j10 Progress Chart.xls
XLS spreadsheet 159 KB Posted
- Attached to
- Competitive 8(a) SATOC JOC Federal contract opportunity
- Solicitation number
- W9124P-19-R-A029
About this file
This document contains a federal construction contract progress chart and related federal contract opportunity notice. The progress chart tracks the estimated and actual costs and completion percentages for 13 construction tasks on an unspecified military construction project. Tasks include demolition, architecture, mechanical work, communications flooring, plumbing, flooring, ceramic tile, sprinkler system, secondary power, civil work, primary power, communications, and doors. The total estimated cost is $311,930.
The related federal contract opportunity is a five-year Indefinite Delivery Indefinite Quantity single award task order contract seeking a Small Business Administration 8(a) contractor to perform unspecified minor military construction projects, lab revitalization, and other sustainment, restoration, and modernization projects for the US Army Garrison - Redstone Department of Public Works. Questions regarding the anticipated December 16, 2019 award date must be submitted by February 22, 2019 to the named Department of Army contracting staff contacts.
Not Listed
View the file
Other files for this federal contract opportunity
Show all 50
Competitive 8(a) SATOC JOC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Construction Progress Chart | ||||||||||||||||||||||
| Project Description: | ||||||||||||||||||||||
| Contractor: ________________________ | Date: | |||||||||||||||||||||
| Contract No: _______________________ | Task Order No: _________________ | Building No: | ||||||||||||||||||||
| Item | Contract Feature | Wt. | Estimated Cost | Actual Cost | January | February | March | April | May | June | ||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 01 | Demo | 0.0653992883 | $20,400.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 02 | Arch. | 0.2949379669 | $92,000.00 | |||||||||||||||||||
| Actual | 0.0816208765 | |||||||||||||||||||||
| 60 | 100 | |||||||||||||||||||||
| Scheduled | 0.3379078639 | |||||||||||||||||||||
| 03 | Mech. | 0.20 | $62,740.00 | |||||||||||||||||||
| Actual | 0.4543214824 | |||||||||||||||||||||
| Scheduled | 100 | 0.6196646684 | ||||||||||||||||||||
| 04 | Comm. Floor | 0.0699996794 | $21,835.00 | |||||||||||||||||||
| Actual | 0.9397467381 | |||||||||||||||||||||
| 50 | 100 | |||||||||||||||||||||
| Scheduled | 1 | |||||||||||||||||||||
| 05 | Plumbing | 0.0224409323 | $7,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 06 | Flooring | 0.0352643221 | $11,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 07 | Ceramic Tile | 0.0093610746 | $2,920.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 08 | Sprinkler System | 0.0160933543 | $5,020.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 80 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 09 | Secondary Power | 0.1272240567 | $39,685.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 60 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 10 | Civil | 0.0259673645 | $8,100.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 10 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 11 | Primary Power | 0.0392075145 | $12,230.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 50 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 12 | Communications | 0.0705286442 | $22,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| Scheduled | 100 | |||||||||||||||||||||
| 13 | Doors | 0.0224409323 | $7,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 8.16 | 33.79 | 45.43 | 61.97 | 93.97 | 100 | |||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| TOTAL | 1.00 | $311,930.00 | ||||||||||||||||||||
| Actual |
&CATTACHMENT J10
AGM:
Sheet2
&A Page &P
Sheet3
Sheet4
Sheet5
Sheet6
Sheet7
Sheet8
Sheet9
Sheet10
Sheet11
Sheet12
Sheet13
Sheet14
Sheet15
Sheet16