Q A_V.6_RAM_Blast.pdf
PDF 47 KB Posted
- Attached to
- RAM Blast Project Federal contract opportunity
- Solicitation number
- W9127P-13-R-0003
About this file
Questions Answers V.6
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF_30_Amendment_0001.pdf | ||
| QA_V.4_RAM_Blast_answered.pdf | ||
| QA_V.5_RAM_Blast_Answered.pdf | ||
| EXHIBIT_C_DB_April_2013.doc | DOC document | |
| Q A_V.3_RAM_Blast.pdf | ||
| RAM_Blast_Pre-Bid_sign_in.pdf | ||
| Q A_V.2_RAM_Blast.pdf | ||
| RAM_BLAST_BUILDING_SOW.pdf | ||
| RAM_BLAST_DRAWINGS.pdf | ||
| Q A_V.1_RAM_Blast.pdf | ||
| EXHIBIT_B_April_2013.pdf | ||
| EXHIBIT_C_DB_April_2013.pdf | ||
| 1442_Solicitation_RAM_Blast.pdf | ||
| EXHIBIT_A_DB_April_2013.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9127P-13-R-003 – RAM Blast
Q&A V.6
6 SEP 2013
1. Could you please send technical specs of the RAM Blaster?
a. The weight or dimensions are not needed. The building and openings as specified will handle the RAM Blaster installation. Installation will be by a third party.
2. We are needing the weight, dimensions and how much heat it puts out for HVAC calculations.
a. Do not size the HVAC for the RAM Blaster. Size the AC to keep the building stable in a not in use configuration. When the RAM blast is in operation the overhead door will most likely be open.