j10 Progress Chart.xls

XLS spreadsheet 159 KB Posted

Attached to
Competitive 8(a) SATOC JOC Federal contract opportunity
Solicitation number
W9124P-19-R-A029
Issued by
Department of the Army Materiel Command Contracting Command Redstone Arsenal

About this file

This document contains a federal construction contract progress chart and related federal contract opportunity notice. The progress chart tracks the estimated and actual costs and completion percentages for 13 construction tasks on an unspecified military construction project. Tasks include demolition, architecture, mechanical work, communications flooring, plumbing, flooring, ceramic tile, sprinkler system, secondary power, civil work, primary power, communications, and doors. The total estimated cost is $311,930.

The related federal contract opportunity is a five-year Indefinite Delivery Indefinite Quantity single award task order contract seeking a Small Business Administration 8(a) contractor to perform unspecified minor military construction projects, lab revitalization, and other sustainment, restoration, and modernization projects for the US Army Garrison - Redstone Department of Public Works. Questions regarding the anticipated December 16, 2019 award date must be submitted by February 22, 2019 to the named Department of Army contracting staff contacts.

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to Competitive 8(a) SATOC JOC, newest first.
File Type Posted
Amendment_0001_.pdf PDF
C2_CORRECTED.PDF PDF
Questions_Govt_Response_21May2019_(004).pdf PDF
ACT_Section_Unit_Price_Book.pdf PDF
j3 Environmental Laws.doc DOC document
j19 Past Perfomance Record.doc DOC document
j26 Trial Proposal Drawing Set.pdf PDF
j28 Trial Proposal Site Visit Memo Attachment.pdf PDF
j8 Quality Control Report.xls XLS spreadsheet
j23 Company Specialized Experience.docx DOCX document
j2 RSA 200-6 Hazmat Management Plan.pdf PDF
j13 cc order form.xlsx XLSX spreadsheet
j16 ADEM Form 23 BMP Inspection Report.pdf PDF
j12 JOC Evaluation Form.xls XLS spreadsheet
j17 Storm Water Runoff Permit Terminaiton Request.pdf PDF
j27 Seed Project.pdf PDF
j23 Company Specialized Experience.docx DOCX document
j6 Manifest of Material Delivered to the City Landfill.doc DOC document
j10 Progress Chart.xls XLS spreadsheet
j21 Key Personnel Resume.docx DOCX document
j12 JOC Evaluation Form.xls XLS spreadsheet
j24 Background Checks for Installation Access.xlsx XLSX spreadsheet
j25 CDRLs.docx DOCX document
j22 Letter of Commitment.docx DOCX document
Construction_Task_Catalog_-_April_2019.pdf PDF
j14 septic.pdf PDF
j6 Manifest of Material Delivered to the City Landfill.doc DOC document
J1 DD Form 1348-1 Turn-in Slip.xls XLS spreadsheet
Technical_Specifications_-_April_2019.pdf PDF
j3 Environmental Laws.doc DOC document
j7 Manifest of Material Delivered to the City Incenerator.doc DOC document
j2 RSA 200-6 Hazmat Management Plan.pdf PDF
j9 Site Visit Memo.doc DOC document
j27 Seed Project.pdf PDF
j20 Past Performance Survey.docx DOCX document
j13__Small_Projects_order_form.xlsx XLSX spreadsheet
j22 Letter of Commitment.docx DOCX document
j18 Spill Plan.pdf PDF
W9124P-19-R-A029_JOC_KO_Signed.pdf PDF
j5 Manifest of Material Delivered to SWMA.xls XLS spreadsheet
j21 Key Personnel Resume.docx DOCX document
j11 Equipment Warranty List.doc DOC document
j26 Trial Proposal Drawing Set.pdf PDF
J1 DD Form 1348-1 Turn-in Slip.xls XLS spreadsheet
j4 Equipment Data Sheet.xls XLS spreadsheet
j17 Storm Water Runoff Permit Terminaiton Request.pdf PDF
j19 Past Perfomance Record.doc DOC document
BLDG_3434_Photo_Studio_Equipmnt_Listing.xlsx XLSX spreadsheet
W9124P-19-R-A029_QUESTIONS_AND_RESPONSES.pdf PDF
DRAFT_RFP_W9124P-19-R-A029.pdf PDF
Show all 50

Competitive 8(a) SATOC JOC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Construction Progress Chart
Project Description:
Contractor: ________________________Date:
Contract No: _______________________Task Order No: _________________Building No:
ItemContract FeatureWt.Estimated CostActual CostJanuaryFebruaryMarchAprilMayJune
100
Scheduled
01Demo0.0653992883$20,400.00
Actual
100
Scheduled
02Arch.0.2949379669$92,000.00
Actual0.0816208765
60100
Scheduled0.3379078639
03Mech.0.20$62,740.00
Actual0.4543214824
Scheduled1000.6196646684
04Comm. Floor0.0699996794$21,835.00
Actual0.9397467381
50100
Scheduled1
05Plumbing0.0224409323$7,000.00
Actual
100
Scheduled
06Flooring0.0352643221$11,000.00
Actual
100
Scheduled
07Ceramic Tile0.0093610746$2,920.00
Actual
100
Scheduled
08Sprinkler System0.0160933543$5,020.00
Actual
80100
Scheduled
09Secondary Power0.1272240567$39,685.00
Actual
60100
Scheduled
10Civil0.0259673645$8,100.00
Actual
10100
Scheduled
11Primary Power0.0392075145$12,230.00
Actual
50100
Scheduled
12Communications0.0705286442$22,000.00
Actual
Scheduled100
13Doors0.0224409323$7,000.00
Actual
8.1633.7945.4361.9793.97100
Scheduled
TOTAL1.00$311,930.00
Actual

&CATTACHMENT J10

AGM:

Sheet2

&A Page &P

Sheet3

Sheet4