W91238-16-R-0007-0004_Amend.pdf

PDF 184 KB Posted

Attached to
DB F-35A Hangar 40/42 Additions and AMU
Solicitation number
W91238-16-R-0007
Issued by

About this file

Amendment 0004 W91238-16-R-0007

View the file

Other files

File Type Posted
C01.14_Award_Announcement_(Synopsis).doc DOC document
Atch_5_Acknowledgement_Statement_05-06-2016.pdf PDF
A07.02_W91238-16-R-0008_Amend.pdf PDF
W91238-16-R-0007-0007_Amend.pdf PDF
A07.6_Bidder_Inquiry_Responses.pdf PDF
Amendment_6_SF30.pdf PDF
Amendment_6.pdf PDF
W9123816R00070005.pdf PDF
Atch_5_Acknowledgement_Statement_03-22-2016.pdf PDF
Pending_Amendment_4-4-2016.docx DOCX document
Pending_Correction_of_Due_Date.pdf PDF
A07.5_Site_Walk_Sign-In_Sheet_Public_Version_with_Redactions.pdf PDF
W91238-16-R-0007_Phase_2_Potential_Offerors.pdf PDF
Atch_1_SOW_F-35A_Hangar_40_42_Additions_and_AMU.pdf PDF
W91238-16-R-0007-0003_Amend.pdf PDF
Atch_3_Wage_Determination_Building_03-04-2016.pdf PDF
HILL_AFB_DB_RFP_HANGAR_40_42_AMU_JAN_2016_RTA.pdf PDF
Atch_2_Supplemental_Contract_Requirements.pdf PDF
Atch_5_Acknowledgement_Statement.pdf PDF
Atch_4_Wage_Determination_Heavy_01-08-2016.pdf PDF
W91238-16-R-0007-0002.pdf PDF
Attachment_9-01_45_00_(Amend_0002).pdf PDF
Attachment_8-01_33_00_(Amend_0002).pdf PDF
W91238-16-R-0007_Amend_0002.pdf PDF
W1238-16-R-0007_Amend_0001.pdf PDF
2-App1_HILL_AFB_CONSOLIDATED_DB_RFP_FULL_BC2_HANGAR_40_42_AMU_2015_12_21_d.pdf PDF
A07.1_6-Atch_5_Acknowledgement_Statement.pdf PDF
A07.1_3-Atch_2_Supplemental_Contract_Requirements.pdf PDF
A07.1_1-Atch_1_SOW_F-35A_Hangar_40_42_Additions_and_AMU.pdf PDF
W91238-16-R-0007.pdf PDF
A07.1_2-App_1_Hill_AFB_Final_D-B_RFP_F-35A_Hangar_40 42_Additions_and_AMU.pdf PDF
A07.1_4-Atch_3_Wage_Determination_Building.pdf PDF
A07.1_7-HILL_AFB_FINAL_DB_RFP_HANGAR_40_42_AMU_Drawings_2015_09_18.pdf PDF
A07.1_5-Atch_4_Wage_Determination_Heavy.pdf PDF
Synopsis_(Presolicitation)_F-35A.doc DOC document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. The purpose of this amendment is to correct the due date for the solicitation, and to ensure a consistent CLIN schedule throught the RFP and all attachments.

B. Unless noted otherw ise, "track changes" has been used to indicate the altered portions of the solicitation and attachment(s).

C. Except as noted in the follow ing pages, all other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 39

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Apr-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-16-R-0007

X 9B. DATED (SEE ITEM 11)

18-Dec-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Apr-2016

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4 SSP for W91238-16-R-0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION - CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Atch 1_SOW_F-35A

