View the file

Other files

File Type Posted
W9127821R0056 RFP Attachment 5.2 Seed Project Bid Schedule Amd 07.xlsx XLSX spreadsheet
W9127821R0056 RFP Amendment 07.pdf PDF
W9127821R0056 RFP Attachment 5.2 Seed Project Bid Schedule Amd 06.xlsx XLSX spreadsheet
W9127821R0056 RFP Amendment 06.pdf PDF
W9127821R0056 DD3150 C19 Vaccination Attestation Contractor and Visitor.pdf PDF
W9127821R0056 RFP Amendment 04.pdf PDF
W9127821R0056 WFG Drawings Amended 12-2-21.pdf PDF
W9127821R0056 GDACS and Controls Installation MATOC Specification 12-2-21.pdf PDF
W9127821R0056 RFP Amendment 03.pdf PDF
W9127821R0056 RFP Attachment 5.2 Seed Project Bid Schedule Amd 02.xlsx XLSX spreadsheet
W9127821R0056 RFP Amendment 02.pdf PDF
W9127821R0056 RFP Attachment 5.1 MATOC Labor Rate Schedule Amd 02.xlsx XLSX spreadsheet
W9127821R0056 RFP Amendment 01.pdf PDF
W9127821R0056 RFP Attachment 5.1 MATOC Labor Rate Schedule Amd 01.xlsx XLSX spreadsheet
W9127821R0056 RFP Attachment 5.2 Seed Project Bid Schedule Amd 01.xlsx XLSX spreadsheet
W9127821R0056 RFP for Control System Installation.pdf PDF
W9127821R0056 RFP Attachment 5.2 Seed Project Bid Schedule.xlsx XLSX spreadsheet
W9127821R0056 RFP Attachment 1 Company Data Sheet.docx DOCX document
W9127821R0056 RFP Reference_Drawings.pdf PDF
W9127821R0056 RFP Attachment 3 Past Performance Data Sheet.docx DOCX document
W9127821R0056 RFP Attachment 4 Past Performance Questionnaire_fillable.pdf PDF
W9127821R0056 RFP WFG Generator Install Drawings Final.pdf PDF
W9127821R0056 RFP Attachment 5.1 MATOC Labor Rate Schedule.xlsx XLSX spreadsheet
W9127821R0056 RFP Attachment 6 SubContactingPlanTemplate.docx DOCX document
W9127821R0056 RFP Attachment 2 Notice of Exceptions.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X

X 9B. DATED (SEE ITEM 11)

07-Sep-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

W9127821R0056

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X is not extended.The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of amendment 05 is to extend the proposal due date, extend the RFI date, post photos of the Walter F. George Powerhouse, update the outage schedule in specification section 01 11 00, and remove clause 252.223-7999 (Dev) .

See next page.

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY CODE

ENDIST MOBILE CONTRACTING DIVISION

109 ST JOSEPH ST

MOBILE AL 36602

W91278 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

3. EFFECTIVE DATE

30-Dec-2021

X

W9127821R0056

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

RESPONSE DATE CHANGE:

The required proposal response date/time has changed from January 10, 2022 10:00 AM Central Standard Time to January 24, 2022 10:00 AM Central Standard Time.

REQUEST FOR INFORMATION (RFI):

The Bidder Inquiry portal is open for question entry. Instructions are detailed in the original solicitation document. The portal will be closed for question entry on January 10, 2022 at 2:30pm central standard time.

REFERENCE PHOTOS: See the attached photos of the Walter F. George Powerhouse. The photos were requested as an RFI.

SPECIFICATION UPDATE: Section 01 11 00 is updated to revise outage dates in paragraph 1.3.1.

CLAUSES UPDATE: Remove clause 252.223-7999 (Dev) Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009) OCT 2021

(End of Summary of Changes)

WFG Task Order Site Visit Pictures Pictures and notes are for reference only and do not change the SOW posted to the solicitation

Generator Floor

Turbine Floor

Basement Floor

SAD GDACS & Controls Upgrades - Installation MATOC 19MU10M1WFG equipment manufacturer and/or designer of the turbine controller or a government approval alternative to make necessary programming changes to the turbine controller PLC.

1.2.1.10 Exciter

The contractor shall solicit the original equipment manufacturer and/or designer of the exciter or a government approval alternative to make necessary programming changes to the exciter PLC.

1.2.1.11 Provide and install new network cabling

Provide and install new network cabling to include but not limited to fiber optic and CAT-6 Ethernet cable. Cable installations shall include terminations and testing. See contract drawings for installation details.

1.2.1.12 Removal & Installation Drawings

The contractor will be responsible for the development of removal and installation drawings for units 2, 3, & 4 based off the provided unit 1 contract drawings. The drawings shall be approved prior to the start of work on a given unit.

1.2.2 Location

The work is located at the Walter F. George Powerhouse and Switchyard.

Walter F. George Powerhouse

Powerhouse Access Road Shorterville, AL 36373.

1.3 WORK SCHEDULE

All work shall be performed during the normal duty hours of the power plant maintenance staff. Normal duty hours for work are from 0600 to 1445

CST, Monday through Thursday.

1.3.1 Government Outage Schedule

Generator outages have already been approved and scheduled as listed below. These outages cannot be changed. The last 3 weeks of each outage are reserved for government commissioning. Contractor installation work shall be complete prior to government commissioning.

Outage Start Date Return to service date

Unit 4 01 August 2022 30 October 2022

Unit 1 01 November 2022 30 January 2023

Unit 2 01 March 2023 03 June 2023

Unit 3 02 October 2023 30 December 2023

1.3.2 Work Rescheduling

Allow for a maximum of two (2) calendar days per scheduled outage in the construction schedule where construction activity is prohibited due to powerhouse operations. Government will provide 24 hour notification each time the restrictions are invoked.

Requests for work outside of normal duty hours requires written approval

SECTION 01 11 00 Page 3