W9128F-20-R-0079am_0001 SPECS Chng.pdf

PDF 364 KB Posted

Attached to
General Billy Mitchell ANGB, WI Hydrant Fuel System Replacement Federal contract opportunity
Solicitation number
W9128F-20-R-0079
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This solicitation seeks proposals to construct a new consolidated fueling facility at General Billy Mitchell Air National Guard Base in Wisconsin. The project includes building a new aboveground fuel storage tanks, pump house with control room, product recovery tank, POL operations building with laboratory, refueling vehicle parking area, truck loading and unloading points, motor gas storage tank, diesel storage tank, and associated supporting facilities. The solicitation was issued by the Department of the Army Corps of Engineers Omaha District. Proposals are due by the specified closing date.

View the file

Other files for this federal contract opportunity

Other files attached to General Billy Mitchell ANGB, WI Hydrant Fuel System Replacement, newest first.
File Type Posted
Question and Answer related to Projnet question 8737383.pdf PDF
W9128F20R0079-Drawings-Am-4.pdf PDF
02 41 00-Am4.pdf PDF
Amendment 0004 Modification Copy W9128F-20-R-0079.pdf PDF
Amendment 0004 Conformed Copy.pdf PDF
Amendment 0003 W9128F-20-R-0079.pdf PDF
W9128F20R0079-Vol-2-Specs-Am2.pdf PDF
Amendment 0002 W9128F-20-R-0079.pdf PDF
W9128F20R0079-Drawings-Am-2.pdf PDF
Bid Walk sign in list.pdf PDF
Amendment 0001 W9128F-20-R-0079.pdf PDF
ARW Form 11 Visitor Access.pdf PDF
Site Walk and Visitor Access Instructions W9128F20R0079.pdf PDF
Solicitation Gen. Billy Mitchell W9128F-20-R-0079.pdf PDF
W9128F-20-R-0079-Vol-2-Specs.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POL Facilities Replacement, DESC2001, General Mitchell IAP, WI MT18

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1 Am #0001

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

*Am-1 Contract drawings are as follows:

