FY 11 General Instruction Building (GIB) Presidio of Monterey 1624

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 57 23.00 41

TEMPORARY STORM WATER POLLUTION CONTROL

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.2.1 Required Submittal Meetings

1.3 GENERAL REQUIREMENTS

1.3.1 TRAINING REQUIREMENTS

1.3.1.1 Qualified SWPPP Developer (QSD)

1.3.1.2 Qualified SWPPP Practitioner (QSP)

1.3.2 Additional Requirements

1.4 DEVELOPMENT AND DESIGN

1.4.1 SWPPP Development

1.4.1.1 Construction Site Management Plan (CSMP)

1.4.1.2 Sampling And Analysis Plan (SAP) Design

1.4.1.3 Best Management Practices (BMPs)

1.4.2 Permit Registration Documents (PRDs)

PART 2 PRODUCTS

2.1 REQUIRED BEST MANAGEMENT PRACTICES

2.1.1 Erosion Control BMPs

2.1.1.1 SCHEDULING

2.1.1.2 PRESERVATION OF EXISTING VEGETATION

2.1.1.3 HYDRAULIC MULCH

2.1.1.4 HYDROSEEDIMG

2.1.1.5 SOIL BINDERS

2.1.1.6 STRAW MULCH

2.1.1.7 GEOTEXTILES AND MATS

2.1.2 Sediment Control BMPs

2.1.2.1 SILT FENCE

2.1.2.1.1 SEDIMENT BASIN

2.1.2.2 FIBER ROLLS

2.1.2.3 STREET SWEEPING AND VACUUMING

2.1.2.4 STORM DRAIN INLET PROTECTION

2.1.3 Wind Erosion Control BMP

2.1.4 Tracking Control BMPs

2.1.4.1 STABILIZED CONSTRUCTION ENTRANCE/EXIT

2.1.5 Non-Stormwater Management BMPs

2.1.5.1 ILLICIT CONNECTION/ILLEGAL DISCHARGE DETECTION AND REPORTING

2.1.5.2 VEHICLE AND EQUIPMENT CLEANING

2.1.5.3 VEHICLE AND EQUIPMENT FUELING

2.1.5.4 VEHICLE AND EQUIPMENT MAINTENANCE

2.1.6 Waste Management And Materials Pollution Control BMPs

2.1.6.1 Material Delivery And Storage

2.1.6.2 Material Use

2.1.6.3 Stockpile Management

01 57 23.00 41- 1 AM-01

2.1.6.4 Spill Prevention And Control

2.1.6.5 Sanitary/Septic Waste Management

2.2 AVAILABLE BEST MANAGEMENT PRACTICES

PART 3 EXECUTION

3.1 MOBILIZATION AND DEMOBILIZATION

3.1.1 BMP Installation And Removal

3.1.2 Termination Of SWPPP And CSMP Responsibilities

3.1.3 Records

3.2 MAINTENANCE, MONITORING AND INSPECTIONS

3.2.1 SWPPP And Amendments

3.2.2 Rain Event Action Plans (REAPs)

3.2.3 Monitoring And Inspections

3.2.4 Correcting Deficiencies

3.2.5 Sampling And Analysis Plan (SAP)

3.2.5.1 Non-Storm Water Discharge

3.2.5.2 Non-Visible Pollutants

3.2.5.3 NAL Exceedance Report

-- End of Section Table of Contents --

01 57 23.00 41- 2 AM-01

SECTION 01 57 23.00 41

TEMPORARY STORM WATER POLLUTION CONTROL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

CALIFORNIA STATE WATER RESOURCES CONTROL BOARD (CSWRCB)

CSWRCB GO 2009-0009-DWQ (2009) Construction Activities Storm Water General Permit Order No. 2009-0009-DWQ

CALIFORNIA STORMWATER QUALITY ASSOCIATION (CASQA)

CASQA CABMPHB (2009) California Stormwater Best Management Practice Handbook for Construction

STANDARD METHODS (SM)

SM 2130 (2001) Turbidity

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA Method 180.1 (1993; R2) Determination Of Turbidity By Nephelometry

NPDES (1972; R 2005) National Pollutant Discharge Elimination System

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 136 Guidelines Establishing Test Procedures For The Analysis Of Pollutants

