A07.1_3-Atch_2_Supplemental_Contract_Requirements.pdf

PDF 39 KB Posted

Attached to
DB F-35A Hangar 40/42 Additions and AMU
Solicitation number
W91238-16-R-0007
Issued by

About this file

Atch 2_Supplemental Contract Requirements

View the file

Other files

File Type Posted
C01.14_Award_Announcement_(Synopsis).doc DOC document
Atch_5_Acknowledgement_Statement_05-06-2016.pdf PDF
A07.02_W91238-16-R-0008_Amend.pdf PDF
W91238-16-R-0007-0007_Amend.pdf PDF
A07.6_Bidder_Inquiry_Responses.pdf PDF
Amendment_6_SF30.pdf PDF
Amendment_6.pdf PDF
W9123816R00070005.pdf PDF
Atch_5_Acknowledgement_Statement_03-22-2016.pdf PDF
W91238-16-R-0007-0004_Amend.pdf PDF
Pending_Amendment_4-4-2016.docx DOCX document
Pending_Correction_of_Due_Date.pdf PDF
A07.5_Site_Walk_Sign-In_Sheet_Public_Version_with_Redactions.pdf PDF
W91238-16-R-0007_Phase_2_Potential_Offerors.pdf PDF
Atch_1_SOW_F-35A_Hangar_40_42_Additions_and_AMU.pdf PDF
W91238-16-R-0007-0003_Amend.pdf PDF
Atch_3_Wage_Determination_Building_03-04-2016.pdf PDF
HILL_AFB_DB_RFP_HANGAR_40_42_AMU_JAN_2016_RTA.pdf PDF
Atch_2_Supplemental_Contract_Requirements.pdf PDF
Atch_5_Acknowledgement_Statement.pdf PDF
Atch_4_Wage_Determination_Heavy_01-08-2016.pdf PDF
W91238-16-R-0007-0002.pdf PDF
Attachment_9-01_45_00_(Amend_0002).pdf PDF
Attachment_8-01_33_00_(Amend_0002).pdf PDF
W91238-16-R-0007_Amend_0002.pdf PDF
W1238-16-R-0007_Amend_0001.pdf PDF
2-App1_HILL_AFB_CONSOLIDATED_DB_RFP_FULL_BC2_HANGAR_40_42_AMU_2015_12_21_d.pdf PDF
A07.1_6-Atch_5_Acknowledgement_Statement.pdf PDF
A07.1_1-Atch_1_SOW_F-35A_Hangar_40_42_Additions_and_AMU.pdf PDF
W91238-16-R-0007.pdf PDF
A07.1_2-App_1_Hill_AFB_Final_D-B_RFP_F-35A_Hangar_40 42_Additions_and_AMU.pdf PDF
A07.1_4-Atch_3_Wage_Determination_Building.pdf PDF
A07.1_7-HILL_AFB_FINAL_DB_RFP_HANGAR_40_42_AMU_Drawings_2015_09_18.pdf PDF
A07.1_5-Atch_4_Wage_Determination_Heavy.pdf PDF
Synopsis_(Presolicitation)_F-35A.doc DOC document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2 – Supplemental Contract Requirements F-35A Hangar 40/42 Additions and AMU Hill AFB, UT October 29, 2015

SUPPLEMENTAL CONTRACT REQUIREMENTS

1. Performance Period. Refer to FAR 52.211-10, Commencement, Prosecution, And Completion of Work. The time duration of performance period is 730 calendar days after Notice to Proceed date.

2. Liquidated Damages. Refer to FAR 52.211-12, Liquidated Damages-Construction.

Liquidated damages for this work is $1,250.00 for each day of delay.

3. Authorities. Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer. The Government Contracting Officer/Administrative Contracting Officer has the authority to make any changes to this contract action that impact cost or schedule. Authority from the Contracting Officer/Administrative Contracting Officer to the contractor to make changes that impact cost or schedule will be in the form of an official, signed modification.

4. Wage Determination. General Decision Numbers UT150104, 01/16/2015 (Building) and UT150028, 08/07/2015 (Heavy), Davis County, Utah, or their most current modifications at the time of award are hereby applicable to work performed under this contract. The most current decisions or their modifications can be found by clicking on hyperlink http://www.wdol.gov/dba.aspx for such information.

