Summary of TOs by Cost Element
| Attachment 20 Task Order Template | |||
| Summary of Awardable Task Orders by Cost Element | |||
| Prime Contractor: ________________ | |||
| Task Order 0001 | Task Order 0002 | TOTAL | |
| COST ELEMENT | |||
| Direct Labor (DL) Hours | - 0 | - 0 | - 0 |
| Direct Labor Dollars | $ - 0 | $ - 0 | $ - 0 |
| Fringe Benefits | $ - 0 | $ - 0 | $ - 0 |
| Overhead | $ - 0 | $ - 0 | $ - 0 |
| Total Fully Burdened Direct Labor | $ - 0 | $ - 0 | $ - 0 |
| Total Travel | $ - 0 | $ - 0 | $ - 0 |
| Total ODCs | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 |
| G&A | $ - 0 | $ - 0 | $ - 0 |
| Total Estimated Cost | $ - 0 | $ - 0 | $ - 0 |
| Fixed Fee (burden labor only) | $ - 0 | $ - 0 | $ - 0 |
| Total Estimated Price | $ - 0 | $ - 0 | $ - 0 |
&RW91260-09-R-0002
Attachment 20 &R&F &A
Task Order 0001
| Task Order: 0001 | ||||
| Prime Contractor:___________________ | ||||
| Cost Elements | Rate | Hours | Total | |
| Direct Labor (DL) On-Site (Gov't Site) | ||||
| Labor Category | Employee Name | |||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| Subtotal Direct Labor On-Site | $ - 0 | |||
| Fringe Benefits | ||||
| On-Site Overhead | ||||
| Direct Labor (DL) Off-Site (Ktr Site) | ||||
| Labor Category | Employee Name | |||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| Subtotal Direct Labor Off-Site | $ - 0 | |||
| Fringe Benefits | ||||
| Off-Site Overhead | ||||
| Total Direct Labor (on-site and off-site) | $ - 0 | |||
| Total Fringe Benefits | $ - 0 | |||
| Total Overhead (on-site and off-site) | $ - 0 | |||
| Total Fully Burdened Direct Labor | - 0 | $ - 0 | ||
| Travel | ||||
| List destinations in column A; total amount of trip in column D; provide details of the trip in a different tab within the workbook | ||||
| Total Travel | $ - 0 | |||
| Other Direct Costs (ODCs) | ||||
| list ODC detail | ||||
| Total ODCs | $ - 0 | |||
| Total Subcontracts (see sub calculation below) | $ - 0 | |||
| Subtotal before G&A | $ - 0 | |||
| G&A | $ - 0 | |||
| Total Estimated Cost | $ - 0 | |||
| Fixed Fee (Burden Labor only) | ||||
| Total Estimated Price | $ - 0 | |||
| *Subcontractor:___________________ | ||||
| Cost Elements | Rate | Hours | Total | |
| Direct Labor | ||||
| list job titles & names; rate is fully burdened; (specify gov't site vs. ktr site) | ||||
| Total Direct Labor | $ - 0 | |||
| Travel | ||||
| list destination of trip & amount w/ applied G&A | ||||
| Total Travel | $ - 0 | |||
| ODC | ||||
| list ODC detail w/ applied G&A | ||||
| Total ODC | $ - 0 | |||
| Fixed Fee (Burden Labor Only) | ||||
| Total Cost Plus Fixed Fee | $ - 0 | |||
| *Complete for all subcontractors. |
&RW91260-09-R-0002
Attachment 20 &R&F &A
Task Order 0002
| Task Order: 0002 | ||||
| Prime Contractor:___________________ | ||||
| Cost Elements | Rate | Hours | Total | |
| Direct Labor (DL) On-Site (Gov't Site) | ||||
| Labor Category | Employee Name | |||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| Subtotal Direct Labor On-Site | $ - 0 | |||
| Fringe Benefits | ||||
| On-Site Overhead | ||||
| Direct Labor (DL) Off-Site (Ktr Site) | ||||
| Labor Category | Employee Name | |||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| $ - 0 | ||||
| Subtotal Direct Labor Off-Site | $ - 0 | |||
| Fringe Benefits | ||||
| Off-Site Overhead | ||||
| Total Direct Labor (on-site and off-site) | $ - 0 | |||
| Total Fringe Benefits | $ - 0 | |||
| Total Overhead (on-site and off-site) | $ - 0 | |||
| Total Fully Burdened Direct Labor | - 0 | $ - 0 | ||
| Travel | ||||
| List destinations in column A; total amount of trip in column D; provide details of the trip in a different tab within the workbook | ||||
| Total Travel | $ - 0 | |||
| Other Direct Costs (ODCs) | ||||
| list ODC detail | ||||
| Total ODCs | $ - 0 | |||
| Total Subcontracts (see sub calculation below) | $ - 0 | |||
| Subtotal before G&A | $ - 0 | |||
| G&A | $ - 0 | |||
| Total Estimated Cost | $ - 0 | |||
| Fixed Fee (Burden Labor only) | ||||
| Total Estimated Price | $ - 0 | |||
| *Subcontractor:___________________ | ||||
| Cost Elements | Rate | Hours | Total | |
| Direct Labor | ||||
| list labor categories & names; rate is fully burdened; (specify gov't site vs. ktr site) | ||||
| Total Direct Labor | $ - 0 | |||
| Travel | ||||
| list destination of trip & amount w/ applied G&A | ||||
| Total Travel | $ - 0 | |||
| ODC | ||||
| list ODC detail w/ applied G&A | ||||
| Total ODC | $ - 0 | |||
| Fixed Fee (Burden Labor Only) | ||||
| Total Cost Plus Fixed Fee | $ - 0 | |||
| *Complete for all subcontractors. |
&RW91260-09-R-0002
Attachment 20 &R&F &A
Small Business Requirement
| Small Business Concern | ||||
| The matrix below will be used for the purpose of compliance with FAR 52.219-14, Limitations of Subcontract. At least 50 percent of the cost of contract performance incurred for personnel (of prime contractors and subcontractors) shall be expended for employees of the concern. The concern is defined as the small business prime contractor plus subcontractors that are considered small business teaming partners*. | ||||
| The following costs shall apply: | ||||
| (1) Direct Labor Dollars | ||||
| (2) Direct Labor Overhead Dollars | ||||
| (3) General and Administrative Dollars on Direct Labor and Direct Labor Overhead. | ||||
| The OFFEROR shall complete the matrix below depicting the total allocation of personnel costs/hours between the prime contractor and each subcontractor. Please add Subcontract columns as needed. | ||||
| Task Order ________ | Prime | Subcontractor 1 | Subcontractor 2 | Total |
| Labor Hours | ||||
| Labor Dollars | ||||
| Labor Fringe Benefits | ||||
| Labor OH Dollars | ||||
| G&A | ||||
| Total Estimated Labor** | ||||
| *To be recognized towards the small business requirement, a formal teaming agreement with the small business subcontractors must be in place. | ||||
| **Total Estimated Labor should not include fixed fee from the prime contractor or subcontractor. |
&RW91260-09-R-0002