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The contractor will be responsible to present submittals with sufficient lead time to reasonably allow for government review and contractor revisions in a time frame which will not delay project schedule. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Certified Storm Water Pollution Prevention Plan (SWPPP); G, DO

01 57 23.00 41- 3 AM-01

The SWPPP will implement best management practices consistent with industry standards and State and local regulatory requirements for construction. Manufacturer's installation instructions of erosion controls and sedimentation controls shall be followed to assist in meeting regulatory requirements. A complete Construction Site Monitoring Program (CSMP), including the Sampling and Analysis Plan (SAP), and an initial Rain Event Action Plan (REAP) must be included in the SWPPP. The SWPPP shall be signed by the QSD and shall be submitted electronically, and in paper, no later than 30 days after receiving Contract Award. The SWPPP must be submitted and approved before construction can commence.

SD-06 Test Reports

SWPPP Amendments; G, DO

Amend the SWPPP as needed to be in compliance with these specifications and the CSWRCB GO 2009-0009-DWQ requirements.

SWPPP amendments include, but are not limited to: inspection and maintenance sheets, BMP design changes/updates (any changes to the SWPPP or BMP implementation or design need to be approved and signed off by the Qualified SWPPP Developer), and any change of authorization as described in paragraph "SWPPP And Amendments."

Submit all amendments in both electronic and paper forms, and included in the SWPPP.

Sampling Results; G, DO

At a minimum, collect three samples per day for each qualifying rain event, as described in paragraphs "Sampling And Analysis Plan Design" and "Sampling And Analysis Plan For Non-Storm Water Discharge." Submit all sampling results in both electronic and paper forms, and include in the SWPPP.

Exceedance Reports;

In the event that any effluent sample exceeds an applicable Numeric Action Level (NAL) or Numeric Effluent Limitation (NEL), submit the sampling results in both electronic and paper form no later than 1 business day after the conclusion of the storm event. Also electronically submit the sampling results to the SWRCB in SMARTS as described in paragraph "Permit Registration Documents" no later than 10 days after the conclusion of the storm event. In the event of an effluent exceedance of an applicable NAL or NEL, adhere to paragraphs governing exceedance reports in the General Permit.

Annual Reports; G, DO

Prepare and submit Annual reports in both electronic and paper form no later than August 15 of each year. Electronically submit Annual reports to the SWRCB in SMARTS as described in paragraph "Permit Registration Documents" no later than September 1 of each year. Compliance with the Annual Report guidelines found in Section XVI. Annual Reporting Requirements within the CSWRCB GO 2009-0009-DWQ Order is mandatory.

SD-07 Certificates

01 57 23.00 41- 4 AM-01

Mill Certificate or Affidavit

Certificate attesting that the Contractor has met all specified requirements.

SD-11 Closeout Submittals

Final Storm Water Pollution Prevention Plan (SWPPP); G, DO

Submit records of all storm water monitoring information in the final SWPPP as described in paragraph MOBILIZATION AND

DEMOBILIZATION.

1.2.1 Required Submittal Meetings

A coordination meeting shall be conducted upon Contract Award at the USACE Monterey Office. At a minimum, the Contractor's Project Manager, or appropriate technical person, the Qualified SWPPP Practitioner (QSP) and the Qualified SWPPP Developer (QSD) are required to be present. (See paragraph titled TRAINING REQUIREMENTS for position details.) The purpose of this meeting will be to discuss the roles and responsibilities of the Contractor, the LRP, and USACE for permit compliance.

The Certified Storm Water Pollution Prevention Plan (SWPPP) submittal shall also require a meeting to be held approximately 5 days after the government has received the submittal. This meeting shall be an on-board review in which the Government provides their comments regarding the Contractor's SWPPP submittal, and a discussion to clarify the approval requirements.

This meeting is mandatory in order to approve the SWPPP submittal. See paragraph 1.4.2 SWPPP DEVELOPMENT for further details. Upon approval the Contractor will be responsible for electronically filing the SWPPP submittal into SMARTS as detailed in paragraph 1.4.7 PERMIT REGISTRATION DOCUMENTS (PRDs).

