This document provides details of a federal construction contract solicitation for the Tule River/Success Lake Spillway Enlargement Phase 2 project. The U.S. Army Corps of Engineers seeks a firm-fixed price contract to construct a 10 foot high 350 foot long curved reinforced concrete ogee weir across Success Lake spillway along with constructing side walls, downstream apron, and other improvements. The work includes widening the spillway, excavating the weir and apron foundations using blasting and excavation, installing rock anchors, constructing trench drains, flood proofing recreation facilities, and raising and relocating wells and storage tanks. Additional work involves adding rock slope protection to Frazier Dike and other areas around the lake. The solicitation will be issued on or about May 27, 2021 with bids due tentatively on June 25, 2021. The estimated value is between $25-100 million and it is set aside for small businesses. The NAICS code is 237990 and size standard is $39.5 million.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tule River Spillway
Enlargement
W9123821B0010
Bid Abstract
July 16, 2021 Independent Government Estimate $46,885,817.00
Michels $31,806,526.37
ShimmickConstruction $42,849,000.00
Malcolm International $48,517,269.00
NW Construction $54,975,000.00
Montana Civil Construction $45,260,260.00