

1.7.6 Phasing of Work, Security, and Construction Staging

The Contractor shall maintain a construction area fence throughout the

SECTION 01 81 00 Page 11Am #0008 duration of the contract. See Section 01 89 00 SITE WORK REQUIREMENTS and the bridging documents for additional information.

1.7.7 Sustainability

1.7.7.1 Criteria

Comply with Air Force sustainable design and development (SDD) criteria as follows:

Comply with all the Federal sustainability requirements as detailed in UFC 1-200-02, High Performance and Sustainable Building Requirements.

Design Build Contractor is responsible for all costs and activities required to successfully third-party validate that all of the Federal/UFC requirements have been met using the DoD version of either the US Green Building Council (USGBC)/Green Business Certification Inc. (GBCI) Guiding Principles Assessment or Green Building Initiative (GBI) Guiding Principle Compliance (GPC) system. (See specification section 01 33 29).

Use the AF Sustainability Requirements Scoresheet (attached) to track and report project compliance status at all design/construction submittals;

and submit the Microsoft Excel scoresheet, along with the design analysis to AFCEC.CF.SustainableRpt@us.af.mil in conjunction with each design submission and when construction is complete.

1.7.7.2 Life-Cycle Cost Analysis (LCCA)

The purpose of the LCCA methodology as detailed in CFR Title 10 Part 436 Subpart A is to identify and compare life-cycle cost-effective (LCCE) building energy and water systems that will in total achieve the energy and water requirements stated in this document. An LCCA is required for the following:

1. Energy consuming systems (ex: HVAC Systems and Domestic Water Heating System)

2. When LCCE is selected as the reason any requirement of the AF Sustainability Requirements Scoresheet is "Partially compliant" or "Not Applicable" (reference paragraph 4-2). The LCCA methodology may also be used to evaluate multiple options, such as selecting the building construction type and comparing compliant materials; and is at the discretion of the project team.

1.7.7.2.1 LCCA Format

Prepare the LCCA in accordance with CFR Title 10 Part 436, Subpart A and NIST Handbook 135 "Life-Cycle Costing Manual for the Federal Energy Management Program". The LCCA must be prepared using the Building LifeCycle Costing (BLCC) program, available from the National Institute of Standards and Technology (http://energy.gov/eere/femp/building-lifecycle-cost-programs). The implied long-term inflation rate and discount rates identified in the Annual supplement to NIST Handbook 135 must be used. A link to BLCC can also be found at the Department of Energy's building energy tools web site: http://energy.gov/eere/femp/buildinglife-cycle-cost-programs.

1.7.7.2.2 LCCA Building-Level Analysis

Any building-level LCCA must be calculated using a maximum of a 40-year

SECTION 01 81 00 Page 12Am #0008 building life and equipment lives based on accepted industry averages.

Individual components or systems life expectancies must be reflected by inclusion of appropriate replacement and salvage values in the appropriate year of this analysis.

1.7.7.2.3 LCCA Individual Component or System Alternatives Analysis

LCCAs comparing at least three individual component or system alternatives must use the estimated life of the mutually exclusive alternative having the longest life, not to exceed 40 years from the beginning of beneficial use or the lowest common multiple of the expected lives of the alternatives. Include the appropriate replacement and salvage values for each of the other alternatives. A number of tools comparing energy system alternatives and evaluating specific efficiency measures may be of benefit in performing energy efficiency calculations. Perform this analysis based on the actual conditions expected over the life of the facility including anticipated occupancies, scheduled hours of operation and process loads.

Use UFC 3410-01 Appendix E.

1.7.7.3 Energy Consumption Reduction Requirement

Meet the requirements of ASHRAE 90.1.

Design the building to achieve at least 30% energy consumption reduction from ASHRAE 90.1 baseline.

If a 30% reduction is not LCCE, modify the design of the proposed building to achieve an energy consumption level at the highest level of energy efficiency that is LCCE.

Determine energy consumption levels for both the ASHRAE Baseline Building and proposed building alternatives by using the Performance Rating Method found in UFC 1-200-02.