1.3 GENERAL REQUIREMENTS

This specification shall be used in conjunction with SECTION 01 57 20.00 41 ENVIRONMENTAL PROTECTION that addresses the project's environmental requirements and SECTION 32 92 33.00 41 NATIVE PLANT SEEDING AND EROSION CONTROL that addresses the project's permanent BMPs.

This specification was written to ensure that all project activities will be in accordance with The National Pollutant Discharge Elimination System ( NPDES) General Permit No. CAS000002 for Waste Discharge Requirements for Discharge of Storm Water Runoff Associated with Construction and Land Disturbance Activities, CSWRCB GO 2009-0009-DWQ. The General Permit, CSWRCB GO 2009-0009-DWQ, was adopted 2 September 2009, and is effective on 1 July 2010. The Contractor's compliance to this permit and subsequent requirements/updates is mandatory. Any permit noncompliance constitutes a violation of the Clean Water Act and the Porter-Cologne Water Quality Control Act and is grounds for enforcement action and/or removal from General Permit coverage. CSWRCB GO 2009-0009-DWQ, can be found at http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.shtml.

The General Permit, CSWRCB GO 2009-0009-DWQ, does not preempt or supersede the authority of local storm water management agencies to prohibit, restrict, or control storm water discharges to municipal separate storm sewer systems (MS4) or other watercourses within their jurisdictions.

01 57 23.00 41- 5 AM-01

Obtain and include the required local permits and/or agency's approval(s) in the SWPPP.

The General Permit, CSWRCB GO 2009-0009-DWQ, does not authorize discharges of fill or dredged material regulated by the U.S. Army Corps of Engineers under CWA § 404 and does not constitute a waiver of water quality certification under CWA § 401.

A draft copy of the NOI and SWPPP are to be submitted to the Chief of the DPW, Environmental and Natural Resources office for review at: Department of the Army, Environmental and Natural Resources, P.O. Box 5004, Building 4463 Gigling Rd., Monterey, CA 93944-5004.

1.3.1 TRAINING REQUIREMENTS

This contract requires that all personnel responsible for the writing and implementation of the SWPPP are specifically trained in the subject of storm water permitting and erosion and sedimentation controls.

Requirements for training are based on the level of responsibility and must be provided in the SWPPP. Below are the requirements for the position(s) of the Qualified SWPPP Developer (QSD) and the Qualified SWPPP Practitioner (QSP), which must be in place for the entire duration of the project, until meeting the termination requirements as detailed in paragraph "Termination Of SWPPP And CSMP Responsibilities."

1.3.1.1 Qualified SWPPP Developer (QSD)

Ensure that SWPPPs are written, amended and certified by a Qualified SWPPP Developer (QSD). A QSD shall have one of the following registrations or certifications, and appropriate experience, as required for:

a. A California registered professional civil engineer;

b. A California registered professional geologist or engineering geologist;

c. A California registered landscape architect;

d. A professional hydrologist registered through the American Institute of

Hydrology;

e. A Certified Professional in Erosion and Sediment Control (CPESC) (TM) registered through Enviro Cert International, Inc.;

f. A Certified Professional in Storm Water Quality (CPSWQ) (TM) registered through Enviro Cert International, Inc.; or

g. A professional in erosion and sediment control registered through the

National Institute for Certification in Engineering Technologies

(NICET);

The QSD shall also attend a State Water Board-sponsored or approved QSD training course and provide the training certificate in the SWPPP. Check both the SWRCB and CASQA websites for a list of the approved QSD trainings.

The Contractor is responsible for completing the course before developing the SWPPP, or as soon as the applicable training is available.

Ensure the QSD has a minimum of five years experience in developing SWPPPs for construction sites in compliance with NPDES permits. Documentation of past projects shall be delivered upon request.

1.3.1.2 Qualified SWPPP Practitioner (QSP)

Ensure that all BMPs required by this General Permit are implemented by a Qualified SWPPP Practitioner (QSP). A QSP is a person responsible for nonstorm water and storm water visual observations, sampling and analysis.

01 57 23.00 41- 6 AM-01

A QSP shall be either a QSD or have one of the following certifications:

a. A certified erosion, sediment and storm water inspector registered through Enviro Cert International, Inc.; or

b. A certified inspector of sediment and erosion control registered through Certified Inspector of Sediment and Erosion Control, Inc.