Hangar 40_42 Additions and AMU

3 29-OCT-2015

Attachment 2 Atch 2_Supplemental Contract Requirements

9 29-OCT-2015

Attachment 3 Atch 3_Wage Determination_Building 03-04-2016

5 04-MAR-2016

Attachment 4 Atch 4_Wage Determination_Heavy 01- 08-2016

5 08-JAN-2016

Attachment 5 Atch 5_Acknowledgement Statement

5 29-OCT-2015

Attachment 6 HILL AFB DB

RFP_HANGAR 40

42_AMU_JAN 2016

RTA

1494 27-JAN-2016

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Atch 1_SOW_F-35A

Hangar 40_42 Additions and AMU

3 29-OCT-2015

Attachment 2 Atch 2_Supplemental Contract Requirements

9 29-OCT-2015

Attachment 3 Atch 3_Wage Determination_Building 03-04-2016

5 04-MAR-2016

Attachment 4 Atch 4_Wage Determination_Heavy 01- 08-2016

5 08-JAN-2016

Attachment 5 Atch 5_Acknowledgement Statement 03-22-2016

5 22-MAR-2016

Attachment 6 HILL AFB DB

RFP_HANGAR 40

1494 27-JAN-2016

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

SSP for W91238-16-R-0007

42_AMU_JAN 2016

RTA

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 10-Apr-2016 11:00 AM to 26-Apr-2016 02:00 PM.

The number of offeror copies required has increased by 1 from 3 to 4.

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

SECTION 00 21 16

SECTION 00 21 16

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

INQUIRIES:

Prospective offerors should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the QUICK ADD link. Select agency as USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click continue. Fill in all required information and click Add User.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Number is : W91238-16-R-0007

The Bidder Inquiry Key is: 63J5NT-P2WJ2Z

c. The Bidder Inquiry System will be available for new inquiries shortly after the issuance of the Phase-II solicitation up until 10 days prior to the original phase-two proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

SSP for W91238-16-R-0007

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Daniel Czech Telephone: (916) 557-7012

E-MAIL: Daniel.E.Czech@usace.army.mil

DIRECTIONS FOR SUBMITTING OFFERS:

Envelopes/packages containing offers must be sealed, marked and addressed as follows:

MARK ENVELOPES/PACKAGES:

Solicitation No. W91238-16-R-0007

ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division, Daniel Czech 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTION PERTAINING TO HAND-CARRIED OFFERS:

Hand-carried offers must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, offerors may no longer hand-carry their offers directly to Contracting Division. Offers may NOT be turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no public parking in the Building.

The contract specialist will be in the Building Lobby 20 minutes prior to the closing time to accept hand-carried offers.

Offerors who desire to hand-deliver their offers at an earlier time must coordinate with the contract specialist in advance in order to arrange to be met in the Building Lobby by Contracting Division personnel.

Please ensure that all courier and delivery personnel are aware of these procedures.

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Section 00 22 11, Preaward Survey). All offerors will complete and return the Preaward Survey as part of the Price/Cost proposal. Failure to submit the Preaward Survey in conjunction with the price proposal will not of itself render the offer unacceptable.

Determination of Contractor Responsibility will be completed in accordance with FAR 9.104-1:

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

SSP for W91238-16-R-0007

If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in FAR 9.104-1) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.

The Preaward Survey as a tool used by the Government in determining responsibility of the offeror is submitted as part of the Price/Cost proposal and is separate from the technical proposal's response to the technical evaluation criteria found later in this section. Some of the information required from the offeror for completion of the Preaward Survey and the technical proposal may be duplicative but it is necessary that the information be provided in full in both places and that the Price/Cost proposal and the Technical proposal be separate documents. DO NOT state, for example, in the technical proposal, "See Price/Cost proposal for past performance information".

AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

a. The internet URL for Corps of Engineers publications is:

http://www.publications.usace.army.mil/

b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications.

Information about the CCB can be obtained from:

http://www.wbdg.org/ccb/ccb.php

FACSIMILE BIDS/OFFERS:

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15.

INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate.

BID GUARANTEE FORM AND AMOUNT:

The offeror shall furnish a separate bid guarantee in accordance with the solicitation provision titled "Bid Guarantee", FAR 52.228-1. In accordance with FAR 28.101-2 the bid guarantee amount shall be at least 20 percent of the "bid price" but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. If there are option line items on the CLIN Schedule, the term "bid price" is hereby defined as the total bid not to include any amount for line items designated as "options". In bids/proposals that contain "additives", the "bid price" is defined as the total of all bid items including additive line items. FAR 28.106-

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

SSP for W91238-16-R-0007

1 states that a Standard Form (SF) 24 shall be used for the bid bond. In accordance with FAR 28.202(a)(1), corporate sureties utilized must appear on the list contained in the Department of Treasury Circular 570 titled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies."

ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

System for Award Management (SAM) Registration:

It is a requirement that any and all contractors that intend to do business with the government must be registered in the System for Award Management (SAM) database. No contract may be awarded by the government to any contractor who is not registered in SAM. If your company is not registered in SAM, you must register in order to be eligible for any government award.

The following link provides access to the SAM website:

https://www.sam.gov/portal/public/SAM/

If you have difficulties with or questions regarding the SAM registration, the following link has been set up by the Defense Logistics Agency (DLA) to assist contractors registering for CAGE codes for enrollment and navigation within SAM:

https://www.logisticsinformationservice.dla.mil/CAGETier3/

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

The following have been modified:

INSTRUCTIONS TO OFFERORS

Section 00 22 10

PROPOSAL BASIS OF AWARD

GENERAL SUBMISSION REQUIREMENTS AND

INSTRUCTIONS, PHASE I INSTRUCTIONS AND

EVALUATIONS,

AND CONTRACT

AWARD

1. OVERVIEW.

a. This action is a "Best Value" solicitation for the Design-Build F-35A Hangar 40/42 Additions and AMU project at Hill AFB, UT. The Contracting Officer will award to those responsible offerors whom the Source Selection Authority determines offers the best overall value to the Government, considering all non-price factors described herein, and price of the task order project. The task order project requirements will be provided in the amendment to initiate phase two.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

b. This solicitation utilizes a two-phase source selection process requiring two separate proposal submittals, a phase-one (non-price technical volume) proposal and a phase-two (price and technical volumes) proposal. Phase- one will consist of an evaluation of only non-price factors which include Experience and Capability, Past Performance, and Project Approach of the offeror. Approximately four of the most highly qualified offerors in phase-one will be given the opportunity to submit a proposal under phase-two. Phase-two will consist of an evaluation of price and a non-price factors which will be determined at the time of the phase-two solicitation. The phase-two technical volume requirements will be provided in the amendment to initiate phase-two. The Government will award to the best value contract after phase two.

c. The Government neither intends to conduct discussions during phase-one, nor request revised phase-one proposals. However, the Government reserves the right to conduct phase-one discussions, if it deems such to be in its best interest in accordance with FAR 15.306.

2. BASIS OF AWARD.

2.1. ELIGIBILITY FOR CONTRACT AWARD

In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met.

This includes the FAR requirement that no award shall be made unless the contracting officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.

2.2. SOURCE SELECTION USING THE TRADE-OFF PROCESS

The Government will select the offer that represents the best value to the Government by using the tradeoff process described in FAR Part 15. This process permits tradeoffs between price and technical (“non-price”) factors and allows the Government to accept other than the lowest priced offer. The award decision will be based on a comparative analysis and an integrated assessment of proposals against all source selection criteria in the solicitation.

2.3. RELATIVE IMPORTANCE OF PRICE TO THE TECHNICAL EVALUATION FACTORS

All non-price evaluation factors, when combined, will be greater than price. The Government is concerned with striking the most advantageous balance between technical merit (“quality”) and cost to the Government (i.e., the price). If competing technical proposals are determined to be essentially equal, price could become the controlling factor

2.4. EVALUATION OF THE PRICE PROPOSAL

a. Price to the Government will be evaluated and considered but will not be scored or combined with other aspects of the proposal evaluation. The proposed price will be analyzed for reasonableness. It may also be analyzed to determine whether it reflects a clear understanding of the requirements; and is consistent with the offeror’s Technical Proposal. Additionally, all offers will be analyzed for unbalanced pricing.

b. The price evaluation adjustment for Small Disadvantaged Businesses will not apply to this procurement as it is currently suspended for Department of Defense.

c. Information required to be submitted in the Price Proposal volume in addition to the executed SF 1442 with acknowledgement of amendments and the completed pricing schedule will be used to determine the offeror’s eligibility for contract award in accordance with paragraph 2.1 above (for example, the offeror’s

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR

SSP for W91238-16-R-0007 representations and certifications; the bid guarantee; and the offeror’s pre-award survey information).

