Attachment 69 - MCAA Entity Move Report (Overall).pdf
PDF 429 KB Posted
- Solicitation number
- W9127S22R6001
About this file
This document provides details for an initial outfitting and transition supply contract opportunity for the Medical Center Addition and Alteration project at the Walter Reed National Military Medical Center in Bethesda, Maryland. The contract is for a firm-fixed price and involves relocating equipment, transitioning personnel, and excessing assets from buildings scheduled for demolition or renovation to new and renovated spaces. The project includes outfitting and transition services for over 700,000 gross square feet of new, renovated, and temporary facilities. The delivery period is approximately 1870 days. The solicitation is expected to be posted on February 1, 2022 to a Service-Disabled Veteran Owned Small Business set-aside. The United States Army Corps of Engineers Engineering District in Little Rock, Arkansas will administer the contract to support the Naval Support Activity in Bethesda, Maryland and Defense Health Agency with the Medical Center Addition and Alteration project designed by HDR and constructed by CLARK Construction.
View the file
Other files
Show 40 more
Latest 50 of 90 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CMP-MCAA Movement Plan
Friday, December 04, 2020
Alphabetical Report
Addiction Treatment Services* Current Location: Building 7, Floor 4
Future Location: Building C, Floor 4
Relocating from Building 7, Floor 4 to the temp medical facility (85T) in the G Lot, Floor 2. (MCAA Phase I) Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II)
Winter/Spring 2021 (Move 2) Spring/Summer 2027 (Move 3)
Ambulatory Procedures Unit (3E) Current Location: Building 10, Floor 3
Future Location: Building C, Floor 3
Relocating from Building 10, Floor 3 to Building C, Floor 3. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Ambulatory Procedures Unit Pre-Screen Current Location: Building 9, Floor 3
Future Location: Building C, Floor 3
Relocating from Building 9, Floor 3 to Building C, Floor 3. (MCAA Phase I)Summer/Fall 2024 (Move 2)
American Red Cross Current Location: Building 8, Floor 2
Future Location: Building C, Floor 2
Relocating from Building 8, Floor 2 to the temporary medical facility (offices) and cube farm, Building 9, Floor 1 (storage/carts).
Relocating from temporary medical facility (offices) and cube farm, Building 9, Floor 1 (storage/carts) to Building C, Floor 2. (MCAA Phase II)
Oct 2018 (Move 1)
Spring/Summer 2027 (Move 3)
Anesthesia Current Location: Building 9, Floor 3
Future Location: Building C, Floor 3
Relocating Pre-Op Holding and Regional Pain Block to Building C, Floor 3. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Audiovisual Department (NMSC) Current Location: Building 3/5, Floor 1
Future Location: Building C, Floor 0
Relocating from Building 5, Floor 1 to Building C, Floor 0. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Baylor Residents Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Command Urinalysis (Civilian and Military) Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Department of Medicine Headquarters Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Department of Surgery Headquarters Current Location: Building 8, Floor 5
Future Location: Building 9, Floor 2
Relocating from Building 8, Floor 5 to the temporary medical facility in the G Lot, Floor 2.
Relocating from the temporary medical facility in the G Lot, Floor 2 to Building 9, Floor 2. (MCAA Phase II) Oct 2017 (Move 1) Spring/Summer 2027 (Move 3)
Director for Clinical Support (Admin) Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 6 to the temporary medical facility in the G Lot, Floor 2.
Relocating from the temporary medical facility in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Director for Medicine (Admin) Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 6 to the temporary medical facility in the G Lot, Floor 2.
Relocating from the temporary medical facility in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Education, Training and Research Classrooms Current Location: Building 3/5, Floor 3 & 4
Future Location: Building C, Floor 1
Expanding from Building 3/5, Floor 3 & 4 to Building C, Floor 1. (MCAA Phase II)Spring/Summer 2027 (Move 3)
Updated by the OIC, DHA-Project Site Office Bethesda All locations, move phases, and timelines are subject to change.
Alphabetical Report
Equal Employment Opportunity Manager Current Location: Building 8, Floor 6
Future Location: Building C, Floor 4 Relocating from
Building 8, Floor 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Executive Medicine Current Location: Building 7, Floor 1
Future Location: Building C, Floor 2
Relocating from Building 7, Floor 1 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
General Surgery Current Location: Building 9, Floor 1
Future Location: Building 9, Floor 2
Expanding from Building 9, Floor 1 to Building 9, Floor 2. (MCAA Phase II)Spring/Summer 2027 (Move 3)
Housekeeping Current Location: Building 2, Floor 1
Future Location: Building C, Floor 0
Relocating from Building 2, Floor 1 to TBD. (MCAA Phase I) Relocating from TBD to Building C, Floor 0. (MCAA Phase II)
Summer/Fall 2024 (Move 2) Spring/Summer 2027 (Move 3)
Infectious Diseases Current Location: Building 7, Floor 1
Future Location: Building C, Floor 4
Relocating from Building 7, Floor 1 to Building C, Floor 4. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Current Location: Building 10, Floors 5 & 6Inpatient Medical/Surgical Ward (5/6W, 5/6C, 5/6E)*
Summer/Fall 2024 (Move 2)
Inpatient Physical and Occupational Therapy Current Location: Building 10, Floor 3
Future Location: Building 10, Floor 3
Expanding from Building 10, Floor 3 Center to Building 10, Floor 3 East. Phasing and temporary locations TBD. (MCAA Phase III)
Spring/Summer 2027 (Move 3)
Medical Photography (NMSC)* Current Location: Building 4/6, Floor 2
Future Location: Building C, Floor 0
Relocating from Building 4/6, Floor 2 to TBD.