The QSP shall also attend a State Water Board-sponsored or approved QSP training course and provide the training certificate in the SWPPP. Check both the SWRCB and CASQA websites for a list of the approved QSP trainings.

Complete the course before construction commences, or as soon as the applicable training is available.

1.3.2 Additional Requirements

CSWRCB GO 2009-0009-DWQ establishes three levels of risk possible for a construction site. This project site's sediment and receiving water risk falls under Risk Level 2 requirements. The Contractor is responsible for meeting all Risk Level 2 requirements detailed in CSWRCB GO 2009-0009-DWQ to be in compliance. Attachment C of the General Permit details additional Risk Level 2 requirements. When Risk Level 2 requirements conflict with requirements within this specification, the more stringent requirement shall be followed.

Rain events can occur at any time of the year in California, therefore a REAP is necessary to ensure the construction site has adequate erosion and sediment controls implemented prior to the onset of a storm event, even in the dry season. Specific REAP requirements are detailed in paragraph "Rain Event Action Plans (REAPs)." An initial REAP shall be included in the SWPPP submittal for government approval.

1.4 DEVELOPMENT AND DESIGN

1.4.1 SWPPP Development

The Certified Storm Water Pollution Prevention Plan (SWPPP) is a requirement of the CSWRCB GO 2009-0009-DWQ permit and compliance is mandatory. The QSD shall create an applicable SWPPP for the project.

Guidance for creating a SWPPP can be found at the State Water Resources Control Board website http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.shtml and at the California Stormwater Quality Association website http://www.cabmphandbooks.com. The SWPPP must include a CSMP and SAP. Once the SWPPP has been completed, submit it to USACE for government approval no later than 30 days upon receiving the Contract Award. Government approval will be based on the document meeting these specifications, and the CSWRCB GO 2009-0009-DWQ permit and CASQA CABMPHB requirements.

After government approval, the SWPPP will be submitted to the State Water Resource Control Board (SWRCB) by the government LRP. The Contractor shall serve in the role as Data Submitter and be responsible for providing a suitable electronic formatted copy of the approved document and uploading documents and other required data to the SWRCB's Storm water Multi-application and Report Tracking System (SMARTS), as detailed in paragraph Permit Registration Documents.

The SWPPP shall include a narrative section as well as figures in the Water Pollution Control Drawings (WPCDs). At a minimum, the WPCDs shall include

01 57 23.00 41- 7 AM-01

BMPs, discharge points, sampling collection points, drainage patterns across the project area, storm drain inlets and temporary concentrated flow drainage patterns.

1.4.1.1 Construction Site Management Plan (CSMP)

Develop a written site-specific CSMP in accordance with the Risk Level 2 requirements in the General Permit, CSWRCB GO 2009-0009-DWQ. The CSMP shall include all monitoring procedures and instructions, location maps, forms, and checklists as required to be in compliance. The CSMP shall be developed prior to the commencement of construction activities, and revised as necessary to reflect project revisions. The CSMP shall be a part of the SWPPP, included as an appendix or separate chapter.

The CSMP shall be developed and implemented to address the following objectives:

a. To demonstrate that the site is in compliance with the Discharge Prohibitions and applicable Numeric Action Levels (NALs) of the

CSWRCB GO 2009-0009-DWQ;

b. To determine whether non-visible pollutants are present at the construction site and are causing or contributing to exceedance of water quality objectives;

c. To determine whether immediate corrective actions, additional Best Management Practice (BMP) implementation, or SWPPP revisions are necessary to reduce pollutants in storm water discharges and authorized non-storm water discharges; and

d. To determine whether BMPs included in the SWPPP/REAP are effective in preventing or reducing pollutants in storm water discharges and authorized non-storm water discharges.

The CSMP shall include a description of the following items:

a. Visual observation locations, visual observation procedures, and visual observation follow-up and tracking procedures;

b. Sampling locations, and sample collection and handling procedures.

This shall include detailed procedures for sample collection, storage, preservation, and shipping to the testing lab to assure that consistent quality control and quality assurance is maintained. Attach an example Chain of Custody form used when handling and shipping samples to the monitoring program; and

c. Identification of the analytical methods and related method detection limits (if applicable) for each required parameter.