2.5. THE TECHNICAL EVALUATION FACTORS

a. The Government will evaluate each offeror’s technical proposal based on how well the proposal addresses each of the evaluation factors, listed below, and on how well the offeror has performed on related projects through the evaluation of the past performance information provided from references or obtained from other sources. Each of the evaluation factors will be evaluated by the Government and an adjectival rating and risk rating will be determined by consensus of the Government evaluation board for all technical factors other than past performance. The Past Performance factor will be evaluated by the Government and a relevancy and confidence level will be determined by consensus of the Government evaluation board.

b. The evaluation factors correlate directly to the main organizational tabs identified in the proposal submission instructions.

Phase-One Proposal. (Section 00 22 10)

(1) Factor 1: Experience and Capability

(2) Factor 2: Technical Approach

(3) Factor 3: Past Performance

Phase-Two Proposal. (Section 00 22 20)

(1) Factor 4: Technical Solution

(2) Factor 5: Performance Capability

c. The Source Selection Authority will consider both the phase one and phase two proposal evaluations with their relative strengths and weaknesses in determining the best value to the Government.

2.6 RELATIVE WEIGHTING OF THE TECHNICAL EVALUATION FACTORS

The Technical Evaluation Factors are listed below in descending order of importance, as follows:

Factor 1 – Experience and Capability is the most heavily weighted factor.

Factor 2 – Technical Approach is weighted less than Factor 1.

Factor 3 – Past Performance is weighted less than Factor 2.

Factor 4 – Technical Solution: both Factors 1 and 4 are of approximately equal importance.

Factor 5 – Performance Capability is approximately equal in importance to Factor 2.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

2.7 GENERAL TECHNICAL EVALUATION CRITERIA

a. The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. In addition, mistakes and errors will also be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements, significant mistakes/errors, or more than a nominal number of mistakes/errors may be seen as indicative of the type of problems that could be expected during contract performance. Lack of conformance may therefore result in a higher risk assessment, in addition to any other impacts on the evaluation. Material omission(s) may cause the technical proposal to be rejected as unacceptable. However, in accordance with FAR 52.215-1, the Government may waive informalities and minor irregularities in proposals. For example, a failure by a proposed key subcontractor to submit a properly executed letter of commitment may be considered as increasing risk, but will not be considered a proposal deficiency.

b. Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may be downgraded. The Government is under no obligation to search for information that is not in the specified location.

c. Proposals which are generic, vague, or lacking in detail may be downgraded. Responses that are essentially blanket offers of compliance are not adequate substitutes for the detailed and complete technical information necessary to establish that an offeror can meet US Government needs. The proposal submission instructions are written to give prospective contractors, where feasible, an indication of the level of detail desired by the Government. The offeror’s failure to include information that the Government has indicated should be included may result in the proposal being downgraded and/or being found deficient if inadequate detail is provided.

d. Any prescribed page and formatting limitations will be strictly adhered to and enforced by the Government.

The Government will not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit three pages in response to an item with a two page limitation, the information on the first two pages would be evaluated but the information on the third page would not be evaluated. If an offeror were to submit a fold-out sheet (e.g. 11”x17”) in response to a one-page limitation where fold-out sheets were not authorized, only the information that could reasonably have been submitted on one 8-1/2 x 11 inch sheet would be evaluated. If an offeror were to submit three 8-1/2 x 11 inch pages in response to a one not-to-exceed 11 x 17 inch page limitation, only the information that could reasonably have been submitted on one 11 x 17 inch sheet would be evaluated. If an offeror submitted alternates that were not requested (e.g. key subcontractor), the information will not be evaluated.

e. The degree of risk to the Government inherent in the offeror’s technical proposal will be a consideration under every evaluation factor.

f. A “deficiency” is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. “Weakness” means a flaw in a proposal that increases the risk of unsuccessful contract performance. A “significant weakness” is a proposal flaw that appreciably increases the risk of unsuccessful contract performance. The Government cannot accept an offer with a deficiency in its technical proposal. The term “acceptable” is therefore used in this context to describe a technical proposal that does not contain a deficiency and thus could be accepted by the Government, notwithstanding any weaknesses or significant weaknesses in the proposal.