5. Time Extensions For Unusually Severe Weather. Refer to FAR 52.249-10, Default (Fixed- Priced Construction). All weather delays will need to be submitted and approved by the Contracting Officer Representative.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(22) (17) (13) (08) (05) (03) (01) (02) (03) (05) (12) (22)

Hill AFB, UT October 29, 2015

DESIGN BUILD CONDITIONS

52.236-5000 Design-Build Contract Order of Precedence

Design-Build Contract Order of Precedence (AUG 1997)

(a) The contract includes the standard contract clauses and schedules current at the time of contract award. It entails (1) the solicitation in its entirety, including all drawings, cuts, and illustrations, and any amendments, and (2) the successful offeror’s accepted proposal. The contract constitutes and defines the entire agreement between the Contractor and the Government. No documentation shall be omitted which in any way bears upon the terms of that agreement.

(b) In the event of conflict or inconsistency between any of the provisions of this contract, precedence shall be given in the following order:

(1) Betterments: Any portions of the accepted proposal which both conform to and exceed the provisions of the solicitation.

(2) The provisions of the solicitation. (See also FAR 52.236-2 Alt 1, Specifications and Drawings for Construction)

(3) All other provisions of the accepted proposal.

(4) Any design products including, but not limited to, plans, specifications, engineering studies and analyses, shop drawings, equipment installation drawings, etc. These are "deliverables" under the contract and are not part of the contract itself. Design products must conform with all provisions of the contract, in the order of precedence herein.

52.236-5001 Personnel, Subcontractors and Outside Associates or Consultants.

Personnel, Subcontractors and Outside Associates or Consultants (MAY 2006)

In connection with this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.

As prescribed at 11.703(c), insert the following clause in solicitations and contracts for fixed-price construction contracts when subdivided items are to be separately priced for payment purposes

52.236-5002 Government-Furnished Specifications, Drawings, Surveys, and Specifications in the Request for Proposal (JUL 2002)

This is to clarify DFARS 252.236-7001, Contract Drawings and Specifications, refers to any Government- furnished design or design criteria included in the Request for Proposal (RFP).

Hill AFB, UT October 29, 2015

52.236-5003 Government-Furnished Specifications and Drawings for Construction (JUL 2003)

This is to clarify FAR 52.236-21Alt 1, Specifications and Drawings for Construction, refers to any specifications and drawings furnished in the Request for Proposal (RFP). The term "specifications" refers to the design criteria or scope of work, in addition to any attached specifications.

52.236-5004 Responsibility of the Contractor for Design (MAY 2002)

(a) The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other non-construction services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiency in its designs, drawings, specifications, and other non-construction services and perform any necessary rework or modifications, including any damage to real or personal property, resulting from the design error or omission.

(b) The standard of care for all design services performed under this agreement shall be the care and skill ordinarily used by members of the architectural or engineering professions practicing under similar conditions at the same time and locality. Notwithstanding the above, in the event that the contract specifies that portions of the Work be performed in accordance with a performance standard, the design services shall be performed so as to achieve such standards.

(c) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contact, shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract. The Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance of any of these services furnished under this contract.

(d) The rights and remedies of the Government provided for under this contract are in addition to any other rights and remedies provided by law.

(e) If the Contractor is comprised of more than one legal entity, each entity shall be jointly and severally liable hereunder.

52.236-5005 Warranty of Design (MAY 2002)

(a) The Contractor warrants that the design shall be performed in accordance with the contract requirements. Design and design related construction not conforming to the Contract requirements shall be corrected at no additional cost to the Government. The standard of care for design is defined in paragraph (b) of special contract requirement 52.236-5004, Responsibility of the Contractor for Design.

(b) The period of this warranty shall commence upon final completion and the Government’s acceptance of the work, or in the case of the Government’s beneficial occupancy of all or part of the work for its convenience, prior to final completion and acceptance, at the time of such occupancy.

(c) This design warranty shall be effective from the above event through the Statue of Limitations and Statute of Repose, as applicable to the state that the project is located in.

Hill AFB, UT October 29, 2015

(d) The rights and remedies of the Government provided for under this clause are in addition to any other rights and remedies provided in this contract or by law.