1.4.1.2 Sampling And Analysis Plan (SAP) Design

Develop a written site-specific SAP, as part of the CSMP, in the SWPPP to monitor the effectiveness of the water pollution control practices, to be in compliance with the CSWRCB GO 2009-0009-DWQ.

Designate trained personnel to collect water quality samples. The personnel and training shall be documented in the SAP. Training shall consist of the following elements:

01 57 23.00 41- 8 AM-01

a. SAP review,

b. Health and safety review, and

c. Sampling simulations.

At a minimum, the SAP shall describe the following water quality sampling procedures:

a. Sampling preparation,

b. Collection,

c. Quality assurance and quality control,

d. Sample labeling,

e. Collection documentation,

f. Sample shipping,

g. Chain of custody,

h. Sample numbering, and

i. Precautions from the construction site health and safety plan.

Stormwater grab samples shall be collected a minimum of three (3) times per day for each qualifying rain events (producing precipitation of 1/2 inch or more at the time of discharge). The storm water grab samples shall be representative of the flow and characteristics of the discharge. The effluent samples shall be analyzed for pH and turbidity. Refer to the table below for the required test methods, detection limits, and reporting units for the effluent testing, to be in compliance with the CSWRCB GO 2009-0009-DWQ Risk Level 2 requirements:

EFFLUENT MONITORING

Parameter Test Method/ Protocol

Units Minimum Detection

Limit

Numeric Action Level (NAL) pH Field test with calibrated portable instrument units 0.2 lower NAL = 6.5 upper NAL = 8.5

Turbidity EPA 0180.1 and/or field test with calibrated portable instrument

NTU 1 250

In the SAP, identify the locations where runoff sources on the construction

01 57 23.00 41- 9 AM-01

site discharge directly into the listed body of water. Also, identify the locations where water flows onto the project with the potential to combine with runoff that discharges directly into the listed body of water. These locations shall also be shown on the WPCDs.

Identify locations for sampling and analysis of storm water discharges to characterize discharges associated with construction activity from the entire project disturbed area and the reason for their selection. Sampling locations shall also be shown on the WPCDs. The sampling locations shall include:

a. Upstream/up-gradient from direct discharges from the construction site from a representative and accessible location as close as possible and upstream from the effluent discharge point;

b. Immediately downstream/down-gradient from the last point of direct discharge from the construction site from a representative and accessible location as close as possible and downstream from the effluent discharge point;

c. Immediately downhill from the locations where water flows onto into the water body.

d. If storm water is to be discharged into a lake, the SWRCB shall be contacted to determine lake sampling locations. The QSP shall notify the USACE water quality representative of the SWRCB's recommendations and update the SWPPP appropriately.

This project has the potential to discharge non-visible pollutants in storm water from the construction site. The SAP shall include a description of the sampling and analysis strategy to be implemented on the project for monitoring non-visible pollutants.

Identify potential non-visible pollutants that will be present on the construction site associated with the following:

a. Construction materials and wastes;

b. Existing contamination due to historical site usage; or

c. Application of soil amendments, including soil stabilization products, with the potential to alter pH or contribute toxic pollutants to storm water.

Show the locations planned for storage and use of the potential non-visible pollutants on the WPCDs.

The SAP shall describe the schedule for collecting non-visible pollutant effluent samples. The following list of conditions requires sampling when observed during inspections:

a. Materials or wastes containing potential non-visible pollutants are not stored under watertight conditions.

b. Materials or wastes containing potential non-visible pollutants are stored under watertight conditions, but:

1. A breach, leakage, malfunction, or spill is observed;

01 57 23.00 41- 10 AM-01

2. The leak or spill has not been cleaned up before precipitation; and

3. There is the potential for discharge of non-visible pollutants to surface waters or drainage system.

c. Construction activities; such as application of fertilizer, pesticide, herbicide, methyl methacrylate concrete sealant, or non-pigmented curing compound; have occurred during precipitation or within 24 hours preceding precipitation, and have the potential to discharge pollutants to surface waters or drainage system.

d. Soil amendments, including soil stabilization products, with the potential to alter pH levels or contribute toxic pollutants to storm water runoff have been applied, and have the potential to discharge pollutants to surface waters or drainage system (unless independent test data are available that demonstrate acceptable concentrations of non-visible pollutants in the soil amendment).

e. Storm water runoff from an area contaminated by historical usage of the site has the potential to discharge pollutants to surface waters or drainage system.