g. The Government cannot make award based on a deficient offer. Therefore, a rating of “Unacceptable” under any factor will render the offer ineligible for award, unless the Government elects to enter into discussions with that offeror and all deficiencies are remedied in a revised proposal.

h. Failure of a proposed key subcontractor to furnish authorization for the Government to discuss its past performance with the offeror will not be considered a proposal deficiency. However, the Government will not be able to disclose to the offeror any details pertaining to their performance problems that may impact their overall rating.

i. Technical/Risk Rating for other than past performance.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

RATING DESCRIPTION

Outstanding

Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses.

Risk of unsuccessful performance is very low.

Good

Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses.

Acceptable

Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance.

Risk of unsuccessful performance is no worse than moderate.

Marginal

Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths.

Risk of unsuccessful performance is high.

Unacceptable

Proposal does not meet requirements and contains one or more deficiencies.

Proposal is unawardable.

j. Past Performance Evaluation. The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. The past performance evaluation considers each offeror's demonstrated recent and relevant record of performance in supplying products and services that meet the contract’s requirements. One performance confidence assessment rating is assigned for each offeror after evaluating the offeror's recent past performance, focusing on performance that is relevant to the contract requirements.

There are two aspects to the past performance evaluation. The first is to evaluate the offeror’s past performance to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The Government will review this past performance information and determine the quality and usefulness as it applies to performance confidence assessment.

1. Past Performance Relevancy Ratings

Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant

Present/past performance effort involved some of the scope and magnitude of effort and complexities this li it ti iNot Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation

2. Past Performance Confidence Assessments - In conducting a performance confidence assessment, each offeror shall be assigned one of the ratings in the table below:

Substantial Confidence

Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence

Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

Limited Confidence

Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort

Unknown Confidenc e (Neutral)

No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS FOR A TWO-PHASE DESIGN-

BUILD PROPOSAL.

3.1 GENERAL INSTRUCTIONS.

3.1.1 Media, Page Size, Margins, Fonts, and Page Limitations.

Submit only the hard-copy paper documents and electronic files specifically authorized elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal.

Except where another size is specifically authorized for a specific submission, use only 8 1/2” x 11” paper.

Use at least 1 inch margins, which may include headers and footers. Do not justify the right margin. Ensure that all text and graphics are clearly legible. Do not use a font size smaller than 10, unusual font styles such as script, or condensed fonts. For submissions with page limitations, the pages will be counted as follows:

One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, a foldout sheet will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.

3.1.2 Proposal Binding.

The preferred method for assembling proposals is a method that enables the rapid insertion or deletion of pages such as three ring binders. Ensure recommended capacity is not exceeded and that pages turn freely.

Do not use spring clamps, spiral binding systems, or heat binding systems.

3.1.3 Conditioning of Offer.

Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal volumes. Inclusion of any standard company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the offer is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the offer; see “Inquiries”, located in Section 00 21 16, for points of contact. Notwithstanding the above, the offeror must clearly describe in the proposal cover sheet submitted with the price volume any exceptions, within the offer, to the contractual and/or technical terms and conditions of the solicitation.

3.1.4 Restrictions on Offeror-Provided Information.

“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must clearly mark the information in accordance with FAR 52.215-1, “Instructions to Offeror – Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”. Files shall not contain classified data.

3.2 GENERAL PROPOSAL PREPARATION.

The proposal shall be submitted as summarized below and as required by the specifications.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

a. Phase-One Proposal.

(1) Technical Volume

(a) Submittal Information:

--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.

--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.

--Joint Venture Agreement --Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).

(b) Preface

(c) Technical Factors

(1) Factor 1: Experience and Capability

(2) Factor 2: Technical Approach

(3) Factor 3: Past Performance

b. Phase-Two Proposal.