52.236-5006 Deviating from the Accepted Design (JUN 2002)

(a) The Contractor must obtain the approval of the Designer of Record and the Government’s concurrence for any Contractor proposed revision to the professionally stamped and sealed and Government reviewed design, before proceeding with the revision.

(b) The Government reserves the right to non-concur with any revision to the design, which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed design.

(c) Any revision to the design, which deviates from the contract requirements (i.e., the RFP and the accepted proposal), will require a modification, pursuant to the Changes clause, in addition to Government concurrence. The Government reserves the right to disapprove such a revision.

(d) Unless the Government initiates a change to the contract requirements, or the Government determines that the Government furnished design criteria are incorrect and must be revised, any Contractor initiated proposed change to the contract requirements, which results in additional cost, shall strictly be at the Contractor's expense.

(e) The Contractor shall track all approved revisions to the reviewed and accepted design and shall incorporate them into the as-built design documentation, in accordance with agreed procedures. The Designer of Record shall document its professional concurrence on the as-builts for any revisions in the stamped and sealed drawings and specifications.

52.236-5007 Contractor's Role During Design Process (JUN 1998)

The contractor's construction management key personnel shall be actively involved during the design process to effectively integrate the design and construction requirements of this contract.

In addition to the typical required construction activities, the Contractor's involvement includes, but is not limited to actions such as: integrating the design schedule into the Master Schedule to maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the contract), ensuring constructability and economy of the design, integrating the shop drawing and installation drawing process into the design, executing the material and equipment acquisition programs to meet critical schedules, effectively interfacing the construction QC program with the design QC program, and maintaining and providing the design team with accurate, up-to-date redline and as-built documentation. The Contractor shall require and manage the active involvement of key trade subcontractors in the above activities.

52.236-5008 Value Engineering after Award (JUN 1999)

(a) In reference to FAR 52.248-3, Value Engineering-Construction, the Government may refuse to entertain a "Value Engineering Change Proposal" (VECP) for those "performance oriented"

Hill AFB, UT October 29, 2015 aspects of the Solicitation documents which were addressed in the Contractor's accepted contract proposal and which were evaluated in competition with other offerors for award of this contract.

(b) The Government may consider a VECP for those "prescriptive" aspects of the Solicitation documents, not addressed in the Contractor's accepted contract proposal or addressed but evaluated only for minimum conformance with the Solicitation requirements.

(c) For purposes of this clause, the term "performance oriented" refers to those aspects of the design criteria or other contract requirements which allow the offeror or Contractor certain latitude, choice of and flexibility to propose in its accepted contract offer a choice of design, technical approach, design solution, construction approach or other approach to fulfill the contract requirements. Such requirements generally tend to be expressed in terms of functions to be performed, performance required or essential physical characteristics, without dictating a specific process or specific design solution for achieving the desired result.

(d) In contrast, for purposes of this clause, the term "prescriptive" refers to those aspects of the design criteria or other Solicitation requirements wherein the Government expressed the design solution or other requirements in terms of specific material, approaches, systems, and/or processes to be used. Prescriptive aspects typically allow the offerors little or no freedom in the choice of design approach, materials, fabrication techniques, methods of installation, or any other approach to fulfill the contract requirements.

52.236-5009 Partnering (FEB 2000)

In order to most effectively accomplish this contract, the Government proposes to form a partnership with the Contractor to develop a cohesive building team. It is anticipated that this partnership would involve the U.S. Army Dugway Proving Ground Installation, the Contractor, primary subcontractors and designers and the Corps of Engineers. This partnership would strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This partnership would be bilateral in membership and participation will be totally voluntary.

52.236-5010 Government Re-Use of Design (MAY 2006)

In conjunction with the DFARS 252.227-7022, Government Rights (Unlimited), the Government will not ask for additional originals or copies of the design works after the Contractor provides all required design documentation and as-built documentation under the instant contract. Further, if the Government uses the design for other projects without additional compensation to the Contractor for re-use, the Government releases the Contractor from liability in the design on the other projects, due to defects in the design that are not the result of fraud, gross mistake as amounts to fraud, gross negligence or intentional misrepresentation.

DESIGN BUILD SUPPLEMENTARY CONDITIONS

PROPOSED BETTERMENTS

(a) The minimum requirements of the contract are identified in the Request for Proposal. All betterments offered in the proposal become a requirement of the awarded contract.