SHEET NO. DESCRIPTION

GENERAL

G-000 COVER

G-001 SHEET INDEX 1

G-002 SHEET INDEX 2

G-003 GENERAL LEGEND AND ABBREVIATIONS

G-004 GENERAL NOTES

G-005 ACCESS & SAFETY PLAN

G-011 CONSTRUCTION PHASE 1 PLAN

G-012 CONSTRUCTION PHASE 2 PLAN

G-013 CONSTRUCTION PHASE 3 PLAN

G-014 CONSTRUCTION PHASE 4 PLAN

G-100 OVERALL FUEL FACILITY PLAN

CIVIL

V-100 OVERALL EXISTING CONDITIONS PLAN

V-101 EXISTING CONDITIONS PLAN - 1

V-102 EXISTING CONDITIONS PLAN - 2

V-103 EXISTING CONDITIONS PLAN - 3

DOCUMENT 00 01 15 Page 2

SHEET NO. DESCRIPTION

V-104 EXISTING CONDITIONS PLAN - 4

V-105 EXISTING CONDITIONS PLAN - 5

V-106 EXISTING CONDITIONS PLAN - 6

V-107 EXISTING CONDITIONS PLAN - 7

V-108 EXISTING CONDITIONS PLAN - 8

V-109 EXISTING CONDITIONS PLAN - 9

V-110 EXISTING CONDITIONS PLAN - 10

B-100 BORING LOCATION PLAN

B-601 BORING LOGS - 1

B-602 BORING LOGS - 2

B-603 BORING LOGS - 3

CD100 OVERALL DEMOLITION PLAN

CD101 DEMOLITION PLAN - 1

CD102 DEMOLITION PLAN - 2

CD103 DEMOLITION PLAN - 3

CD104 DEMOLITION PLAN - 4

CD105 DEMOLITION PLAN - 5

CD106 DEMOLITION PLAN - 6

CD107 DEMOLITION PLAN - 7

CD108 DEMOLITION PLAN - 8

CD109 DEMOLITION PLAN - 9

CD110 DEMOLITION PLAN - 10

CD901 DEMOLITION PHOTOS - 1

CD902 DEMOLITION PHOTOS - 2

CD903 DEMOLITION PHOTOS - 3

CD904 DEMOLITION PHOTOS - 4

DOCUMENT 00 01 15 Page 3

CS100 OVERALL SITE PLAN

CS101 SITE LAYOUT PLAN - 1

CS102 SITE LAYOUT PLAN - 2

CS103 SITE LAYOUT PLAN - 3

CS104 SITE LAYOUT PLAN - 4

CS105 SITE LAYOUT PLAN - 5

CS106 SITE LAYOUT PLAN - 6

CS110 COORDINATE POINTS TABLE

CS111 FUEL FACILITY ELECTRICAL STRUCTURE LOCATION PLAN

CS301 SOUTH ROAD PLAN & PROFILE - 1

CS302 SOUTH ROAD PLAN & PROFILE - 2

CS303 SOUTH ROAD PLAN & PROFILE - 3

CS304 SOUTH ROAD PLAN & PROFILE - 4

CS305 SOUTH ROAD PLAN & PROFILE - 5

CS306 SOUTH ROAD PLAN & PROFILE - 6

CS307 SOUTH ROAD PLAN & PROFILE - 7

CS401 ENLARGED SITE PLAN - 1

CS501 CIVIL DETAILS - 1

CS502 CIVIL DETAILS - 2

CS503 CIVIL DETAILS - 3

CS504 CIVIL DETAILS - 4

CS505 CIVIL DETAILS - 5

CS506 CIVIL DETAILS - 6

CG001 EROSION AND SEDIMENT CONTROL PLAN - PHASE I

CG002 EROSION AND SEDIMENT CONTROL PLAN - PHASE II

CG003 EROSION AND SEDIMENT CONTROL DETAILS - 1

DOCUMENT 00 01 15 Page 4

CG004 EROSION AND SEDIMENT CONTROL DETAILS - 2

CG010 SOIL IMPROVEMENTS PLAN - NEW FUEL FACILITY

CG020 SOIL IMPROVEMENTS PLAN - EXISTING FUEL FACILITY

CG101 GRADING AND DRAINAGE PLAN - 1

CG102 GRADING AND DRAINAGE PLAN - 2

CG103 GRADING AND DRAINAGE PLAN - 3

CG104 GRADING AND DRAINAGE PLAN - 4

CG105 GRADING AND DRAINAGE PLAN - 5

CG110 GRADING COORDINATE POINTS TABLE

CG111 FUEL FACILITY STORMWATER BMP PLAN

CG401 ENLARGED GRADING AND DRAINAGE PLAN -1

CG410 GRADING POINT AND STRUCTURE TABLES

CG501 GRADING AND DRAINAGE DETAILS - 1

CG502 GRADING AND DRAINAGE DETAILS - 2

CU101 UTILITY PLAN - 1

CU102 UTILITY PLAN - 2

CU103 UTILITY PLAN - 3

CU104 UTILITY PLAN - 4

CU105 UTILITY PLAN - 5

CU301 CONTAINMENT DRAIN PROFILES - 1 OF 3

CU302 CONTAINMENT DRAIN PROFILES - 2 OF 3

CU303 CONTAINMENT DRAIN PROFILES - 3 OF 3

CU304 STORM DRAIN PROFILES - 1 OF 2

CU305 STORM DRAIN PROFILES - 2 OF 2

CU306 FUEL PROFILES - 1 OF 3

CU307 FUEL PROFILES - 2 OF 3

DOCUMENT 00 01 15 Page 5

CU308 FUEL PROFILES - 3 OF 3

CU309 SANITARY PROFILES

CU401 ENLARGED UTILITY PLAN - 1

CU501 CIVIL UTILITY DETAILS - 1

CU502 CIVIL UTILITY DETAILS - 2

CU503 CIVIL UTILITY DETAILS - 3

CU504 CIVIL UTILITY DETAILS - 4

CU505 CIVIL UTILITY DETAILS - 5

CU506 CIVIL UTILITY DETAILS - 6

CU507 CIVIL UTILITY DETAILS - 7

CU508 CIVIL UTILITY DETAILS - 8

LS401 FUEL FACILITY LANDSCAPE PLAN

LS501 LANDSCAPING DETAILS

STRUCTURAL

S-001 STRUCTURAL GENERAL NOTES

S-002 LEGENDS AND ABBREVIATIONS

S-003 STATEMENT OF SPECIAL INSPECTIONS - SHEET 1

S-004 STATEMENT OF SPECIAL INSPECTIONS - SHEET 2

S-005 STATEMENT OF SPECIAL INSPECTIONS - SHEET 3

S-006 OVERALL STRUCTURAL LAYOUT

S-101 TANK CONTAINMENT AREA - FOUNDATION PLAN

S-102 TANK CONTAINMENT AREA - SLAB PLAN

S-103 PUMPHOUSE - FOUNDATION PLAN

S-104 PUMPHOUSE - FLOOR SLAB PLAN

S-105 PUMPHOUSE - PIPE SUPPORT PLAN

S-106 PUMPHOUSE - CONTROL ROOM FRAMING PLAN

DOCUMENT 00 01 15 Page 6

S-107 PUMPHOUSE - ROOF FRAMING PLAN

S-108 PUMPHOUSE - BRIDGE CRANE PLAN AND DETAILS

S-111 POL BUILDING - FOUNDATION PLAN

S-112 POL BUILDING - SLAB PLAN

S-113 POL BUILDING - ROOF FRAMING PLAN

S-114 POL BUILDING - WIND ISOMETRIC

S-121 TRUCK OFFLOAD AND REFUELER LOAD STATIONS -

FOUNDATION AND SLAB PLAN

S-122 TRUCK OFFLOAD AND REFUELER LOAD STATIONS -

CANOPY FRAMING PLAN

S-123 REFUELER PARKING - FOUNDATION AND SLAB PLAN

S-124 REFUELER PARKING - CANOPY FRAMING PLAN

S-125 MILITARY SERVICE STATION - FOUNDATION AND SLAB PLAN

S-126 MILITARY SERVICE STATION - CANOPY FRAMING PLAN

S-127 MILITARY SERVICE STATION -

PUMP PAD CANOPY FRAMING PLAN

S-128 MILITARY SERVICE STATION - TANK CONTAINMENT PAD

S-129 REMOTE SPILL CONTAINMENT BASIN - PLANS

S-130 OWS - TOP SLAB PLAN AND DETAILS

S-131 PRODUCT RECOVERY TANK - SLAB PLAN

S-132 MISCELLANEOUS STRUCTURES

S-201 PUMPHOUSE SECTIONS AND ELEVATIONS - SHEET 1

S-202 PUMPHOUSE SECTIONS AND ELEVATIONS - SHEET 2

S-203 PUMPHOUSE MASONRY WALL ELEVATIONS - SHEET 1

S-204 PUMPHOUSE MASONRY WALL ELEVATIONS - SHEET 2

S-205 POL BUILDING ELEVATIONS - SHEET 1

S-206 POL BUILDING ELEVATIONS - SHEET 2

S-207 TRUCK OFFLOAD AND REFUELER LOAD STATIONS -

CANOPY ELEVATIONS - SHEET 1

S-208 TRUCK OFFLOAD AND REFUELER LOAD STATIONS -

CANOPY ELEVATIONS - SHEET 2

DOCUMENT 00 01 15 Page 7

S-209 REFUELER PARKING - CANOPY ELEVATIONS - SHEET 1

S-210 REFUELER PARKING - CANOPY ELEVATIONS - SHEET 2

S-211 MILITARY SERVICE STATION -

CANOPY ELEVATIONS - SHEET 1

S-212 MILITARY SERVICE STATION -

CANOPY ELEVATIONS - SHEET 2

S-213 MILITARY SERVICE STATION -

PUMP PAD CANOPY ELEVATIONS - SHEET 1

S-501 STANDARD STRUCTURAL DETAILS - SHEET 1

S-502 STANDARD STRUCTURAL DETAILS - SHEET 2

S-503 STANDARD STRUCTURAL DETAILS - SHEET 3

S-511 TANK FOUNDATION - PLAN AND SECTIONS

S-512 TANK FOUNDATION - SECTIONS AND DETAILS