Identify sampling locations for collecting downstream and control samples, and the reason for their selection. The control sampling location shall be selected so the sample does not come into contact with materials, wastes or areas associated with potential non-visible pollutants or disturbed soil areas. Show non-visible pollutant sampling locations on the WPCDs.

Identify in the SAP the analytical method to be used for downhill and control samples for potential non-visible pollutants on the project.

Samples to be analyzed by a laboratory shall be sampled, preserved, and analyzed by a State-certified laboratory in conformance with the requirements in 40 CFR 136, "Guidelines Establishing Test Procedures for the Analysis of Pollutants." Identify the laboratory, sample containers, preservation requirements, holding times, and analysis method in the SAP.

Ensure that the analyzing laboratories will receive samples within 48 hours of the physical sampling (unless otherwise required by the laboratory), and shall use only the sample containers provided by the laboratory to collect and store samples. Submit a hard copy and electronic copy of water quality analytical results, and quality assurance and quality control data to the USACE water quality representative within 5 days of sampling for field analyses. Also provide an evaluation of whether the downhill or downstream samples show levels of the tested parameter higher than in the control sample. If downhill or downstream samples show increased levels, the Contractor will assess the water pollution control measures, site conditions, and surrounding influences to determine the probable cause for the increase. As determined by the assessment, the Contractor will repair or modify water pollution control measures to address increases and amend the SWPPP as necessary. Electronic results (in one of the following file formats: .xls, .txt) shall have the following information:

a. Sample identification number.

b. Contract number.

c. Constituent.

d. Reported value.

01 57 23.00 41- 11 AM-01

e. Analytical method.

f. Method detection limit.

g. Reported limit.

Maintain the water quality sampling documentation and analytical results with the SWPPP on the project site and in accordance with CSWRCB GO 2009-0009-DWQ, ATTACHMENT D, 14. Risk Level 2 -- Records. If construction activities or knowledge of site conditions change such that discharges or sampling locations change, amend the CSMP as necessary.

1.4.1.3 Best Management Practices (BMPs)

The QSD shall select BMPs to include in the SWPPP. The selection and implementation of BMPs is based on the pollution risks associated with the construction activity and shall be fully compliant with CSWRCB GO 2009-0009-DWQ, ATTACHEMENT D, RISK LEVEL 2 REQUIREMENTS. The BMP's installation and maintenance schedule and on-site location shall be included in the SWPPP. The SWPPP shall include the following water pollution control practices as needed for compliance with

CSWRCB GO 2009-0009-DWQ:

Erosion Control Sediment Control Wind Erosion Control Tracking Control Non-Storm Water Management Waste Management and Materials Pollution Control Active Treatment System Plan (if needed)

Erosion control practices are the primary means of preventing storm water contamination and shall be implemented for all disturbed soil on the project site. Select a variety of erosion control measures to protect the soil surface and prevent soil particles from being detached by rainfall, flowing water, or wind. Consider covering disturbed area with mulch, temporary seeding, soil stabilizers and binders, and installing fiber rolls or blankets, temporary vegetation, and permanent seeding. The minimum erosion control BMPs required shall include, but are not limited to:

scheduling, preservation of existing vegetation, and a combination of at least two or more of the following: Hydraulic Mulch, Hydroseeding, Soil Binders, Straw Much, or Geotextiles and Mats, as required to meet the CSWRCB GO 2009-0009-DWQ requirements. Installation, maintenance and inspection details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph Erosion Control BMPs.

Sediment Control BMPs are the secondary means of preventing storm water contamination. When erosion control techniques are ineffective, sediment control techniques shall be used to capture any soil that becomes eroded.

These practices shall be implemented to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Effective perimeter controls shall be established; consider installing silt fences or placing straw wattles below slopes. The minimum required sediment control BMPs shall include, but are not limited to: silt fences, fiber rolls, street sweeping and vacuuming, and storm drain inlet protection to ensure permit compliance. Installation, maintenance and inspection details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph

01 57 23.00 41- 12 AM-01

Sediment Control BMPs.