Relocating from temporary location to Building C, Floor 0. (MCAA Phase I) Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Medical Readiness and Operational/Deployment Health
Relocating from Building 8, Floor 2 to Building 7, Floor 2.
Relocating from Building 7, Floor 2 to Building C, Floor 2. (MCAA Phase I) Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Memorial Auditorium Current Location: Building 2, Floor 3 & 4
Future Location: Building C, Floor 1
Closes Fall 2023. (MCAA Phase I) Opens in Building C, Floor 1. (MCAA Phase II)
Summer/Fall 2024 (Move 2) Spring/Summer 2027 (Move 3)
Military Medical Records Current Location: Building 2, Floor 2
Future Location: Building C, Floor 2
Relocating from Building 2, Floor 2 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Mother Infant Care Center Current Location: Building 10, Floor 6
Future Location: Building C, Floor 5
Relocating from Building 10, Floor 6 to Building C, Floor 5. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Naval Dosimetry Center Current Location: Building 4/6, Floor 4
Future Location: Building C, Floor 0 .
March, 2014
Summer/Fall 2024 (Move 2)
Updated by the OIC, DHA-Project Site Office Bethesda All locations, move phases, and timelines are subject to change.
Begins the 22 month certification process to relocate Naval Dosimetry Center into temp medical facility (84T) Relocating from the temp medical facility (85T) in the G Lot, Floor 1 to Building C, Floor 0. (MCAA Phase I)
Education, Training and Research Simulation Center Current Location: Building 3/5, Floor 4 Future Location: Building C, Floor 2
Spring/Summer 2027 (Move 3) Expanding from Building 3/5, Floor 4 to Building C, Floor 3. (MCAA Phase II)
Current Location: Building 8, Floor 2 Future Location: Building C, Floor 2
Phasing and temporary location sequencing TBD. (MCAA Phase III) Future Location: Building 10, Floors 5 & 6
Alphabetical Report
Occupational Audiology / Hearing Conservation Current Location: Building 7, Floor 2
Relocating from new designated location in Building C, Floor 2. (MCAA Phase II)
Future Locations: Bldg 3/5 Flr (TBD) then to Bdg C, Flr 2
Spring/Summer 2027 (Move 3)
Occupational Medicine* Current Location: Building 7, Floor 2
Future Location: Building C, Floor 2
Relocating from Building 7, Floor 2 to the temp medical facility (86T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 2. (MCAA Phase II) Oct 2017 (Move 1) Summer 2026 (Move 3)
Current Location: Building 9, Floor 3
Future Location: Building C, Floor 3
Additional 2 Operating Rooms in Building C, Floor 3. (MCAA Phase I)
Operating Rooms
Summer/Fall 2024 (Move 2)
Ophthalmology Current Location: Building 8, Floor 1
Future Location: Building C, Floor 3
Relocating from Building 8, Floor 1 to the temp medical facility (85T) in the G Lot, Floor 1.
Relocating from the temporary medical facility in the G Lot, Floor 1 to Building C, Floor 3. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Optometry Current Location: Building 8, Floor 1
Future Location: Building C, Floor 3
Relocating from Building 8, Floor 1 to the temp medical facility (85T) in the G Lot, Floor 1.
Relocating from the temp medical facility ((85T) in the G Lot, Floor 1 to Building C, Floor 3. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Oral Medication Radiology / Radiology (NPDS) Current Location: Building 2, Floor 2
Future Location: Building C, Floor 2
Relocating from Building 2, Floor 2 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Orofacial Pain Center (NPDS) Current Location: Building 2, Floor 3
Future Location: Building C, Floor 2
Relocating from Building 2, Floor 3 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Outpatient Clinical Nutrition Services Current Location: Building 7, Floor 3
Future Location: Building C, Floor 2
Relocating from Building 7, Floor 3 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Pastoral Care Current Location: Building 8, Floor 1 & 2
Future Location: Building C, Floor 1
Relocating from Building 8, Floor 1 & 2 to the temporary medical facility in the G Lot, Floor 1 & 2.
Relocating from the temporary medical facility in the G Lot, Floor 1 & 2 to Building C, Floor 1. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Patient Transport* Current Location: Building 6, Floor 2
Future Location: Building C, Floor 2 Relocating from Building 6, Floor 2 to cube farm, Building 9, Floor 1.