1.7.7.4 Energy Compliance Analysis (ECA)

In the design analysis, include an ECA which demonstrates compliance with all energy related requirements in UFC 1-200-02. Identify the specific energy efficiency criteria that apply to the project, the software used to prepare the necessary calculations, a summary of all input to and output from the calculations, and the calculated baseline and as-designed building energy consumption of the proposed design. Include in the ECA a completed "Performance Rating Report" as shown in Appendix G of the ASHRAE

90.1 "User's Manual." Building-level energy consumption calculations must be performed using a computer program or programs that integrate architectural features such as windows for daylighting, air-conditioning, heating, lighting, and other energy producing or consuming systems. These programs must be capable of simulating the features, systems, and thermal loads used in the design. Include the energy savings and any parasitic energy loads associated with the utilization of recovered energy, solar heat, solar photovoltaic energy and other renewable or waste heat applications. The program must be capable of performing 8,760 hourly calculations. The Department of Energy (DoE) maintains a list of building energy tools for design (such as eQuest).

1.7.7.4.1 ECA Narrative Requirements

ECA LCCA narratives must be prepared by each of the following individuals:

the Lead Project Architect, Lead Project Mechanical Engineer, and the Lead

SECTION 01 81 00 Page 13Am #0008

Project Electrical Engineer. List in each of the three narratives the conservation features considered for that discipline; conservation measures adopted in the design; and any supporting LCCA calculations.

1.7.7.5 Total Building Commissioning

Apply total building commissioning principles and fully commission the facility, in compliance with 01 91 00.15 TOTAL BUILDING COMMISSIONING and

UFC 1-200-02.

1.7.8 Cybersecurity

All control systems (including systems separate from an energy management control system) shall be planned, designed, acquired, executed, and maintained in accordance with DODI 8500.01, DOD 8510.01, NIST SP 800-82, and UFC 4-010-06 [*Am-7] <text deleted> [**Am-7]. Systems requiring cybersecurity are listed in 01 86 10 MECHANICAL REQUIREMENTS.

1.7.9 Bridging Documents

Conceptual drawings of the site plans, floor plans, and elevations are included for use in developing this design.

1.7.10 Design and Construction Measurement Units

Design, products, and construction for the project shall be accomplished using English units of measurement. All measurement in the technical specifications sections shall be shown in English.

1.7.11 Personnel Qualifications and Experience

Design and construction personnel qualifications and experience shall be per the requirements of 01 45 00.00 10 QUALITY CONTROL and 01 33 00.32

DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES.

1.7.12 Design and Construction Deliverables

See 01 33 00.32 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES.

1.7.13 Advanced Modeling and Facility Data Requirements

The contractor shall design and construct this project by leveraging BIM, CIM, CAD, and electronic facility data to the greatest extent practical under the scope of this project. See 01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS for minimum project requirements. This project also requires the development and turnover of electronic facility data (via a Facility Data Workbook (FDW)) to the Government.

1.7.14 Operations and Maintenance Requirements

See Section 01 78 23 OPERATION AND MAINTENANCE DATA for requirements.

1.8 OVERVIEW OF DESIGN-BUILD PROCESS

1.8.1 Overview

Since the early 1980s Congress has urged the military services to explore alternative construction methods, such as "Design-Build," which includes both design and construction under a single contract. This process is

SECTION 01 81 00 Page 14Am #0008 similar to "one-stop turnkey selection procedures" and is defined in Title 10 of the United States Codes, Section 2862.

1.8.2 Process

The design-build process uses a Request for Proposal (RFP) to solicit for design and construction of a facility by a single contractual entity, such as a design-build firm, or joint venture between architect-engineer (A-E) and construction firm, or a construction management (CM) firm joint venture with an A-E and a construction firm. A design-build RFP states the project functional requirements, design and engineering criteria, technical performance specifications, and proposal evaluation factors.

Potential contractors develop their proposals for the government to evaluate competitively, with the contract award based on a combination of technical merit and price.

In general, the RFP is a conceptual design document and the Contractor is responsible for completing the design and constructing the project. The plans provided in this Request For Proposal (RFP) show the User's intent and expectations. The RFP has developed the site plan and building design and given the facility an architectural character.

The Contractor will be required to coordinate and adjust final dimensioning, detailing, furniture arrangements and other items necessary to make this a usable facility in accordance with the furnished RFP drawings. The design, with permitted flexibility for detailing and contractibility, must be carried through to construction. The design-build contractor is responsible for all design on the project.

The…