j10 Progress Chart.xls
XLS spreadsheet 159 KB Posted
- Attached to
- Competitive 8(a) SATOC JOC Federal contract opportunity
- Solicitation number
- W9124P-19-R-A029
About this file
This document contains a construction progress chart and information on a related federal contract opportunity. The construction progress chart outlines a renovation project with 13 tasks and estimated costs, weights, and progress percentages for January through June. The federal contract opportunity is a five-year Indefinite Delivery Indefinite Quantity single award task order contract seeking unspecified minor military construction, lab revitalization, and sustainment projects for the US Army Garrison - Redstone Department of Public Works. Interested parties were instructed to submit any questions by February 22, 2019 to the named contracting contacts in order to meet the anticipated award date of December 16, 2019. The solicitation number provided is W9124P-19-R-A029 and the opportunity type is a solicitation. The contracting agency is the Department of the Army Materiel Command Contracting Command located at Redstone Arsenal.
j10 Progress Chart
View the file
Other files for this federal contract opportunity
Show all 50
Competitive 8(a) SATOC JOC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Construction Progress Chart | ||||||||||||||||||||||
| Project Description: | ||||||||||||||||||||||
| Contractor: ________________________ | Date: | |||||||||||||||||||||
| Contract No: _______________________ | Task Order No: _________________ | Building No: | ||||||||||||||||||||
| Item | Contract Feature | Wt. | Estimated Cost | Actual Cost | January | February | March | April | May | June | ||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 01 | Demo | 0.0653992883 | $20,400.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 02 | Arch. | 0.2949379669 | $92,000.00 | |||||||||||||||||||
| Actual | 0.0816208765 | |||||||||||||||||||||
| 60 | 100 | |||||||||||||||||||||
| Scheduled | 0.3379078639 | |||||||||||||||||||||
| 03 | Mech. | 0.20 | $62,740.00 | |||||||||||||||||||
| Actual | 0.4543214824 | |||||||||||||||||||||
| Scheduled | 100 | 0.6196646684 | ||||||||||||||||||||
| 04 | Comm. Floor | 0.0699996794 | $21,835.00 | |||||||||||||||||||
| Actual | 0.9397467381 | |||||||||||||||||||||
| 50 | 100 | |||||||||||||||||||||
| Scheduled | 1 | |||||||||||||||||||||
| 05 | Plumbing | 0.0224409323 | $7,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 06 | Flooring | 0.0352643221 | $11,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 07 | Ceramic Tile | 0.0093610746 | $2,920.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 100 | ||||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 08 | Sprinkler System | 0.0160933543 | $5,020.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 80 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 09 | Secondary Power | 0.1272240567 | $39,685.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 60 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 10 | Civil | 0.0259673645 | $8,100.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 10 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 11 | Primary Power | 0.0392075145 | $12,230.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 50 | 100 | |||||||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| 12 | Communications | 0.0705286442 | $22,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| Scheduled | 100 | |||||||||||||||||||||
| 13 | Doors | 0.0224409323 | $7,000.00 | |||||||||||||||||||
| Actual | ||||||||||||||||||||||
| 8.16 | 33.79 | 45.43 | 61.97 | 93.97 | 100 | |||||||||||||||||
| Scheduled | ||||||||||||||||||||||
| TOTAL | 1.00 | $311,930.00 | ||||||||||||||||||||
| Actual |
&CATTACHMENT J10
AGM:
Sheet2
&A Page &P
Sheet3
Sheet4
Sheet5
Sheet6
Sheet7
Sheet8
Sheet9
Sheet10
Sheet11
Sheet12
Sheet13
Sheet14
Sheet15
Sheet16