S-513 CONTAINMENT AREA - SECTIONS AND DETAILS - SHEET 1

S-514 CONTAINMENT AREA - SECTIONS AND DETAILS - SHEET 2

S-515 CONTAINMENT AREA - SECTIONS AND DETAILS - SHEET 3

S-521 FOUNDATION DETAILS - SHEET 1

S-522 FOUNDATION DETAILS - SHEET 2

S-523 FOUNDATION DETAILS - SHEET 3

S-524 FOUNDATION DETAILS - SHEET 4

S-525 FOUNDATION DETAILS - SHEET 5

S-526 FOUNDATION DETAILS - SHEET 6

S-527 FOUNDATION DETAILS - SHEET 7

S-528 STEEL FRAMING DETAILS - SHEET 1

S-529 STEEL FRAMING DETAILS - SHEET 2

S-530 STEEL FRAMING DETAILS - SHEET 3

S-531 HPV AND LPD PITS - PLAN AND SECTION

S-532 REMOTE SPILL CONTAINMENT BASIN -

SECTIONS AND DETAILS

S-533 OWS HOLD-DOWN SLAB - DETAILS

DOCUMENT 00 01 15 Page 8

S-534 LIGHTPOLE FOUNDATION DETAILS

S-535 STANDARD MASONRY DETAILS - SHEET 1

S-536 STANDARD MASONRY DETAILS - SHEET 2

S-541 STAIRS AND PLATFORMS - PLANS AND SECTIONS - SHEET 1

S-542 STAIRS AND PLATFORMS - PLANS AND SECTIONS - SHEET 2

S-543 STAIRS AND PLATFORMS - PLANS AND SECTIONS - SHEET 3

S-544 STAIRS AND PLATFORMS - PLANS AND SECTIONS - SHEET 4

S-545 STAIRS AND PLATFORMS - DETAILS - SHEET 1

S-546 STAIRS AND PLATFORMS - DETAILS - SHEET 2

S-551 PIPE SUPPORT DETAILS - SHEET 1

S-552 PIPE SUPPORT DETAILS - SHEET 2

S-553 PIPE SUPPORT DETAILS - SHEET 3

S-554 PIPE SUPPORT DETAILS - SHEET 4

S-555 PIPE SUPPORT DETAILS - SHEET 5

S-556 PIPE SUPPORT DETAILS - SHEET 6

ARCHITECTURAL

AG001 ARCHITECTURAL LEGEND & ABBREVIATIONS

AL111 PUMP HOUSE LIFE SAFETY PLAN

AL121 OPS BUILDING LIFE SAFETY PLAN

A-111 PUMP HOUSE FLOOR PLAN

A-112 PUMP HOUSE ROOF AND REFLECTED CEILING PLANS

A-121 OPS BUILDING FLOOR PLAN

A-122 OPS BUILDING ROOF PLAN

A-123 OPS BUILDING REFLECTED CEILING PLAN

A-211 PUMP HOUSE EXTERIOR ELEVATIONS

A-221 OPS BUILDING EXTERIOR ELEVATIONS

DOCUMENT 00 01 15 Page 9

A-311 PUMP HOUSE BUILDING SECTIONS

A-321 OPS BUILDING SECTIONS

A-351 PUMP HOUSE WALL SECTIONS

A-361 OPS BUILDING WALL SECTIONS

A-421 OPS BUILDING ENLARGED PLANS

A-422 OPS BUILDING CASEWORK ELEVATIONS

A-423 OPS BUILDING ENLARGED TOILET PLANS

A-424 OPS BUILDING TOILET ELEVATIONS

A-501 EXTERIOR WALL DETAILS

A-502 DOOR DETAILS

A-503 WINDOW & LOUVER DETAILS

A-504 CEILING DETAILS

A-505 INTERIOR DETAILS

A-506 INTERIOR DETAILS

A-507 MILLWORK DETAILS

A-611 PUMP HOUSE SCHEDULES

A-621 OPS BUILDING DOOR SCHEDULE

A-661 OPS BUILDING WINDOW & LOUVER SCHEDULE

A-721 OPS BUILDING ROOM FINISH SCHEDULE

CATHODIC

PROTECTION

CP101 CATHODIC PROTECTION SITE PLAN - 1

CP102 CATHODIC PROTECTION SITE PLAN - 2

CP103 CATHODIC PROTECTION SITE PLAN - 3

CP104 CATHODIC PROTECTION SITE PLAN - 4

CP501 DETAIL - CATHODIC PROTECTION DETAILS 1

CP502 DETAIL - CATHODIC PROTECTION DETAILS 2

DOCUMENT 00 01 15 Page 10

CP503 DETAIL - CATHODIC PROTECTION DETAILS 3

CP504 DETAIL - CATHODIC PROTECTION DETAILS 4

CP505 DETAIL - CATHODIC PROTECTION DETAILS 5

MECHANICAL

MF001 MECHANICAL LEGEND

MF002 MECHANICAL ABBREVIATIONS & GENERAL NOTES

MF010 FLOW DIAGRAM - TYPE III HYDRANT SYSTEM

MF011 FLOW DIAGRAM - MILITARY SERVICE STATION

MF101 MECHANICAL FUELING SITE PLAN - 1

MF102 MECHANICAL FUELING SITE PLAN - 2

MF103 MECHANICAL FUELING SITE PLAN - 3

MF104 MECHANICAL FUELING SITE PLAN - 4

MF311 SECTIONS - TYPE III PUMPHOUSE - 1

MF312 SECTIONS - TYPE III PUMPHOUSE - 2

MF313 SECTION - TYPE III PUMPHOUSE - 3

MF314 SECTION - PRODUCT RECOVERY TANK

MF341 SECTIONS - TRUCK OFFLOAD POSITIONS 1 & 2

MF342 SECTIONS - TRUCK LOAD POSITIONS 1 & 2

AND HHT CHECKOUT

MF351 SECTIONS - MILITARY SERVICE STATION - 1

MF352 SECTIONS - MILITARY SERVICE STATION - 2

MF411 ENLARGED PLAN - TYPE III HYDRANT SYSTEM PUMP HOUSE

MF412 ENLARGED PLAN - PRODUCT RECOVERY TANK

MF431 ENLARGED PLAN - OPERATING STORAGE TANK 1

MF432 ENLARGED PLAN - OPERATING STORAGE TANK 2

MF441 ENLARGED PLANS - TRUCK OFFLOAD POSITIONS 1 & 2

MF442 ENLARGED PLANS - TRUCK LOAD POSTIONS 1 & 2

AND HHT CHECKOUT

DOCUMENT 00 01 15 Page 11

MF451 ENLARGED PLAN - MILITARY SERVICE STATION TANKS

MF452 ENLARGED PLAN - MILITARY SERVICE STATION TRUCK

OFFLOAD AND DISPENSERS

MF471 ENLARGED PLAN & SECTION - ISOLATION VALVE VAULT

MF501 DETAIL - TANK 1 PLAN, ELEVATION AND NOZZLE SCHEDULE

MF502 DETAIL - TANK 2 PLAN, ELEVATION AND NOZZLE SCHEDULE

MF503 DETAIL - TANK APPURTENANCE DETAILS 1

MF504 DETAIL - TANK APPURTENANCE DETAILS 2

MF505 DETAIL - TANK APPURTENANCE DETAILS 3

MF506 DETAIL - TANK APPURTENANCE DETAILS 4

MF507 DETAIL - TANK APPURTENANCE DETAILS 5

MF508 DETAIL - TANK APPURTENANCE DETAILS 6

MF509 DETAIL - TANK APPURTENANCE DETAILS 7

MF510 DETAIL - TANK APPURTENANCE DETAILS 8

MF511 DETAIL - TANK APPURTENANCE DETAILS 9

MF512 DETAIL - MECHANICAL PIPING DETAILS 1

MF513 DETAIL - MECHANICAL PIPING DETAILS 2

MF514 DETAIL - MECHANICAL PIPING DETAILS 3

MF515 DETAIL - MECHANICAL PIPING DETAILS 4

MF516 DETAIL - MECHANICAL PIPING DETAILS 5

MF517 DETAIL - MECHANICAL PIPING DETAILS 6

MF518 DETAIL - MECHANICAL PIPING DETAILS 7

MF519 DETAIL - MECHANICAL PIPING DETAILS 8

MF520 DETAIL - PRT-1 PLAN, ELEVATION, AND NOZZLE SCHEDULE

MF521 DETAIL - MSS TANKS PLAN, ELEVATION,

AND NOZZLE SCHEDULE

MF522 DETAIL - OIL WATER SEPARATORS PLAN AND ELEVATION

(OWS-01 AND OWS-02)

MF601 P&ID - OPERATING STORAGE TANKS (F-24)

DOCUMENT 00 01 15 Page 12

MF602 P&ID - PRODUCT RECOVERY TANK

MF603 P&ID - TYPE III PUMPHOUSE RECEIPT FILTRATION

MF604 P&ID - TYPE III PUMPHOUSE HYDRANT ISSUE PUMPS

AND ISSUE FILTRATION 1

MF605 P&ID - TYPE III PUMPHOUSE HYDRANT ISSUE PUMPS

AND ISSUE FILTRATION 2

MF606 P&ID - TYPE III PUMPHOUSE HYDRANT ISSUE

AND RETURN LINES

MF607 P&ID - JET FUEL TRUCK OFFLOADING

MF608 P&ID - TRUCK LOAD POSITIONS AND HHT CHECKOUT

MF609 P&ID - EXISTING HYDRANT LOOP

MF610 P&ID - MILITARY SERVICE STATION

MF611 P&ID - OIL WATER SEPARATORS OWS-01 AND OWS-02

MF612 P&ID - TYPICAL INSTRUMENTATION

MF700 SEQUENCE OF OPERATIONS - TYPE III HYDRANT

SYSTEM ISOMETRIC

MF701 SEQUENCE OF OPERATIONS - TYPE III

HYDRANT SYSTEM (1 OF 3)

MF702 SEQUENCE OF OPERATIONS - TYPE III

HYDRANT SYSTEM (2 OF 3)