Relocating from temporary location to Building C, Floor 2. (MCAA Phase I) Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Current Location: Building 2, Floor 1
Future Location: Building C, Floor 1
Relocating from Building 2, Floor 1 to Building C, Floor 1. (MCAA Phase I)
Postal Operations
Summer/Fall 2024 (Move 2)
Preventive Medicine / Public Health Current Location: Building 7, Floor 5
Future Location: Building C, Floor 2
Relocating from Building 7, Floor 5 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Primary Care Dentistry Current Location: Building 2, Floor 2
Future Location: Building C, Floor 2
Relocating from Building 2, Floor 2 to Building C, Floor 2. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Updated by the OIC, DHA-Project Site Office Bethesda All locations, move phases, and timelines are subject to change.
Neonatal Intensive Care Unit (NICU) Current Location: Building 10, Floor 6
Future Location: Building C, Floor 5
Relocating from Building 10, Floor 6 to Building C, Floor 5. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Summer/Fall 2024 (Move 2) Relocating from Bldg 7, Flr 2 to Bldg 3/5 (Location TBD). (MCAA Phase I)
Alphabetical Report
Radiation Safety Current Location: Building 8, Floor 5
Future Location: Building C, Floor 2
Relocating from Building 8, Floor 5 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 2. (MCAA Phase I) Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Refractive Surgery Current Location: Building 8, Floor 1
Future Location: Building C, Floor 3
Relocating from Building 8, Floor 1 to the temp medical facility (85T) in the G Lot, Floor 1.
Relocating from the temp medical facility (85T) in the G Lot, Floor 1 to Building C, Floor 3. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Current Location: Building 4, Floor 3
Future Location: Building C, Floor 0
Relocating from Building 4, Floor 3 to Building 9, Floor 0.
Relocating from temp medical facility (85T) to Building C, Floor 0. (MCAA Phase I)
Reprographic*
Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Safety Current Location: Building 8, Floor 5 & 6
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 5 & 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Security and Emergency Management Current Location: Building 7, Floor 1
Future Location: Building C, Floor 1
Relocating from Building 7, Floor 1 to Building C, Floor 1. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Senior Enlisted Mess* Current Location: Building 4, Floor 1
Future Location: Building C, Floor 1
Relocating from Building 4, Floor 1 to temp medical facility (85T) in the G Lot, Floor 2.
Relocating from temporary location to Building C, Floor 1. (MCAA Phase II)
Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Current Location: Building 7, Floor 6
Future Location: Building 9, Floor 2
Relocating from Building 7, Floor 6 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building 9, Floor 2. (MCAA Phase II)
Social Work
Summer/Fall 2024 (Move 2) Spring/Summer 2027 (Move 3)
Current Location: Building 9, Floor 3
Future Location: Building C, Floor 3
Relocating from Building 9, Floor 3 to Building C, Floor 3. (MCAA Phase I)
Stone Center
Summer/Fall 2024 (Move 2)
Trauma Services (Admin) Current Location: Building 7, Floor 3
Future Location: Building 9, Floor 2 Relocating from Building 7, Floor 3 to Building 9, Floor 2. (MCAA Phase I) Relocating from the temp medical facility (85T) in the G Lot to Building 9, Floor 2. (MCAA Phase II)
Summer/Fall 2024 (Move 2) Spring/Summer 2027 (Move 3)
Visual Information (NMSC) Current Location: Building 4/6, Floor 2 & 3
Future Location: Building C, Floor 0 Relocating from Building 4/6, Floor 2 & 3 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 0. (MCAA Phase I) Oct 2018 (Move 1) Summer/Fall 2024 (Move 2)
Warrior Clinic Current Location: Building 8, Floor 3
Future Location: Building C, Floor 2 Relocating from Building 8, Floor 3 to the temp medical facility (85T) in the G Lot, Floor 1.
Relocating from the temporary medical facility in the G Lot, Floor 1 to Building C, Floor 2. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
Women's Health Current Location: Building 10, Floor 2
Future Location: Building C, Floor 4
Relocating from Building 10, Floor 2 to Building C, Floor 4. (MCAA Phase I)Summer/Fall 2024 (Move 2)
Updated by the OIC, DHA-Project Site Office Bethesda All locations, move phases, and timelines are subject to change.
Psychiatric Continuity Service Current Location: Building 8, Floor 4
Future Location: Building C, Floor 4
Relocating from Building 8, Floor 4 to the temp medical facility (85T) in the G Lot, Floor 2.
Relocating from the temp medical facility (85T) in the G Lot, Floor 2 to Building C, Floor 4. (MCAA Phase II) Oct 2018 (Move 1) Spring/Summer 2027 (Move 3)
NOTE*: (Move 1) has already occurred prior. For information purposes only. (Not required as part of MCAA IOT Contract)