(1) Volume I – Price Volume

(a) Proposal Cover Sheet

(b) Standard Form 1442, Acknowledgement of Amendments, Joint Venture Agreement

(c) Pricing Schedule

(d) Work Breakdown Structure

(e) Bid Guarantee

(f) Pre-Award Survey Information

(2) Volume II – Technical Volume

(1) Factor 4: Technical Solution

(2) Factor 5: Performance Capability

Each offeror must submit a phase-one proposal consisting of only a “technical” volume and each selected phase-two offeror must submit a phase-two proposal consisting of both a “price” volume and a “technical” volume. The price volume includes the signed offer and the offeror’s proposed prices. The technical volume includes all required information relating to the “non-price” evaluation factors. The two volumes must be submitted as separate, physically distinct volumes. Both volumes must be received at the location shown in Block 8 of Standard Form 1442, not later than the date and time specified in Block 13 of Standard Form 1442.

The information in the two volumes is evaluated separately and independently. Therefore, all information intended by the offeror to be evaluated as part of the price volume must be submitted as part of the price volume. All information intended by the offeror to be evaluated as part of the technical volume must be submitted as part of the technical volume. Do not merely cross-reference similar material between the technical and price volumes.

3.2.1 Marking of Proposal Volumes.

Mark each volume as either the “Price Volume” or the “Technical Volume”. In addition, mark the outside front cover of each volume with the project title and location, solicitation number, name and address of the offeror, and volume copy number. (Markings which identify the offeror are not required on either the back cover or on the spine/binding.)

3.2.2 Tabbing of Proposal Volumes.

Offers are to be formatted and tabbed in accordance with the instructions that follow for each proposal volume.

3.2.3 Table of Contents.

Include a table of contents for each proposal volume.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

4 PHASE-ONE PROPOSAL.

4.1 NUMBER OF SETS OF THE TECHNICAL VOLUME.

The Technical Proposal is to be submitted in one hard “original” and three (3) copies. In addition, submit one complete copy of the technical proposal on Compact Disk (CD).

4.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE TECHNICAL VOLUME.

Use 8-1/2” x 11” pages for the narrative portions of the proposal. There is not a page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location. Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal. Limit your submittals to the information specified; excess information will not be evaluated.

PHASE-ONE TECHNICAL VOLUME

TAB CONTENTS

1. FACTOR 1 – EXPERIENCE AND CAPABILITY

Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability Key Personnel Resumes

2. FACTOR 2 –TECHNICAL APPROACH

Narrative and Discussion of Technical Approach

3. FACTOR 3 – PAST PERFORMANCE

4.3 DETAILED SUBMISSION REQUIREMENTS AND EVALUATION CRITERIA FOR THE TECHNICAL

PROPOSAL.

4.3.1 Preface – Prime Contractor/Key Subcontractor Introduction

a. The Offeror is required to propose a specific project team including key subcontractors for evaluation in response to this Request for Proposals. For purposes of this procurement, the terms “key subcontractors” are used to refer only to the prospective subcontractors whose qualifications, experience, and past performance will be evaluated by the Government as part of the source selection process. For reasons of efficiency, not all of the subcontractors critical to successful post-award contract performance have been included in this group.

In order to streamline the proposal submission and evaluation process, please limit your submission to the information specifically requested. Information pertaining to other subcontractors not designated as “key” by the Government will be considered excess and may not be evaluated.

b. For the purposes of this procurement, a key subcontractor is defined as any subcontractor performing “key” major work elements for which capability information is required to be submitted for evaluation as part of the Offeror’s technical proposal. The Government has designated the following major work elements as “key”:

- Architect-Engineer Design Firm

c. Any changes to key subcontractors in your Phase 2 proposal from your Phase 1 proposal will not be allowed.

d. The Offeror’s attention is directed to the clause in Section 00 72 00 titled “Personnel, Subcontractors and Outside Associates or Consultants.” In accordance with this clause, any post-award changes to the key personnel and/or key subcontractors in the accepted proposal will require contracting officer approval.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

e. Provide a brief introduction narrative. Identify and provide the name, DUNS number, address, point of contact e-mail address, and a brief description of the role and authority of each firm that will be involved in performance of this contract at the prime contractor and key subcontractor level. If the proposed prime contractor is a Joint Venture, describe the relationship, role, and authority (to include management authority) of each firm. (Note: If a proposed firm has branch offices, provide information for each individual branch office that will perform work under the contract with its own workforce.) List the major work elements to be self-performed by the offeror’s in-house work force, the major work elements to be performed by each key subcontractor, and any other major work to be subcontracted to other contractors. The submission is limited to two (2) 8-1/2”x11” pages for narrative.

f. The Government will not evaluate the Preface - Prime Contractor/Key Subcontractor Introduction. The purpose of this narrative is to provide a brief introduction for information purposes; however, if applicable, the government reserves the right to consider it throughout the evaluation of the other factors.

