Tyndall AFB Temporary Modular Medical Facility
Solicitation number
W9127S19Q6039
Issued by

About this file

Tyndall TMMF Response to Questions 13Aug19

View the file

Other files

File Type Posted
49_22__TLV2.0_Combined_Clinic_TPF_Low_Voltage_Systems_Notes_&_Details.pdf PDF
55_TQ3.11A_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_A.pdf PDF
49_21__TFP1.0_Combined_Clinic_TPF_Life_Safety_Narrative.pdf PDF
49_25__TPFV5.0_STANDARD_CANOPY_DETAILS_STAMPED.pdf PDF
49_25__TPFV3.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
49_24__TPF2.1-P2_Full_Building_Plan_Phase_2.pdf PDF
1-V1.03_SURVEY_PLAN.pdf PDF
49_21__TFP2.0_Combined_Clinic_TPF_Life_Safety_Plan.pdf PDF
1-V1.01_SURVEY_PLAN.pdf PDF
49_23__TCP1.4_Combined_Clinic_TPF_RCP.pdf PDF
1-V1.04_SURVEY_PLAN.pdf PDF
55_TQ3.11B_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_B.pdf PDF
49_21__TFP3.3_Combined_Clinic_TPF_Fire_Suppression_Notes_and_Details.pdf PDF
49_23__TCP1.0_Combined_Clinic_TPF_RCP.pdf PDF
49_24__TPF3.0_Full_Luminary_Plan.pdf PDF
56_SGT.02_TEMP_SIGNAGE_TPF_PHASE_1.pdf PDF
49_22__TLV1.0_Combined_Clinic_TPF_LV_Systems_Notes_&_Details.pdf PDF
55_TQ3.01_-_FFE_JSN_LEGEND.pdf PDF
49_25__TPFV6.0_CANOPY_FOOTING_DETAILS_STAMPED.pdf PDF
49_24__TPF4.0_Overall_Supply_Plumbing_Schematic.pdf PDF
1-V1.08_SURVEY_PLAN.pdf PDF
55_TQ3.11C_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_C.pdf PDF
49_24__TPF2.0-PI_Full_Building_Plan-Phase_1.pdf PDF
49_25__TPFV2.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
49_23__TCP1.3_Combined_Clinic_TPF_RCP.pdf PDF
55_TQ4.11D_-_FFE_PLAN_-_TPF_PHASE_2,_AREA_D.pdf PDF
1-V1.05_SURVEY_PLAN.pdf PDF
49_23__TCP1.5_Combined_Clinic_TPF_RCP.pdf PDF
55_TQ4.11C_-_FFE_PLAN_-_TPF_PHASE_2,_AREA_C.pdf PDF
49_23__TCP1.2_Combined_Clinic_TPF_RCP.pdf PDF
55_TQ3.11_-_FFE_PLAN_-_TPF_PHASE_1.pdf PDF
49_21__TFP4.3_Combined_Clinic_TPF_Fire_Alarm_Details_and_Notes.pdf PDF
55_TQ4.01_-_FFE_JSN_LEGEND.pdf PDF
49_21__TFP3.2_Combined_Clinic_TPF_Fire_Suppression_Plan_Phase_2.pdf PDF
49_23__TCP1.4-PI_Combined_Clinic_TPF_RCP-PHASE_1.pdf PDF
49_21__TFP4.2_Combined_Clinic_TPF_Fire_Alarm_Plan_Phase_2.pdf PDF
49_24__TPF5.0_Overall_DWV_&_Waste_Schematic.pdf PDF
56_SGT.03_TEMP_SIGNAGE_TPF_PHASE_2.pdf PDF
49_25__TPFV4.0_STANDARD_RAMP_AND_STAIR_DETAILS_STAMPED.pdf PDF
49_21__TFP4.1_Combined_Clinic_TPF_Fire_Alarm_Plan_Phase_1.pdf PDF
49_25__TPFV7.0_RAMP_STEP_AND_PLATFORM_CONNECTION_DETAILS_STAMPED.pdf PDF
55_TQ3.02_-_FFE_JSN_LEGEND.pdf PDF
49_24__TPF1.0_Full_Building_Elevations.pdf PDF
49_24__TPF7.0_Overall_Plumbing_Plan_-_D.W.V.pdf PDF
55_TQ3.11D_-_FFE_PLAN_-_TPF_PHASE_1,_AREA_D.pdf PDF
49_23__TCP1.4-PII_Combined_Clinic_TPF_RCP-PHASE_II.PDF PDF
1-V1.06_SURVEY_PLAN.pdf PDF
49_23__TCP1.1_Combined_Clinic_TPF_RCP.pdf PDF
49_25__TPFV8.0_CANOPY_ASSEMBLY_AND_FOOTING_DETAILS_STAMPED.pdf PDF
49_21__TFP3.1_Combined_Clinic_TPF_Fire_Suppression_Plan_Phase_1.pdf PDF
Show 40 more

Latest 50 of 129 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9127S19Q6039 Response to Questions

Tyndall AFB Temporary Modular Medical Facility (TMMF)

Q1. Is there any more information about what the government is looking for?

A1. No

Q2. What size building are they looking for?

A2. Estimated 23,600 square feet to accommodate sizes in Attachment G – PFD Tyndall TPF v2 20190702

Q3. Is it a lease or purchase?

A3. Purchase

Q4. Does the government want new or used buildings?

A4. New or Used buildings are acceptable.

Q5. Did I read the completion date to be Sept 30, 2019?

A5. No, completion date is on or before 13 Oct 2019 for occupancy date of 14 Oct 2019. Statement of Work has been revised in Amendment 0001.

Q6. Please confirm delivery/install date is on or before 13 Oct 2019 for occupancy date of 14 Oct 2019?

Q6. Yes, that is correct.

Q7. Are used building(s) acceptable?

A7. Yes

Q8. What is the estimated usage of the building?

A8. Estimated 23,600 square feet.

Q9. Is the Statement of Work “open for business” date of 9/30/19 correct?

A9. No, Statement of Work is revised in Amendment 0001 to reflect “Open for Business” date of 14 Oct 2019.