Q A_V.2_RAM_Blast.pdf

PDF 126 KB Posted

Attached to
RAM Blast Project Federal contract opportunity
Solicitation number
W9127P-13-R-0003
Issued by
Department of the Army Virgin Islands Army National Guard

About this file

Questions Answers V.2

View the file

Other files for this federal contract opportunity

Other files attached to RAM Blast Project, newest first.
File Type Posted
SF_30_Amendment_0001.pdf PDF
QA_V.4_RAM_Blast_answered.pdf PDF
QA_V.5_RAM_Blast_Answered.pdf PDF
Q A_V.6_RAM_Blast.pdf PDF
EXHIBIT_C_DB_April_2013.doc DOC document
Q A_V.3_RAM_Blast.pdf PDF
RAM_Blast_Pre-Bid_sign_in.pdf PDF
RAM_BLAST_BUILDING_SOW.pdf PDF
RAM_BLAST_DRAWINGS.pdf PDF
Q A_V.1_RAM_Blast.pdf PDF
EXHIBIT_B_April_2013.pdf PDF
EXHIBIT_C_DB_April_2013.pdf PDF
1442_Solicitation_RAM_Blast.pdf PDF
EXHIBIT_A_DB_April_2013.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9127P-13-R-003 – RAM Blast

Q&A V.2

21 AUG 2013

1. Can you provide any soil tests so that we can assure foundation design?

a. No soil tests will be provided.

2. Can you provide an existing slab dimension and cross section?

a. Dimensions 115' South to North and 70' East to West, 12" thick. No cross section available. SOW dictates reinforced top slab to be provided; therefore contractor is not responsible for any issues with the existing slab.

3. Can you provide a current land survey for the site?

a. No land survey is necessary for this project.

4. The Detail of site Drawing shows a hip roof on the proposed building.

Does the building require a hip roof or will a gable roof be acceptable?

a. Hip roof is preferred. If a gable roof is designed and constructed to withstand hurricane wind loads it will be accepted.