4.3.2 Tab 1 of the Technical Volume: Factor 1 – Experience and Capability.

4.3.2.1. General

a. The resumes and example projects will provide the primary basis for the Government’s evaluation of the offeror’s experience and capability.

b. The Government is interested in selecting a contractor with the ability to complete projects similar in size, complexity, and scope to that of the prospective contract, including Design-Build and Construction experience of similar aircraft maintenance hangars (Addition/Alteration and New Construction)

c. Offeror’s must submit example projects (either commercial or institutional) demonstrating the following capabilities:

(1) At least one project demonstrating the offeror’s capability as a prime contractor on a construction project of similar type and scope.

(2) At least one project demonstrating the capability of the lead firm that will be designing the project, on a construction project of similar type and scope.

(3) At least one project demonstrating the offeror’s design-build management capability as a prime contractor on a construction project of similar type and scope.

4.3.2.2. Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability.

a. The offeror shall, if possible, submit “example projects” per paragraphs (1) and (2) below, that demonstrate the prime’s and/or key subcontractor’s wide experience and capability meeting the Evaluation Criteria to successfully perform under the resulting contract. The offeror must explain how the work performed by the proposed firm in the example project is relevant to this project. Example projects can demonstrate multiple experiences and capabilities. However, if an example project is being used for multiple experiences and capabilities, ensure sufficient information is provided to demonstrate those applicable experiences and capabilities. Each example project submitted does not need to demonstrate multiple experiences and capabilities; however, all the example projects should collectively demonstrate wide experience and capability. Submit:

(1) Three (3) but no more than five (5) example projects demonstrating the those capabilities listed above at

4.3.2.1 c, and

b. Do not submit construction projects that are not substantially complete. (For this purpose, “substantially complete” means that only punch list items remain for project acceptance or that the majority of the elements of the project have been turned over to the customer for beneficial occupancy.) If a design-build project is being used by an A-E to demonstrate their design capability, the design portion of the contract must be complete in order for it to be considered.

c. Provide a Summary Matrix that indicates which submitted example project(s) demonstrates which

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4 experience and/or capability. The example provided is not mandatory, develop and provide your own matrix that best explains your proposal.

PRIME A/E

CAPABILITY/EXAMPLE

PROJECT

#1 #2 #3 #4 #5

Construction project of similar type and scope

X X

X

A-E Design of project of similar type and scope

X

Design-build management capability as a prime contractor on a construction project of similar type and scope.

X X

Prime and A/E teaming X X

Corps of Engineers experience X X

Hill AFB experience X X

d. Formatting and Other Restrictions.

(1) Start the information for each example project on a new page.

(2) Use the “Project Information Form” below to submit the example projects. Use of an alternate format could result in a lower rating if all of the specified information is not provided. (Note: Do not submit a group of related jobs as one project unless all of the work was done under the same contract, or for indefinite delivery contracts, under one task order.) Example projects are limited to 10 pages 8-1/2" x 11" (or a maximum of 20 pages front and back) total, for all projects.

(3) The Summary Matrix is limited to one (1) 8-1/2”x11” page.

PROJECT INFORMATION FORM

1. Example Project Number: Start with “1” for the first of all submitted projects and number consecutively.

2. Name of Contractor(s)/Key Subcontractor (s) that Project is Demonstrating Experience: Provide the name of the proposed firm(s) that this example project is demonstrating experience and capability.

3. Contract Number and Awarded Prime Contractor Name: Provide contract number assigned by the procuring Contracting Office and the name of the contractor that was awarded the contract.