MF703 SEQUENCE OF OPERATIONS - TYPE III

HYDRANT SYSTEM (3 OF 3)

MF705 SEQUENCE OF OPERATIONS - MILITARY SERVICE STATION

MF801 MECHANICAL EQUIPMENT SCHEDULES (1 OF 2)

MF802 MECHANICAL EQUIPMENT SCHEDULES (2 OF 2)

MH001 MECHANICAL HVAC NOTES, LEGEND,

SYMBOLS & ABBREVIATIONS

MH111 PUMPHOUSE - HVAC FLOOR PLAN

MH121 POL OPERATIONS BUILDING - HVAC FLOOR PLAN

MH201 AIRFLOW DIAGRAMS

MH501 HVAC DETAILS

MH502 HVAC DETAILS

MH601 HVAC SCHEDULES

MH602 HVAC SCHEDULES

DOCUMENT 00 01 15 Page 13

MH701 HVAC CONTROLS

MH702 HVAC CONTROLS

MH703 HVAC CONTROLS

MH704 HVAC CONTROLS

MH705 HVAC CONTROLS

MH706 HVAC CONTROLS

PLUMBING

P001 PLUMBING NOTES, LEGEND, SYMBOLS & ABBREVIATIONS

P111 PUMP HOUSE - PLUMBING UNDERGROUND FLOOR PLAN

P112 PUMP HOUSE - PLUMBING ABOVEGROUND FLOOR PLAN

P121 POL OPERATIONS BUILDING - PLUMBING

UNDERGROUND FLOOR PLAN

P122 POL OPERATIONS BUILDING - PLUMBING

ABOVEGROUND FLOOR PLAN

P211 PUMP HOUSE - PLUMBING RISER DIAGRAMS

P221 POL OPERATIONS BUILDING - PLUMBING RISER DIAGRAMS

P501 PLUMBING DETAILS

P502 PLUMBING DETAILS

P601 PLUMBING SCHEDULES

ELECTRICAL

E-001 ELECTRICAL LEGEND, ABBREVIATIONS & GENERAL NOTES

E-002 ELECTRICAL GENERAL NOTES AND LEGEND

E-003 ELECTRICAL GENERAL NOTES AND LEGEND

E-091 HAZARDOUS AREA CLASSIFICATION PLAN

E-092 HAZARDOUS AREA CLASSIFICATION DETAILS

E-093 HAZARDOUS AREA CLASSIFICATION DETAILS

ED101 ELECTRICAL DEMO PLAN

ES100 OVERALL SITE PLAN

DOCUMENT 00 01 15 Page 14

ES101 ELECTRICAL SITE PLAN

ES102 DUCTBANK RISER PLAN

ES103 UTILITY CONNECTION PLAN

ES501 ELECTRICAL SITE DETAILS - 1 (DUCTBANKS & CONDUIT)

ES502 ELECTRICAL SITE DETAILS - 2

(UNDERGROUND STRUCTURES)

ES503 ELECTRICAL SITE DETAILS - 3 (ELEVATIONS)

ES504 ELECTRICAL SITE DETAILS - 4 (ELEVATIONS)

ES505 ELECTRICAL SITE DETAILS - 5 (ELEVATIONS)

EP411 PUMPHOUSE CONTROL ROOM POWER PLAN

EP412 PUMPHOUSE POWER PLAN

EP413 PUMPHOUSE HVAC POWER PLAN

EP421 POL OPS BUILDING (FCC) POWER PLAN

EP431 ENLARGED PLAN - JET FUEL STORAGE TANK 1

EP432 ENLARGED PLAN - JET FUEL STORAGE TANK 2

EP433 ENLARGED PLAN - PRT & STORAGE TANK

EP434 ENLARGED PLAN - OWS-1 & OWS-2

EP441 TRUCK OFFLOAD POSITIONS 1 & 2 POWER PLAN

EP442 TRUCK REFUELER LOAD POSITIONS 1 & 2 POWER PLAN

EP451 ENLARGED PLAN - MILITARY SERVICE STATION AREA

EP452 ENLARGED PLAN - MSS STORAGE TANKS &

OFFLOAD PUMPS

EP453 ENLARGED PLAN - MSS FUEL ISLAND

EP461 REFUELER PARKING POWER PLAN

EP501 TYPICAL ELECTRICAL DETAILS

EP521 POL OPS BUILDING (FCC) POWER DETAILS

EP601 PUMPHOUSE ONE-LINE DIAGRAM

EP601A PUMPHOUSE ONE-LINE DIAGRAM (BID OPTION 12)Deleted

DOCUMENT 00 01 15 Page 15

EP602 CONTROL DIAGRAMS (FP, FTP, MOV)

EP603 ZOOM

EP604 CONTROL DIAGRAMS (JP-1 & PDP-1, LIGHTING, RECPT)

EP621 POL OPERATIONS BUILDING ONE-LINE DIAGRAM

EP641 TRUCK OFFLOAD DIAGRAMS

EP642 TRUCK LOAD DIAGRAMS

EP651 MSS DIAGRAMS - 1

EP652 MSS DIAGRAMS - 2

EP653 MSS DIAGRAMS - 3

EP701 PANELBOARD SCHEDULES

EP702 SCHEDULES - POWER CIRCUITS & SPARES

EP721 POL OPS BUILDING (FCC) PANELBOARD SCHEDULES

EL101 SITE LIGHTING PLAN

EL104 SITE LIGHTING PLAN

EL411 PUMPHOUSE LIGHTING PLAN

EL421 POL OPS BUILDING (FCC) LIGHTING PLAN

EL431 JET FUEL STORAGE TANK 1 LIGHTING PLAN

EL432 JET FUEL STORAGE TANK 2 LIGHTING PLAN

EL441 TRUCK OFFLOAD & LOAD LIGHTING PLAN

EL451 MSS STORAGE TANKS AND OFFLOAD PUMPS

LIGHTING PLAN

EL461 REFUELER PARKING LIGHTING PLAN

EL501 LIGHTING FIXTURE DETAILS

EL521 POL OPS BUILDING (FCC)

LIGHTING DETAILS

EL522 POL OPS BUILDING (FCC)

LIGHTING DETAILS

EL523 POL OPS BUILDING (FCC) LIGHTING

SCHEDULES

EG101 SITE GROUNDING PLAN

DOCUMENT 00 01 15 Page 16

EG104 SITE GROUNDING PLAN

EG411 PUMPHOUSE GROUNDING PLAN

EG412 PUMPHOUSE LIGHTNING PROTECTION PLAN

EG421 POL OPS BUILDING (FCC)

GROUNDING PLAN

EG422 POL OPS BUILDING (FCC)

LIGHTNING PROTECTION PLAN

EG431 JET FUEL TANK 1 GROUNDING PLAN

EG432 JET FUEL TANK 2 GROUNDING PLAN

EG441 TRUCK OFFLOAD & LOAD GROUNDING PLAN

EG442 TRUCK OFFLOAD & LOAD LPS PLAN

EG451 MSS STORAGE TANKS AND OFFLOAD PUMPS

GROUNDING PLAN

EG452 MSS CANOPIES LIGHTNING PROTECTION PLAN

EG453 MSS FUEL ISLAND GROUNDING PLAN

EG461 REFUELER PARKING LIGHTNING PROTECTION PLAN

EG501 TYPICAL GROUNDING DETAILS - 1

EG502 TYPICAL GROUNDING DETAILS - 2

EG503 TYPICAL LIGHTNING PROTECTION DETAILS

EG504 GROUNDING DETAILS

EG521 POL OPS BUILDING (FCC)

