This document contains ultrasonic thickness measurements for the port bottom plating in way of the steering gear room on the USACE dredge Yaquina. Readings were taken at various locations on the plating and percentages of wastage are provided, with substantial wastage shown in blue and excessive wastage shown in red. One page provides thickness readings across 112 locations on the plating and percentages of wastage, while another page summarizes the average percentage of loss for the steering gear room port bottom plating.

The related federal contract opportunity is solicitation number W9127N23B0014 for the FY24 Yaquina Overhaul from the Department of the Army Corps of Engineers Engineering District Portland. The solicitation appears to be for overhaul and repair services on the dredge Yaquina, likely related to the ultrasonic testing results shown in the thickness measurement documents. No further details are provided on response dates, award dates, pricing terms, or set-asides in the information given.

View the file

Other files

File Type Posted
C.04_FormalAbstractOfOffers7N23B0014.pdf PDF
C.04_BidRoster7N23B0014.pdf PDF
B.08 W9127N23B0014 Yaquina Overhaul Amendment 0003.pdf PDF
B.08 Price List Amendment 0003.xlsx XLSX spreadsheet
Port Sewage Flat Tank Top fR 94 95.pdf PDF
Furuno 2827 Radars.pdf PDF
VD-TM-91721User Op.Manual.pdf PDF
Y-2232-18 Arrgt Details of Bow Thruster Instl.pdf PDF
Bottom plating within 4th strake from keel.pdf PDF
Furuno GP-170.pdf PDF
Furuno GP-170 AIS.pdf PDF
Ned-deck Marine O M Davit SCH rev E 14-12-2010.pdf PDF
Tank Top in way of Trunnion Room.pdf PDF
DT50-55 Tech Manual 80-677.pdf PDF
Dredge Yaquina - TAB Report March 2023.pdf PDF
B.08 W9127N23B0014 Yaquina Overhaul Amendment 0002.pdf PDF
Furuno FE-700 Echo Sounder.pdf PDF
GX5500S.pdf PDF
LIPS-A004654.pdf PDF
Furuno RD-30 Repeater.pdf PDF
Y-2470-4_Installation_of_New_Hopper_Distribution_System.pdf PDF
Y-2496-3 Hyd Cylinders Ovfl Trough Hopper Doors.pdf PDF
95340 Swell Compensator Cylinder.pdf PDF
Y-2496-2 Arrgt Details Hopper Doors Operating Gear.pdf PDF
P7555 - Dredge Yaquina Launch Final.pdf PDF
19731_Longitudinal Stiffeners.pdf PDF
19731 REV 06 Sent to cust. 4.12.21.pdf PDF
Y-1032-16 Sheets 1 to 6.pdf PDF
Hundested 1-022-021126-2 MP700-CPG120 Installation Unit 6331-G1178.pdf PDF
Red Hawk FA-101 Fire Alarm System FAS Layout.pdf PDF
5241127.pdf PDF
Y-2636-1 Shaft Struts.pdf PDF
Y-2232-44 Seachests.pdf PDF
Y-2274-1 Detail 15-A Rudder Seal Ring.pdf PDF
D-1441-1.PDF PDF
Hundested 0-002-020932-2 MP700 Propeller Hoved Samling.pdf PDF
5241115 Trunnion.pdf PDF
Red Hawk FA-000 Fire Alarm System General Notes.pdf PDF
Y-3874-3 DIAGRAM Bilge and Ballast System.pdf PDF
Y-3872-4 Arrangement Firemain System.pdf PDF
Y-3874-4 Arrangement Bilge and Ballast System.pdf PDF
1788 0878 Stuffing Box female recess.pdf PDF
12V2000_P82_operating instructions.pdf PDF
Y-2636-2 Shafting Arrangement.pdf PDF
X-1441-2 Rev G.pdf PDF
Y-3872-3 DIAGRAM Firemain System.pdf PDF
Y-3872-5 DIAGRAM Sea Water Circ System.pdf PDF
Hundested 2-140-021135-1 MP700-CPG120 Flange Coupling Assembly.pdf PDF
Y-2274-1 Rudders.pdf PDF
Y-3872-6 Sea Water Argmt.pdf PDF
Show 40 more

Latest 50 of 119 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USACE Dredge "YAQUINA" Ultrasonic Thickness Measurements of Port Bottom Plating in way of Steering Gear Room

Drawing 30

Forward

CL

.387

.413

.407

.432

.372

.400

.268 .255

.271

.349

.396

.510

.283

.357

.321

.368

.508

.438

Note: Substantial wastage [18.75%] readings are shown in (blue) and excessive wastage [25%] readings are shown in (red).

See following spreadsheet for a complete list of readings and wastage.

.342 .339

Note: Blue percentages show Substantial wastage. Red percentages show excessive wastage.

info@certifiedndt.com

(253-952-2337

Report: 53303 Date: 3/3/2023

1 2 3 4 5 6 7 8 9 10 .437 .357 .368 .407 .396 .413 .372 .400 .438 .432 .342

%Wastage 18.31% 15.79% 6.86% 9.38% 5.49% 14.87% 8.47% 0.00% 1.14% 21.74% .437 .339 .321 .268 .271 .255 .283 .387 .349 .355

%Wastage 22.43% 26.54% 38.67% 37.99% 41.65% 35.24% 11.44% 20.14% 18.66% .500 .508 .510 .509

%Wastage 0.00% 0.00% 0.00% .375

Steering Gear Room

[cont.] Port Bottom Plating 25% .328

Steering Gear Room 2 Port Bottom Plating 25%

.328

Avg./ % Loss

Steering Gear Room 1 Port Bottom Plating 25%

USACE Dredge "YAQUINA"

Ultrasonic Thickness Measurements of: Port Bottom Plating in way of Steering Gear Room [Drawing 30]

Structure Location Number Side Structural

Member Max. Allow.

Wastage Max.

Dim.

Nominal Thickness

Readings