Hill AFB, UT October 29, 2015

(b) A “Betterment” is defined as any component or system, which exceeds the minimum requirements stated in the Request for Proposal. This includes all proposed betterments listed in accordance with the “Proposal Submission Requirements” of the Solicitation, and all Government identified betterments.

(c) “Government identified betterments” include the betterments identified on the “List of Accepted Project Betterments” prepared by the Proposal Evaluation Board and made part of the contract by alteration, and all other betterments identified in the accepted Proposal after award.

WARRANTY OF CONSTRUCTION WORK

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (1) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, or workmanship.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--

(1) Obtain all warranties that would be given in normal commercial practice:

Hill AFB, UT October 29, 2015

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the

Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

SEQUENCE OF DESIGN-CONSTRUCTION (HND AUG 1997)

(a) After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply with all design submission requirements as covered under Division 01 General Requirements, and obtain Government review of each submission. No construction may be started, until the Government reviews the Final Design submission and determines it satisfactory for purposes of beginning construction. The ACO or COR will notify the Contractor when the design is cleared for construction. The Government will not grant any time extension for any design resubmittal required when, in the opinion of the ACO or COR, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.

(b) If the Government allows the Contractor to proceed with limited construction based on pending minor revisions to the reviewed Final Design submission, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.

(c) No payment will be made for any in-place construction until all required submittals have been made, reviewed and are satisfactory to the Government.

RECOMMENDED INSURANCE COVERAGE (HND MAR 2002)

The Design-Build Contractor’s attention is invited to the contract requirements concerning

“RESPONSIBILITY OF THE CONTRACTOR FOR DESIGN”, “WARRANTY OF DESIGN”

and “WARRANTY OF CONSTRUCTION WORK”. These requirements vest in the Contractor complete responsibility for the professional quality, technical accuracy, and coordination of all design, drawings, specifications and other work or materials furnish by his in-house or consultant forces. The Design-Build Contractor must correct and revise any errors or deficiencies in his

Hill AFB, UT October 29, 2015 work, notwithstanding any review, approval, acceptance or payment by the Government. The Contractor must correct and change any work resulting from his defective design at no additional cost to the Government. The requirements further stipulate that the Design-Build Contractor shall be liable to the Government for the damages to the Government caused by negligent performance. Though not a mandatory requirement, this is to recommend that the Design-Build Contractor investigate and obtain appropriate insurance coverage for such liability protection.

TRAINING (HND FEB 2000)

The Contractor shall provide operational and maintenance training for all systems furnished under this contract for the operating and maintenance personnel. The system manufacturer shall conduct the training, where feasible. All operation and maintenance manuals shall be submitted and approved prior to conducting the training and shall be used during training. The Contractor shall videotape the training session on DVD and provide the DVD(s) to the government.

DESIGN CONFERENCES (HND AUG 1997)

(a) Pre-Work: As part of the Pre-Work Conference conducted after contract award, key representatives of the Government and the Contractor will review the design submission and review procedures specified herein, discuss the preliminary design schedule and provisions for phase completion of the D-B documents with construction activities, as appropriate, meet with Corps of Engineers Design Review personnel and key Using Agency points of contact and any other appropriate pre-design discussion items.

(b) Design Charette: After award of the contract, the Contractor shall visit the site and conduct extensive interviews, and problem solving discussions with the individual users, base personnel, Corps of Engineers personnel to acquire all necessary site information, review user options, and discuss user needs. The Contractor shall document all discussions. The design shall be finalized as direct result of these meetings.

(c) Design Review Conferences: Review conferences will be held on base for each design submittal. The Contractor will bring the personnel that developed the design submittal to the review conference. The conferences will take place the week after the review is complete.

SUBMITTAL OF WORK TO BE PERFORMED BY THE CONTRACTOR (HND

UNDATED)

The Contractor shall furnish the Contracting Officer within 10 days after the award the items of work he will perform with his own forces and the estimated cost of those items. The percentage of work that must be performed by the Contractor is stated in Contract Clause 52.236-1, “PERFORMANCE OF WORK BY THE CONTRACTOR”.

Hill AFB, UT October 29, 2015