This is a product manual for the HUNDESTED Marine Gear CPG 120 (serial no. G1177-78), specifically detailing installation procedures and requirements.

The manual outlines critical installation preparation steps including pre-installation damage inspection, verification of engine flange and rotation direction, and confirmation that the gear arrives fully function-tested with adjusted hydraulic systems and new filter inserts. The document emphasizes that no external hydraulic connections are necessary, though external cooling water connections are referenced in drawing no. 4-155-020720. The gearbox inclination must not exceed 8° aft, and the foundation must be rigid to withstand thrust forces, torque reactions, and hull loads. Vertical adjustment is accomplished through foundation bolts, while transversal and longitudinal adjustments utilize screws in provisionally welded threaded pieces. The manual stresses that final alignment cannot be completed until vessel launch due to hull deflection, with thermal expansion of the gearbox requiring consideration during output flange and input shaft alignment. Once properly positioned, the gearbox feet are secured with steel shocks or Chockfast material. Supporting technical drawings are referenced throughout (4-048-021095, 4-048-020722), and alignment calculations per GAP-SAK standards and propeller unit manuals are required for proper installation completion.

View the file

Other files

File Type Posted
Bid Roster_YAQ FY27 Overhaul_8.24.2026.pdf PDF
New Door Hinge Placement 5.11.6.pdf PDF
527 000 00 03 S4K Geislinger Coupling Gear.pdf PDF
SCA WD 2015-5687_Kenai Peninsula AK.pdf PDF
Performance Work Statement_YAQ OH_Amend1_7.24.26.pdf PDF
Solicitation Amendment W9127N26BA0290001 SF 30.pdf PDF
DT50-55 Tech Manual.pdf PDF
USACE Drawing 353-E330-024 Gear Foundation Mods.pdf PDF
Hundested Dwg 1-022-020409 Installation Unit.pdf PDF
MTU Series 60 Service Manual.pdf PDF
Red Hawk FA-000 - Fire Alarm System Dredge YAQUINA General Notes Information.pdf PDF
Maintenance Manual for SCBAs - Drager Servicing.pdf PDF
VD-TM-91721 incl drawings (OM) Manual.pdf PDF
NORSHIPCO Y-2232-18 Revision C Sheets 1 to 2 Arrangement Details of Bow Thruster.pdf PDF
NORSHIPCO Y-2494-3 Revision E Sheets 1 to 2 Hopper Plating.pdf PDF
Hundested 0-002-020932-2 MP700 Propeller Hoved Samling.pdf PDF
NORSHIPCO Y-2232-9 Revision F Sheets 1 to 2 Tank Top Plating.pdf PDF
NORSHIPCO Y-1032-16 Revision K Sheets 1 to 6 General Arrangement.pdf PDF
NORSHIPCO Y-2274-2 Arrangement-Details of Rudder Stock Tiller-Tiebar.pdf PDF
NORSHIPCO Y-1032-16 General Arrangement.pdf PDF
NORSHIPCO Y-2274-1 Rudders.pdf PDF
NORSHIPCO Y-2636-1 Shaft Struts.pdf PDF
Grid Cooler Installation and Maintenance Manual Form 185.pdf PDF
D-1441-2- Layout Smoke Detection System.PDF PDF
NORSHIPCO Y-3878-18 HVAC - Upper DK Deck House.pdf PDF
MDC 353-E507-2012-05 Dredge Pipe Flanges Gaskets.pdf PDF
Lips A0 04654 Revision A Assembly Fixed Pitch Transverse Thruster.pdf PDF
Y-2494-3 Hopper Framing.pdf PDF
IHC 50412077 RR Gate Valve.pdf PDF
DTC 5241127 Sliding Piece.pdf PDF
MDC 353-E645-2012-05 Revision A Pump Cofferdam.pdf PDF
Y-1034-17 Docking Plan.pdf PDF
Y-2496-2 Door Operating Gear.pdf PDF
NORSHIPCO Y-1034-2 Alum Doors.pdf PDF
Y-2496-2 Arrgt and Details Hopper Doors Operating Gear.pdf PDF
MTU 8V4000 Service Manual.pdf PDF
Red Hawk FA-101- Fire Alarm System Dredge YAQUINA FAS Layout.pdf PDF
D-1441-1 Revision G- CO2 Fire Extinguishing Smoke Detection Systems.PDF PDF
Example Report for SCBAs.PDF PDF
NORSHIPCO Y-2272-1 Revision C Sheets 1 to 2 Chain Locker Details.pdf PDF
LIPS-A004654.pdf PDF
Y-1034-1 Top of Hopper.pdf PDF
NORSHIPCO Y-2494-1 Revision C Sheets 1 to 2 Hopper Door Frames.pdf PDF
NORSHIPCO Y-2496-1 Revision C Sheets 1 to 2 Hopper Door- Frames.pdf PDF
DTC 5241115 Trunnion.pdf PDF
MDC 353-E507-2012-01 Revision A Dredge Pipe Arrangement.pdf PDF
MDC 353-A640-01 Revision B Sheets 1 to 3 Engine Cooling System.pdf PDF
FY27 Yaquina Overhaul PWS Final.pdf PDF
Solicitation - W9127N26BA029.pdf PDF
Attachment A_Price Schedule.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HUNDESTED manual � Marine Gear CPG 120 serial no. G1177-78

INSTALLATION

INSTALLATION PREPERATIONS

Before the gear is lowered into the engine room, check that the gear has not been damaged during shipping, etc.

Check that the engine flange and direction of rotation are correct.

CPG 120 is delivered fully function tested from the factory, and with the hydraulic system adjusted to the desired number of revolutions and operating temperature.

CPG 120 is delivered with new filter inserts.

The total weight of the gear is stamped on the rating plate.

No external hydraulic connections are necessary.

For external connection of cooling water � see drawing no. 4-155-020720.

ALIGNMENT:

VERY IMPORTANT! The final check of the alignment can not be done until the ship is launched due to deflection of the hull.

When aligning the propeller shaft please see the GAP-SAK alignment calculations for details.

The inclination of the gear must not exceed max. 8° aft. The foundation must be rigid in order to avoid harmful deformation of the gear, taking into consideration thrust forces, torque reactions from the gear and loads on the ship hull. All major welding must be finished before alignment.

Place the gearbox on the prepared foundation in the hull. Make a rough alignment of the gearbox and then the engine. The gearbox can be adjusted vertically by means of bolts in the foundation feet on the gearbox. The transversal and longitudinal adjustment can be done with screws sitting in threaded pieces being provisionally welded to the foundation in the hull. See drawing no. 4-048-021095.

The final alignment of the gear has to be done when the vessel is launched. For the final alignment see the manual of the propeller unit.

The thermal expansion of the gearbox has to be taken into consideration when lining up the output flange/propeller flange and the engine/gearbox input shaft (see drawing no. 4-048- 020722). When the gear has been put in the correct position, the feet are provided with steel shocks, Chockfast or similar.