GROUNDING DETAILS

EG601 EMP GROUNDING AND BONDING DETAILS

EG621 POL OPS BUILDING (FCC)

GROUNDING RISER

EI501 TYPICAL PCP ELEVATION

EI502 INSTRUMENT DETAILS (MOV'S, ATG, ATG BACKBOARD)

EI503 TYPICAL TERMINAL BLOCK CONNECTIONS - 1

EI504 TYPICAL TERMINAL BLOCK CONNECTIONS - 2

EI505 TYPICAL TERMINAL BLOCK CONNECTIONS - 3

EI506 GRAPHIC DISPLAY LAYOUT

DOCUMENT 00 01 15 Page 17

EI601 CONTROL SYSTEM DIAGRAM

EI602 FUEL COMMS, ATG, & FMS RISER DIAGRAM

EI603 SYSTEM I-O - 1

EI604 SYSTEM I-O - 2

EI605 SYSTEM I-O - 3

EI701 CIRCUIT SCHEDULE-1

EI702 CIRCUIT SCHEDULE-2

EI703 CIRCUIT SCHEDULE-3

ET001 TELECOMMUNICATIONS GENERAL

NOTES, LEGEND AND ABBREVIATIONS

ET411 PUMPHOUSE COMMUNICATIONS PLAN

ET421 POL OPS BUILDING (FCC)

TELECOMMUNICATIONS PLAN

ET501 COMMUNICATIONS DETAILS

ET521 POL OPS BUILDING (FCC)

TELECOMMUNICATIONS DETAILS

ET522 POL OPS BUILDING (FCC)

TELECOMMUNICATIONS DETAILS

ET601 RISER DIAGRAM - OUTSIDE PLANT, DDC, & GEN CONTROLS

FIRE

PROTECTION

FA001 FIRE ALARM NOTES, LEGEND AND ABBREVIATIONS

FA101 FIRE ALARM AND MASS NOTIFICATION PLAN

FA501 FIRE ALARM DETAILS

FA601 FIRE ALARM RISER

FA602 FIRE ALARM MATRIX - POL OPERATIONS BUILDING

FA603 FIRE ALARM MATRIX - PUMPHOUSE

FX001 FIRE SUPPRESSION NOTES, LEGEND AND ABBREVIATIONS

FX101 FIRE SUPPRESSION PLAN

FX601 FIRE SUPPRESSION RISER

-- End of Document --

DOCUMENT 00 01 15 Page 18

DIVISION 26 - ELECTRICAL

SECTION 26 24 13

SWITCHBOARDS

05/15

PART 1 GENERAL

1.1 REFERENCES

1.2 RELATED REQUIREMENTS

1.3 DEFINITIONS

1.4 SUBMITTALS

1.5 QUALITY ASSURANCE

1.5.1 Product Data

1.5.2 Switchboard Drawings

1.5.3 Regulatory Requirements

1.5.4 Standard Products

1.5.4.1 Alternative Qualifications

1.5.4.2 Material and Equipment Manufacturing Date

1.6 MAINTENANCE

1.6.1 Switchboard Operation and Maintenance Data

1.6.2 Assembled Operation and Maintenance Manuals

1.7 WARRANTY

PART 2 PRODUCTS

2.1 PRODUCT COORDINATION

2.2 SWITCHBOARD

2.2.1 Ratings

2.2.2 Construction

2.2.2.1 Enclosure

2.2.2.2 Bus Bars

2.2.2.3 Main Section

2.2.2.4 Distribution Sections

2.2.3 Protective Device

2.2.3.1 Insulated-Case Breaker

2.2.3.2 Molded-Case Circuit Breaker

2.2.4 Not Used

2.2.5 Metering

2.2.5.1 Digital Meters

2.2.6 Terminal Boards

2.2.7 Wire Marking

2.2.8 Not Used

2.3 MANUFACTURER'S NAMEPLATE

2.4 FIELD FABRICATED NAMEPLATES

2.5 SOURCE QUALITY CONTROL

2.5.1 Equipment Test Schedule

2.5.2 Switchboard Design Tests

2.5.2.1 Design Tests

2.5.3 Switchboard Production Tests

2.6 ARC FLASH WARNING LABEL

2.7 SERVICE ENTRANCE AVAILABLE FAULT CURRENT LABEL

SECTION 26 24 13 Page 1

2.8 MIMIC BUS LABELING

PART 3 EXECUTION

3.1 INSTALLATION

3.2 GROUNDING

3.2.1 Grounding Electrodes

3.2.2 Equipment Grounding

3.2.3 Connections

3.2.4 Grounding and Bonding Equipment

3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES

3.3.1 Switchboard

3.3.2 Meters and Instrument Transformers

3.3.3 Field Applied Painting

3.3.4 Galvanizing Repair

3.3.5 Field Fabricated Nameplate Mounting

3.4 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES

3.4.1 Interior Location

3.5 FIELD QUALITY CONTROL

3.5.1 Performance of Acceptance Checks and Tests

3.5.1.1 Switchboard Assemblies

3.5.1.2 Circuit Breakers

3.5.1.3 Current Transformers

3.5.1.4 Metering and Instrumentation

3.5.1.5 Grounding System

3.5.2 Follow-Up Verification

-- End of Section Table of Contents --

SECTION 26 24 13 Page 2

SECTION 26 24 13

SWITCHBOARDS

05/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI C12.1 ((2014; Errata 2016) Electric Meters - Code for Electricity Metering

ASTM INTERNATIONAL (ASTM)

ASTM A780/A780M (2009; R 2015) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings

ASTM D1535 (2014; R 2018) Standard Practice for Specifying Color by the Munsell System

ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 100 (2000; Archived) The Authoritative Dictionary of IEEE Standards Terms

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code

INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

NETA ATS (2017; Errata 2017) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

ANSI/NEMA PB 2.1 (2013) General Instructions for Proper Handling, Installation, Operation and Maintenance of Deadfront Distribution Switchboards Rated 600 V or Less

NEMA ICS 6 (1993; R 2016) Industrial Control and Systems: Enclosures

NEMA PB 2 (2011) Deadfront Distribution Switchboards

SECTION 26 24 13 Page 3

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

UNDERWRITERS LABORATORIES (UL)

UL 467 (2013; Reprint Jun 2017) UL Standard for Safety Grounding and Bonding Equipment

UL 489 (2016) UL Standard for Safety Molded-Case Circuit Breakers, Molded-Case Switches and Circuit-Breaker Enclosures

UL 891 (2005; Reprint Oct 2012) Switchboards

1.2 RELATED REQUIREMENTS

Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section, with the additions and modifications specified herein.

1.3 DEFINITIONS

Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, are as defined in

IEEE 100.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor QC approval.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Switchboard Drawings; G

SD-03 Product Data

Switchboard; G

SD-06 Test Reports

Switchboard Design Tests; G

Switchboard Production Tests; G

Acceptance Checks and Tests; G

SD-10 Operation and Maintenance Data

Switchboard Operation and Maintenance, Data Package 5; G

SD-11 Closeout Submittals

SECTION 26 24 13 Page 4

Assembled Operation and Maintenance Manuals; G

Equipment Test Schedule; G

Request for Settings; G

Service Entrance Available Fault Current Label; G

1.5 QUALITY ASSURANCE

1.5.1 Product Data

Include manufacturer's information on each submittal for each component, device and accessory provided with the switchboard including:

a. Circuit breaker type, interrupting rating, and trip devices, including available settings.

b. Manufacturer's instruction manuals and published time-current curves (in electronic format) of the main secondary breaker and largest secondary feeder device.

