I.A.07_Attachment__11_Estimated_Yearly_Workload_Building_Demolition_Contract_12JUN2017.xls
XLS spreadsheet 42 KB Posted
- Attached to
- Demolition Services Federal contract opportunity
- Solicitation number
- W91248-17-Q-A001
About this file
Attachment #11 Estimated Yearly Workload_Building Demolition Contract
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Year
| ESTIMATED WORKLOAD - BASE YEAR | |||
| FE16097 6J | |||
| Building Demolition IDIQ contract | |||
| Item Number | DESCRIPTION | Quantity | UNIT |
| 0001 | Para 5.1.2.4.12 Demolish Concrete and Masonry Structures Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. | 4,000,000 | CF |
| 0002 | Para 5.1.2.4.13 Demolish Wood buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 201,788 | CF |
| 0003 | Para 5.1.2.4.14 Demolish metal buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 86,334 | CF |
| 0004 | Para 5.1.2.4.15 Demolish and remove Relocatable buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 100,000 | SF |
| 0005 | Para 5.1.2.4.16. Demolish building footings, foundations, concrete walls, basement walls, plain concete and slabs and haul concrete debris to the C&D landfill | 175,000 | CF |
| 0006 | Para 5.1.2.4.17.c) Cap and/or loop chiller lines | 100 | LF |
| 0007 | Para 5.1.2.4.18 Saw Cut Concrete 1' deep | 357 | LF |
| 0008 | Para 5.1.2.4.19 Saw Cut Asphalt 8" deep | 737 | LF |
| 0009 | Para 5.1.2.4.20 Demolish and Remove Brick Chimneys | 259 | CY |
| 0010 | Para 5.1.2.4.21 Demolish and remove concrete sidewalks, floors, and slabs on grade (installation-wide). | 10,555 | CF |
| 0011 | Para 5.1.2.4.22 Removal of Asphalt and Curbs. Demolish, remove pavement & curb, remove bituminous driveways, and haul to C&D landfill | 58 | CY |
| 0012 | Para 5.1.2.4.23 Disconnect and cap water and sewer lines | 10 | EA |
| 0013 | Para 5.1.2.4.24 DEMO and remove attached sheds, awnings, supporting facilities/buildings. | 100 | CF |
| 0014 | Para 5.1.2.4.25 Demolish, and remove concrete utility boxes, culverts, headwalls. Utility removal, catch basin or manhole frames and covers, masonry, excludes hauling. | 10 | EA |
| Site Stabilization | |||
| 0015 | Para 5.1.2.5 Borrow Dirt to Backfill demolished area; Compaction of fill, 8" lifts; and, Grading of site | 11,751 | C.Y |
| 0016 | Para 5.1.2.6 SEED, hydroseed and/or mechanical drill seed. Includes lime, fertilizer, seed. | 33,081 | SY |
| 0017 | Para 5.1.2.7 Provide/compact/grade 6" gravel | 1,511 | T |
Option YR 1
| ESTIMATED WORKLOAD Option Year 1 | |||
| FE16097 6J | |||
| Building Demolition IDIQ contract | |||
| Item Number | DESCRIPTION | Quantity | UNIT |
| 1001 | Para 5.1.2.4.12 Demolish Concrete and Masonry Structures Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. | 1,200,000 | CF |
| 1002 | Para 5.1.2.4.13 Demolish Wood buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 600,000 | CF |
| 1003 | Para 5.1.2.4.14 Demolish metal buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 120,000 | CF |
| 1004 | Para 5.1.2.4.15 Demolish and remove Relocatable buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 101,000 | SF |
| 1005 | Para 5.1.2.4.16. Demolish building footings, foundations, concrete walls, basement walls, plain concete and slabs and haul concrete debris to the C&D landfill | 15,000 | CF |
| 1006 | Para 5.1.2.4.17.c) Cap and/or loop chiller lines | 100 | LF |
| 1007 | Para 5.1.2.4.18 Saw Cut Concrete 1' deep | 500 | LF |
| 1008 | Para 5.1.2.4.19 Saw Cut Asphalt 8" deep | 300 | LF |
| 1009 | Para 5.1.2.4.20 Demolish and Remove Brick Chimneys | 200 | CY |
| 1010 | Para 5.1.2.4.21 Demolish and remove concrete sidewalks, floors, and slabs on grade (installation-wide). | 50,000 | CF |
| 1011 | Para 5.1.2.4.22 Removal of Asphalt and Curbs. Demolish, remove pavement & curb, remove bituminous driveways, and haul to C&D landfill | 1,000 | CY |