4. Title and Location: Title and location of project or contract.

5. Month and Year Project Work Commenced and Month and Year Project was Completed.

Include original completion date and actual completion date and a succinct description for changes in these two dates.

6. Project Owner: Project and contract owner or user, such as a government agency or installation, an institution, or corporation or private individual.

7. Point of Contact Name: Provide name of a person associated with the project owner or the organization that contracted for the construction, who is very familiar with the project and the firm’s (or firms’) performance.

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

8. Point of Contact Telephone Number: Include area code.

9. Description of the Project: Provide information relevant to the Evaluation Criteria, including but not limited to the following information. Provide contract type, dollar amount (original contract amount and final dollar value (include an explanation for the difference)), physical size, and brief description of prime contracted effort. If the firm (prime/key subcontractor) performed as a subcontractor, describe the work effort pertaining to the subcontracted effort, not the prime contract requirement. Provide the performance period in month and year. Explain how the project demonstrates the ability to manage multiple projects at once. Explain how the project demonstrates proper management of scope, schedule, and budget.

10. Provide name of firm(s) (prime/key subcontractor) and branch offices, if appropriate, that were involved in the example project, their roles, and their respective contract numbers.

11. Please list the other projects you were completing concurrently (please include dollar value for each concurrent project).

e. Evaluation Criteria.

(1) Demonstrated experience and capability in the following areas will be evaluated for relevancy (similar in project type, dollar value, contact type, complexity, scope, and magnitude to the instant procurement) and recency (example projects completed before 2012 will be considered by the Government to be less recent, than projects completed on or after 2012; the more recent the project is, the greater the consideration).

(a) Prime Contractor’s contractor/construction/project management experience and capability.

(b) Architect-Engineer Design firm’s experience and capability.

(c) Experience and capability with projects similar to that of the project in the resulting contract.

(2) Demonstrations of experience and capability in the following areas may be considered advantageous. (A lack of any of the below items will not be considered unfavorable.):

(a) Prime contractor and Architect-Engineer designer teaming experience on similar design-build projects.

(b) Prior experience on Corps of Engineers construction projects.

(c) Prior experience on Hill AFB construction projects.

4.3.2.3. Key Personnel Resumes

a. The offeror must submit a resume of the qualifications for each of the persons proposed for each of the key positions identified by the Government. The offeror may only submit the qualifications of one person for each key position (i.e., do not submit alternates).

b. Key positions with minimum criteria:

- On-site Project Superintendent – five years’ experience as construction site project superintendent on a substantially completed construction projects with similar construction features, complexity, physical size as the instant procurement, occurring within the last five years.

- On-site CQC System Manager – This individual must be a construction person with a minimum of five years’ experience in related work (to the instant procurement) with a four-year college degree. See Section 01 45 00 for additional minimum qualifications for this position.

c. The Government is especially interested in the experience of the proposed key personnel in the same capacity on relevant projects, defined in the same way as in 4.3.2.2 e, above. For example, experience in the following areas would be considered advantageous:

W91238-16-R-00070004ONLY. SOURCE SELECTION INFORMATION. SEE FAR 2.101 and 3.104 in accordance with FAR 3.104-4

- Experience on an aircraft maintenance hangar construction project.

- Experience on a project installing a high-expansion foam fire suppression system.

- Experience on Corps-of-Engineers-administered aircraft maintenance hangars.

4.3.3 Tab 2 of the Technical Proposal: Factor 2 – Technical Approach.

4.3.3.1 The Government is interested in how the offeror plans to structure, organize, control, and manage this design-build project. Of particular interest is the prime contractor’s plan to manage and direct the design with respect to quality, and timely performance of the design deliverables. Accordingly, Offerors must:

a. Provide a detailed narrative that clearly demonstrates:

o That the offeror has the ability to effectively manage the designers, consultants, and subcontractors on the team.

o The offeror’s ability to coordinate all work throughout the design and construction phases.

o The offeror’s understanding of the phasing of the work and the planned approach to accomplish the project’s scope.

b. Discuss how the offeror plans to ensure quality control throughout the project. This discussion should address the offeror’s understanding of, familiarity with, and…