1.5.2 Switchboard Drawings

Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Identify circuit terminals on wiring diagrams and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Indicate on the drawings adequate clearance for operation, maintenance, and replacement of operating equipment devices. Include the nameplate data, size, and capacity on submittal. Also include applicable federal, military, industry, and technical society publication references on submittals. Include the following:

a. One-line diagram including breakers, current transformers, and meters.

b. Outline drawings including front elevation, section views, footprint, and overall dimensions.

c. Bus configuration including dimensions and ampere ratings of bus bars.

d. Markings and NEMA nameplate data.

e. Circuit breaker type, interrupting rating, and trip devices, including available settings.

f. Wiring diagrams and elementary diagrams with terminals identified, and indicating prewired interconnections between items of equipment and the interconnection between the items.

g. Manufacturer's instruction manuals and published time-current curves (in electronic format) of the main secondary breaker and largest secondary feeder device. Use this information (designer of record) to provide breaker settings that ensures protection and coordination are achieved.

SECTION 26 24 13 Page 5

1.5.3 Regulatory Requirements

In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" or "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Provide equipment, materials, installation, and workmanship in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.

1.5.4 Standard Products

Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship, and:

a. Have been in satisfactory commercial or industrial use for 2 years prior to bid opening including applications of equipment and materials under similar circumstances and of similar size.

b. Have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.

c. Where two or more items of the same class of equipment are required, provide products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.

1.5.4.1 Alternative Qualifications

Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.

1.5.4.2 Material and Equipment Manufacturing Date

Products manufactured more than 1 year prior to date of delivery to site are not acceptable.

1.6 MAINTENANCE

1.6.1 Switchboard Operation and Maintenance Data

Submit Operation and Maintenance Manuals in accordance with Section 01 78 23

OPERATION AND MAINTENANCE DATA.

1.6.2 Assembled Operation and Maintenance Manuals

Assemble and securely bind manuals in durable, hard covered, water resistant binders. Assemble and index the manuals in the following order with a table of contents:

a. Manufacturer's O&M information required by the paragraph SD-10, OPERATION AND MAINTENANCE DATA.

b. Catalog data required by the paragraph SD-03, PRODUCT DATA.

SECTION 26 24 13 Page 6

c. Drawings required by the paragraph SD-02, SHOP DRAWINGS.

d. Prices for spare parts and supply list.

e. Information on metering.

f. Design test reports.

g. Production test reports.

1.7 WARRANTY

Provide equipment items that are supported by service organizations reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

PART 2 PRODUCTS

2.1 PRODUCT COORDINATION

Products and materials not considered to be switchboards and related accessories are specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION, and Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.

2.2 SWITCHBOARD

NEMA PB 2 and UL 891.

2.2.1 Ratings

Provide equipment with the following ratings:

a. Voltage rating: 480 volts AC, three-phase, 3-wire.

b. Continuous current rating of the main bus: Amperes.

c. Short-circuit current rating: 42k rms symmetrical amperes.

d. UL listed and labeled as service entrance equipment.

2.2.2 Construction

Provide the following:

a. Switchboard: Consisting of one or more vertical sections bolted together to form a rigid assembly and rear aligned.

b. All circuit breakers: Front accessible.

c. Rear aligned switchboards: Front accessible load connections.

d. Where indicated, "space for future" or "space" means to include a vertical bus provided behind a blank front cover. Where indicated, "provision for future" means full hardware provided to mount a breaker suitable for the location.

e. Completely factory engineered and assembled, including protective devices and equipment indicated with necessary interconnections, SECTION 26 24 13 Page 7 instrumentation, and control wiring.

2.2.2.1 Enclosure

Provide the following:

a. Enclosure: NEMA ICS 6 Type 1.

b. Enclosure: Bolted together with removable bolt-on side and rear covers. Provide copper braided bonding straps between all panels, doors, and frame to form a continuous bond.

c. Front doors: Provided with padlockable vault handles with a three point catch.

d. Base: Includes any part of enclosure that is within 3 inches of concrete pad.

e. Paint color: ASTM D1535 light gray No. 61 or No. 49 over rust inhibitor.

2.2.2.2 Bus Bars

Provide the following:

a. Bus bars: Aluminum with tin-plated contact surfaces.

(1) Phase bus bars: Uninsulated.

(2) Neutral bus: Rated 100 percent of the main bus continuous current rating.

b. Make bus connections and joints with hardened steel bolts.

c. Main-bus (through bus): Rated at the full ampacity of the main throughout the switchboard.

d. Minimum 1/4 by 2 inch copper ground bus secured to each vertical section along the entire length of the switchboard.

2.2.2.3 Main Section

*Am-1 Provide the main section consisting of an insulated-case circuit breaker (for the utility feed), and digital meter, and power equipment for relays (Bid Option 12). Utility breaker shall be fixed mounted.

2.2.2.4 Distribution Sections

Provide the distribution section consisting ofindividually mounted, insulated-case circuit breakers, and molded-case circuit breakers as indicated.

2.2.3 Protective Device

Provide main and branch protective devices as indicated.

2.2.3.1 Insulated-Case Breaker

*Am-1 Provide the following:

SECTION 26 24 13 Page 8

a. UL 489. UL listed and labeled, 100 percent rated main breaker, manually operated, low voltage, insulated-case circuit breaker, with a short-circuit current rating of 42k rms symmetrical amperes at 480 volts. (Provide electrically operated insulated-case breakers for Bid Option 12.)

b. Breaker frame size: As indicated.

c. Series rated circuit breakers are unacceptable.

2.2.3.2 Molded-Case Circuit Breaker

Provide the following:

a. UL 489. UL listed and labeled, standard rated branch breakers, manually operated, low voltage molded-case circuit breaker, with a short-circuit current rating of 42 rms symmetrical amperes at 480 volts.

b. Breaker frame size: As indicated.

c. Series rated circuit breakers are unacceptable.

*Am-1

2.2.4 Not UsedElectronic Trip Units

Bid Option 12 Equip main and distribution breakers with a solid-state tripping system consisting of three current sensors and a microprocessor-based trip unit SEL 751 (base standard) with mirror bits communications that provides true rms sensing adjustable time-current circuit protection. Include the following:

a. Current sensors ampere rating: As indicated.

b. Trip unit ampere rating: As indicated.

c. Ground fault protection: Zero sequence sensing.

d. Electronic trip units: Provide additional features:

(1) Main breakers: Include short delay pick-up and time settings, instantaneous settings and ground fault settings.

(2) Distribution breakers: Include short delay pick-up and time settings, instantaneous settings, and ground fault settings.

(3) Breakers: Include provisions for communication via a network twisted pair cable for remote monitoring and control. Provide the following communications protocol: Modbus.

(4) For electronic trip units that are rated for or can be adjusted to 1,200 amperes or higher, provide arc energy reduction capability with an energy-reducing maintenance switch with local status indicator.

(5) Electronic operation shall include remote opening and closing of breaker via digital inputs to breaker from relays or control panels as indicated.

SECTION 26 24 13 Page 9

2.2.5 Metering

2.2.5.1 Digital Meters

Provide Electro Industries Nexus 1500+ digital meter, or approved equal.