| 1012 | Para 5.1.2.4.23 Disconnect and cap water and sewer lines | 50 | EA |
| 1013 | Para 5.1.2.4.24 DEMO and remove attached sheds, awnings, supporting facilities/buildings. | 6000 | CF |
| 1014 | Para 5.1.2.4.25 Demolish, and remove concrete utility boxes, culverts, headwalls. Utility removal, catch basin or manhole frames and covers, masonry, excludes hauling. | 9 | EA |
| Site Stabilization | |||
| 1015 | Para 5.1.2.5 Borrow Dirt to Backfill demolished area; Compaction of fill, 8" lifts; and, Grading of site | 4,500 | C.Y |
| 1016 | Para 5.1.2.6 SEED, hydroseed and/or mechanical drill seed. Includes lime, fertilizer, seed. | 25,000 | SY |
| 1017 | Para 5.1.2.7 Provide/compact/grade 6" gravel | 1,100 | T |
Option YR 2
| ESTIMATED WORKLOAD Option Year 2 | |||
| FE16097 6J | |||
| Building Demolition IDIQ contract | |||
| Item Number | DESCRIPTION | Quantity | UNIT |
| 2001 | Para 5.1.2.4.12 Demolish Concrete and Masonry Structures Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. | 815,728 | CF |
| 2002 | Para 5.1.2.4.13 Demolish Wood buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 500,000 | CF |
| 2003 | Para 5.1.2.4.14 Demolish metal buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 60,000 | CF |
| 2004 | Para 5.1.2.4.15 Demolish and remove Relocatable buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 65,000 | SF |
| 2005 | Para 5.1.2.4.16. Demolish building footings, foundations, concrete walls, basement walls, plain concete and slabs and haul concrete debris to the C&D landfill | 10,000 | CF |
| 2006 | Para 5.1.2.4.17.c) Cap and/or loop chiller lines | 100 | LF |
| 2007 | Para 5.1.2.4.18 Saw Cut Concrete 1' deep | 500 | LF |
| 2008 | Para 5.1.2.4.19 Saw Cut Asphalt 8" deep | 300 | LF |
| 2009 | Para 5.1.2.4.20 Demolish and Remove Brick Chimneys | 50 | CY |
| 2010 | Para 5.1.2.4.21 Demolish and remove concrete sidewalks, floors, and slabs on grade (installation-wide). | 20,000 | CF |
| 2011 | Para 5.1.2.4.22 Removal of Asphalt and Curbs. Demolish, remove pavement & curb, remove bituminous driveways, and haul to C&D landfill | 1,000 | CY |
| 2012 | Para 5.1.2.4.23 Disconnect and cap water and sewer lines | 50 | EA |
| 2013 | Para 5.1.2.4.24 DEMO and remove attached sheds, awnings, supporting facilities/buildings. | 6000 | CF |
| 2014 | Para 5.1.2.4.25 Demolish, and remove concrete utility boxes, culverts, headwalls. Utility removal, catch basin or manhole frames and covers, masonry, excludes hauling. | 9 | EA |
| Site Stabilization | |||
| 2015 | Para 5.1.2.5 Borrow Dirt to Backfill demolished area; Compaction of fill, 8" lifts; and, Grading of site | 2,300 | C.Y |
| 2016 | Para 5.1.2.6 SEED, hydroseed and/or mechanical drill seed. Includes lime, fertilizer, seed. | 15,000 | SY |
| 2017 | Para 5.1.2.7 Provide/compact/grade 6" gravel | 800 | T |
| TOTAL for Option Year 2 = | |||
| FORWARD TO SUMMARY SHEET |
Option YR 3
| ESTIMATED WORKLOAD Option Year 3 | ||||
| FE16097 6J | ||||
| Building Demolition IDIQ contract | as of 02 SEP 2016 | |||
| Item Number | DESCRIPTION | Quantity | UNIT | Base Year + 4 |
| 3001 | Para 5.1.2.4.12 Demolish Concrete and Masonry Structures Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. | 350,000 | CF | $ - 0 |
| 3002 | Para 5.1.2.4.13 Demolish Wood buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 75,000 | CF | $ - 0 |
| 3003 | Para 5.1.2.4.14 Demolish metal buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 40,000 | CF | $ - 0 |
| 3004 | Para 5.1.2.4.15 Demolish and remove Relocatable buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 5000 | SF | $ - 0 |
| 3005 | Para 5.1.2.4.16. Demolish building footings, foundations, concrete walls, basement walls, plain concete and slabs and haul concrete debris to the C&D landfill | 5,000 | CF | $ - 0 |