Meter shall include integrated display with 1.1 MB logging memory, and 1024 samples/cycle resolution. Meter shall be current class 2 (2A), 18-60 volts dc control power, and accept line-to-line voltage from 100-600 volts ac.

Communication ports shall include 10Base-T/100Base-Tx Ethernet (RJ45).

Provide Ethernet to BACnet protocol converter for communications to the Base ALC. Provide meter with a minimum of 16 digital inputs, and 6 digital outputs. Metering data shall be communicated to the Base ALC via BACNet protocol.

2.2.6 Terminal Boards

Provide with engraved plastic terminal strips and screw type terminals for external wiring between components and for internal wiring between removable assemblies. Provide short-circuiting type terminal boards associated with current transformer. Terminate conductors for current transformers with ring-tongue lugs. Provide terminal board identification that is identical in similar units. Provide color coded external wiring that is color coded consistently for similar terminal boards.

2.2.7 Wire Marking

Mark control and metering conductors at each end. Provide factory installed, white, plastic tubing, heat stamped with black block type letters on factory-installed wiring. On field-installed wiring, provide white, preprinted, polyvinyl chloride (PVC) sleeves, heat stamped with black block type letters. Provide a single letter or number on each sleeve, elliptically shaped to securely grip the wire, and keyed in such a manner to ensure alignment with adjacent sleeves. Provide specific wire markings using the appropriate combination of individual sleeves. Indicate on each wire marker the device or equipment, including specific terminal number to which the remote end of the wire is attached.

*Am-1

2.2.8 Not UsedIndicator LED

Provide indicator LEDs and placard to show position of generator enclosure mounted 3 position mode switch.

2.3 MANUFACTURER'S NAMEPLATE

Provide a nameplate on each item of equipment bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent is not acceptable. This nameplate and method of attachment may be the manufacturer's standard if it contains the required information.

2.4 FIELD FABRICATED NAMEPLATES

ASTM D709. Provide laminated plastic nameplates for each switchboard, equipment enclosure, relay, switch, and device; as specified in this section or as indicated on the drawings. Identify on each nameplate inscription the function and, when applicable, the position. Provide nameplates of melamine plastic, 0.125 inch thick, white with black center

SECTION 26 24 13 Page 10 core. Provide matte finish surface. Provide square corners. Accurately align lettering and engrave into the core. Provide nameplates with minimum size of 1 by 2.5 inches. Provide lettering that is a minimum of 0.25 inch high normal block style.

2.5 SOURCE QUALITY CONTROL

2.5.1 Equipment Test Schedule

The Government reserves the right to witness tests. Provide equipment test schedules for tests to be performed at the manufacturer's test facility.

Submit required test schedule and location, and notify the Contracting Officer 30 calendar days before scheduled test date. Notify Contracting Officer 15 calendar days in advance of changes to scheduled date.

Provide the following as part of test equipment calibration:

a. Provide a calibration program which assures that all applicable test instruments are maintained within rated accuracy.

b. Accuracy: Traceable to the National Institute of Standards and Technology.

c. Instrument calibration frequency schedule: Less than or equal to 12 months for both test floor instruments and leased specialty equipment.

d. Dated calibration labels: Visible on all test equipment.

e. Calibrating standard: Higher accuracy than that of the instrument tested.

f. Keep up-to-date records that indicate dates and test results of instruments calibrated or tested. For instruments calibrated by the manufacturer on a routine basis, in lieu of third party calibration, include the following:

(1) Maintain up-to-date instrument calibration instructions and procedures for each test instrument.

(2) Identify the third party/laboratory calibrated instrument to verify that calibrating standard is met.

2.5.2 Switchboard Design Tests

NEMA PB 2 and UL 891.

2.5.2.1 Design Tests

Furnish documentation showing the results of design tests on a product of the same series and rating as that provided by this specification.

a. Short-circuit current test.

b. Enclosure tests.

c. Dielectric test.

SECTION 26 24 13 Page 11

2.5.3 Switchboard Production Tests

NEMA PB 2 and UL 891. Furnish reports which include results of production tests performed on the actual equipment for this project. These tests include:

a. 60-hertz dielectric tests.

b. Mechanical operation tests.

c. Electrical operation and control wiring tests.

d. Ground fault sensing equipment test.

2.6 ARC FLASH WARNING LABEL

Provide warning label for switchboards. Locate this self-adhesive warning label on the outside of the enclosure warning of potential electrical arc flash hazards and appropriate PPE required. Provide label format as indicated.

2.7 SERVICE ENTRANCE AVAILABLE FAULT CURRENT LABEL

Provide label on exterior of switchboards used as service equipment listing the maximum available fault current at that location. Include on the label the date that the fault calculation was performed and the contact information for the organization that completed the calculation. Locate this self-adhesive warning label on the outside of the switchboard.

Provide label format as indicated.

2.8 MIMIC BUS LABELING

*Am-1 Provide a mimic bus on the front of the equipment to diagrammatically show the internal bus structure, relaying, and control configuration of the lineup.

PART 3 EXECUTION

3.1 INSTALLATION

Conform to IEEE C2, NFPA 70, and to the requirements specified herein.

Provide new equipment and materials unless indicated or specified otherwise.

3.2 GROUNDING

NFPA 70 and IEEE C2, except that grounds and grounding systems with a resistance to solid earth ground not exceeding 1 ohm.

3.2.1 Grounding Electrodes

Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of the ground rods by exothermic weld or compression connector. Provide compression connectors at equipment end of ground conductors.

3.2.2 Equipment Grounding

Refer to Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION for equipment grounding requirements.

SECTION 26 24 13 Page 12

3.2.3 Connections

Make joints in grounding conductors and loops by exothermic weld or compression connector. Install exothermic welds and compression connectors as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION.

3.2.4 Grounding and Bonding Equipment

UL 467, except as indicated or specified otherwise.

3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES

Install and connect equipment furnished under this section as indicated on project drawings, the approved shop drawings, and as specified herein.

3.3.1 Switchboard

ANSI/NEMA PB 2.1.

3.3.2 Meters and Instrument Transformers

ANSI C12.1.

3.3.3 Field Applied Painting

Where field painting of enclosures is required to correct damage to the manufacturer's factory applied coatings, provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.

3.3.4 Galvanizing Repair

Repair damage to galvanized coatings using ASTM A780/A780M, zinc rich paint, for galvanizing damaged by handling, transporting, cutting, welding, or bolting. Do not heat surfaces that repair paint has been applied to.

3.3.5 Field Fabricated Nameplate Mounting

Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.

3.4 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES

3.4.1 Interior Location

Mount switchboard on concrete slab as follows:

a. Unless otherwise indicated, provide the slab with dimensions at least 4 inches thick.

b. Install slab such that the top of the concrete slab is approximately 4 inches above the finished grade.

c. Provide edges above grade 1/2 inch chamfer.

d. Provide slab of adequate size to project at least 8 inches beyond the equipment.

SECTION 26 24 13 Page 13

e. Provide conduit turnups and cable entrance space required by the equipment to be mounted.

f. Seal voids around conduit openings in slab with water- and oil-resistant caulking or sealant.

g. Cut off and bush conduits 3 inches above slab surface.

h. Provide concrete work as specified in Section 03 30 00 CAST-IN-PLACE

CONCRETE.

3.5 FIELD QUALITY CONTROL

Submit request for settings of breakers to the Contracting Officer after approval of switchboard and at least 30 days in advance of their requirement.