| 3006 | Para 5.1.2.4.17.c) Cap and/or loop chiller lines | 100 | LF | $ - 0 |
| 3007 | Para 5.1.2.4.18 Saw Cut Concrete 1' deep | 500 | LF | $ - 0 |
| 3008 | Para 5.1.2.4.19 Saw Cut Asphalt 8" deep | 300 | LF | $ - 0 |
| 3009 | Para 5.1.2.4.20 Demolish and Remove Brick Chimneys | 50 | CY | $ - 0 |
| 3010 | Para 5.1.2.4.21 Demolish and remove concrete sidewalks, floors, and slabs on grade (installation-wide). | 14,000 | CF | $ - 0 |
| 3011 | Para 5.1.2.4.22 Removal of Asphalt and Curbs. Demolish, remove pavement & curb, remove bituminous driveways, and haul to C&D landfill | 1,000 | CY | 0 |
| 3012 | Para 5.1.2.4.23 Disconnect and cap water and sewer lines | 100 | EA | 0 |
| 3013 | Para 5.1.2.4.24 DEMO and remove attached sheds, awnings, supporting facilities/buildings. | 6,000 | CF | $ - 0 |
| 3014 | Para 5.1.2.4.25 Demolish, and remove concrete utility boxes, culverts, headwalls. Utility removal, catch basin or manhole frames and covers, masonry, excludes hauling. | 9 | EA | $ - 0 |
| Site Stabilization | ||||
| 3015 | Para 5.1.2.5 Borrow Dirt to Backfill demolished area; Compaction of fill, 8" lifts; and, Grading of site | 3,000 | C.Y | $ - 0 |
| 3016 | Para 5.1.2.6 SEED, hydroseed and/or mechanical drill seed. Includes lime, fertilizer, seed. | 15,000 | SY | $ - 0 |
| 3017 | Para 5.1.2.7 Provide/compact/grade 6" gravel | 30 | T | $ - 0 |
| TOTAL for Option Year 3 = | ||||
| FORWARD TO SUMMARY SHEET |
Option YR 4
| ESTIMATED WORKLOAD Option Year 4 | |||
| FE16097 6J | |||
| Building Demolition IDIQ contract | |||
| Item Number | DESCRIPTION | Quantity | UNIT |
| 4001 | Para 5.1.2.4.12 Demolish Concrete and Masonry Structures Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. | 300,000 | CF |
| 4002 | Para 5.1.2.4.13 Demolish Wood buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 150,000 | CF |
| 4003 | Para 5.1.2.4.14 Demolish metal buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 50,000 | CF |
| 4004 | Para 5.1.2.4.15 Demolish and remove Relocatable buildings. Includes hauling all debris to the disposal sites. Includes all attached steps, piers, bollards, fencing, loading docks and ramps. Excludes slabs. | 20000 | SF |
| 4005 | Para 5.1.2.4.16. Demolish building footings, foundations, concrete walls, basement walls, plain concete and slabs and haul concrete debris to the C&D landfill | 10,000 | CF |
| 4006 | Para 5.1.2.4.17.c) Cap and/or loop chiller lines | 100 | LF |
| 4007 | Para 5.1.2.4.18 Saw Cut Concrete 1' deep | 500 | LF |
| 4008 | Para 5.1.2.4.19 Saw Cut Asphalt 8" deep | 300 | LF |
| 4009 | Para 5.1.2.4.20 Demolish and Remove Brick Chimneys | 50 | CY |
| 4010 | Para 5.1.2.4.21 Demolish and remove concrete sidewalks, floors, and slabs on grade (installation-wide). | 20,000 | CF |
| 4011 | Para 5.1.2.4.22 Removal of Asphalt and Curbs. Demolish, remove pavement & curb, remove bituminous driveways, and haul to C&D landfill | 1,000 | CY |
| 4012 | Para 5.1.2.4.23 Disconnect and cap water and sewer lines | 100 | EA |
| 4013 | Para 5.1.2.4.24 DEMO and remove attached sheds, awnings, supporting facilities/buildings. | 6,000 | CF |
| 4014 | Para 5.1.2.4.25 Demolish, and remove concrete utility boxes, culverts, headwalls. Utility removal, catch basin or manhole frames and covers, masonry, excludes hauling. | 9 | EA |
| Site Stabilization | |||
| 4015 | Para 5.1.2.5 Borrow Dirt to Backfill demolished area; Compaction of fill, 8" lifts; and, Grading of site | 3,000 | C.Y |
| 4016 | Para 5.1.2.6 SEED, hydroseed and/or mechanical drill seed. Includes lime, fertilizer, seed. | 15,000 | SY |
| 4017 | Para 5.1.2.7 Provide/compact/grade 6" gravel | 30 | T |
| TOTAL for Option Year 4 = | |||
| FORWARD TO SUMMARY SHEET |