3.5.1 Performance of Acceptance Checks and Tests

Perform in accordance with the manufacturer's recommendations and include the following visual and mechanical inspections and electrical tests, performed by independent NETA or NICET certified technician in accordance with NETA ATS.

3.5.1.1 Switchboard Assemblies

a. Visual and Mechanical Inspection:

(1) Compare equipment nameplate data with specifications and approved shop drawings.

(2) Inspect physical, electrical, and mechanical condition.

(3) Verify appropriate anchorage, required area clearances, and correct alignment.

(4) Clean switchboard and verify shipping bracing, loose parts, and documentation shipped inside cubicles have been removed.

(5) Inspect all doors, panels, and sections for paint, dents, scratches, fit, copper braided bonding strap, and missing hardware.

(6) Verify that circuit breaker sizes and types correspond to approved shop drawings as well as to the circuit breaker’s address for microprocessor-communication packages.

(7) Verify that current transformer ratios correspond to approved shop drawings.

(8) Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey.

(9) Confirm correct operation and sequencing of electrical and mechanical interlock systems.

(10) Confirm correct application of manufacturer's recommended lubricants.

SECTION 26 24 13 Page 14

(11) Inspect insulators for evidence of physical damage or contaminated surfaces.

(12) Verify correct barrier installation and operation.

(13) Exercise all active components.

(14) Inspect all mechanical indicating devices for correct operation.

(15) Verify that filters are in place and vents are clear.

(16) Test operation, alignment, and penetration of instrument transformer withdrawal disconnects.

(17) Inspect control power transformers.

*Am-1

(18) Arc flash and, fault/coordination calculations and protective relay / electronic trip unit setting provided independent of the electrical contractor using a NETA or NICET certified engineering firm or approved substitute.

b. Electrical Tests:

(1) Perform insulation-resistance tests on each bus section.

(2) Perform dielectric withstand voltage tests.

(3) Perform insulation-resistance test on control wiring; do not perform this test on wiring connected to solid-state components.

(4) Perform control wiring performance test.

(5) Perform primary current injection tests on the entire current circuit in each section of assembly.

3.5.1.2 Circuit Breakers

*Am-1 Low Voltage - Insulated-Case and Low Voltage Molded Case with Solid State Trips:

a. Visual and Mechanical Inspection:

(1) Compare nameplate data with specifications and approved shop drawings.

(2) Inspect circuit breaker for correct mounting.

(3) Operate circuit breaker to ensure smooth operation.

(4) Inspect case for cracks or other defects.

(5) Inspect all bolted electrical connections for high resistance using low resistance ohmmeter, verifying tightness of accessible bolted connections and/or cable connections by calibrated torque-wrench method, or performing thermographic survey.

(6) Inspect mechanism contacts and arc chutes in unsealed units.

SECTION 26 24 13 Page 15

b. Electrical Tests:

(1) Perform contact-resistance tests.

(2) Perform insulation-resistance tests.

(3) Perform Breaker adjustments for final settings in accordance with Government provided settings.

(4) Perform long-time delay time-current characteristic tests.

(5) Determine short-time pickup and delay by primary current injection.

(6) Determine ground-fault pickup and time delay by primary current injection.

(7) Determine instantaneous pickup current by primary injection.

(8) Verify correct operation of any auxiliary features such as other IEEE device functions such as 27/59, 25, 32, 67 and inter trip unit communications, trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free, and anti-pump function.

3.5.1.3 Current Transformers

a. Visual and Mechanical Inspection:

(1) Compare equipment nameplate data with specifications and approved shop drawings.

(2) Inspect physical and mechanical condition.

(3) Verify correct connection.

(4) Verify that adequate clearances exist between primary and secondary circuit.

(5) Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey.

(6) Verify that all required grounding and shorting connections provide good contact.

b. Electrical Tests:

(1) Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable.

(2) Perform insulation-resistance tests.

(3) Perform polarity tests.

(4) Perform ratio-verification tests.

SECTION 26 24 13 Page 16

3.5.1.4 Metering and Instrumentation

a. Visual and Mechanical Inspection:

(1) Compare equipment nameplate data with specifications and approved shop drawings.

(2) Inspect physical and mechanical condition.

(3) Verify tightness of electrical connections.

b. Electrical Tests:

(1) Determine accuracy of meters at 25, 50, 75, and 100 percent of full scale.

(2) Calibrate watthour meters according to manufacturer's published data.

(3) Verify all instrument multipliers.

(4) Electrically confirm that current transformer and voltage transformer secondary circuits are intact.

(5) Confirm meter and status contact information is passed via BACNet to ALC system interface.

3.5.1.5 Grounding System

Refer to Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION for grounding system test requirements.

3.5.2 Follow-Up Verification

Upon completion of acceptance checks, settings, and tests, show by demonstration in service that circuits and devices are in good operating condition and properly performing the intended function. Trip circuit breakers by operation of each protective device. Test each item to perform its function not less than three times. As an exception to requirements stated elsewhere in the contract, provide the Contracting Officer 5 working days advance notice of the dates and times for checks, settings, and tests. Independent NETA or NICET certified technician or approved substitute to provide a written acceptance testing report to the Contracting Officer.

-- End of Section --

SECTION 26 24 13 Page 17

This page was intentionally left blank for duplex printing.

DIVISION 26 - ELECTRICAL

SECTION 26 28 01.00 10

COORDINATED POWER SYSTEM PROTECTION

10/07

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 QUALITY ASSURANCE

1.3.1 System Coordinator

1.3.2 System Installer

1.4 DELIVERY, STORAGE, AND HANDLING

1.5 PROJECT/SITE CONDITIONS

PART 2 PRODUCTS

2.1 STANDARD PRODUCT

2.2 NAMEPLATES

2.3 COORDINATED POWER SYSTEM PROTECTION

2.3.1 Scope of Analyses

2.3.2 Determination of Facts

2.3.3 Single Line Diagram

2.3.4 Fault Current Analysis

2.3.4.1 Method

2.3.4.2 Data

2.3.4.3 Fault Current Availability

2.3.5 Coordination Study

2.3.6 Study report

PART 3 EXECUTION

3.1 EXAMINATION

3.2 INSTALLATION

3.3 FIELD TESTING

3.3.1 General

3.3.2 Safety

3.3.3 Molded-Case Circuit Breakers

3.3.4 Protective Relays

-- End of Section Table of Contents --

SECTION 26 28 01.00 10 Page 1

SECTION 26 28 01.00 10

COORDINATED POWER SYSTEM PROTECTION

10/07

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 242 (2001; Errata 2003) Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems - Buff Book

IEEE 399 (1997) Brown Book IEEE Recommended Practice for Power Systems Analysis

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-310-04 (2013; with Change 1, 2016) Seismic Design of Buildings

UNDERWRITERS LABORATORIES (UL)

UL 489 (2016) UL Standard for Safety Molded-Case Circuit Breakers, Molded-Case Switches and Circuit-Breaker Enclosures

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Fault Current Analysis

SECTION 26 28 01.00 10 Page 2

Protective Device Coordination Study

Equipment

System Coordinator

Protective Relays

Installation

SD-06 Test Reports

Field Testing

SD-07 Certificates

Devices and Equipment

1.3 QUALITY ASSURANCE

1.3.1 System Coordinator

System coordination, recommended ratings and settings of protective devices, and design analysis shall be accomplished by a registered professional electrical power engineer with a minimum of 3 years of current experience in the coordination of electrical power systems. Submit verification of experience and license number, of a registered Professional Engineer as specified above.

This is the start of the file's text. The full file is on GovTribe.