The Wind Erosion Control BMP is the primary means of preventing or alleviating dust generated by construction activities. The Wind Erosion Control BMP shall be included in the SWPPP, BMP details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph Wind Erosion Control.

Tracking Control BMPs prevent or reduce the tracking of sediment off-site by vehicles leaving the construction area. Attention to control tracking of sediment off-site is essential. At a minimum the Stabilized Construction Entrance/Exit BMPs shall be listed in the SWPPP as tracking control.

Installation, maintenance, and inspection details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph Tracking Control BMPs.

Non-storm water management and material management BMPs are source control BMPs that prevent pollution by limiting or reducing potential pollutants at their source before they come in contact with storm water. The discharge of materials other than storm water and authorized non-storm water discharges is prohibited. Certain authorized non-storm water discharges may be necessary for the completion of construction activities. The following required non-storm water BMPs shall be included in the SWPPP:

illicit connection/discharge, vehicle and equipment cleaning, vehicle and equipment fueling, and vehicle and equipment maintenance. Installation, maintenance, and inspection details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph Non-Storm Water Management BMPS. The following required waste management and materials pollution control BMPs shall be included in the SWPPP: material delivery and storage, material use, stockpile management, spill prevention and control, and sanitary/septic management. Installation, maintenance, and inspection details are listed in the appropriate CASQA CABMPHB BMP fact sheet as defined in paragraph Waste Management And Materials Pollution Control BMPS.

BMP fact sheets can be found at the CASQA website and shall be included as an appendix of the SWPPP. A BMP fact sheet is a short document that gives all the information about a particular BMP. Typically, each fact sheet design contains the following information: description and purpose, suitable application, limitations, implementation, costs, inspection and maintenance, and references. BMPs must be implemented, maintained, and inspected in accordance with the fact sheets and the CSWRCB GO 2009-0009-DWQ requirements.

Each BMP shall be documented in the SWPPP in both a narrative section and figures in the WPCDs. The SWPPP must indicate all BMPs to be implemented, where they will be located, and when they will be installed on the WPCDs.

In cases where information about BMP installation, implementation, and management are not available on the CASQA website or in CSWRCB GO 2009-0009-DWQ, the BMP specifications and manufacture instructions must be supplied in the SWPPP, or in a SWPPP amendment, for prior government approval.

The SWPPP shall include a discussion of the inspection and maintenance program for all BMPs as identified to be utilized throughout the entire duration of the project. A qualified person (QSP, or persons appropriately trained by the QSP) will be assigned the responsibility to conduct inspections. The name and telephone number of that person shall be listed in the SWPPP document.

01 57 23.00 41- 13 AM-01

Select temporary stabilization methods with a minimum longevity period to meet the duration of the project. The BMPs with long longevity will improve relative effectiveness. The guidelines for required longevity for temporary stabilization methods are detailed in Appendix F of the CASQA CABMPHB. Additionally, temporary stabilization methods shall be selected which are habitat sensitive, including, but not limited to:

biodegradable or photodegradable materials and materials compatible with existing vegetation.

1.4.2 Permit Registration Documents (PRDs)

An additional part of the compliance requirement includes electronic filing of Permit Registration Documents (PRDs) to the SWRCB's Storm water Multi-application and Report Tracking System (SMARTS). The Contractor will likely be assigned the role of "Data Submitter" in SMARTS, which includes entering (in suitable eletronic format) the following PRDs in SMARTS:

a. Site Map,

b. Storm Water Pollution Prevention Plan (SWPPP),

c. Signed Certification Statement,

d. ATS Plan including training certifications (if needed)

e. Annual Reports

Follow the submittal schedule and submit all PRDs within the SWPPP for government approval. Government approval of the PRDs must be obtained prior to filing any PRDs in electronic form to SMARTS. If any of the required items are missing (per Attachment B in the CSWRCB GO 2009-0009-DWQ requirements) the PRD submittal is considered incomplete and will be rejected. The government shall be responsible for the following PRDs:

Notice of Intent (NOI), Risk Assessment, Bioassessment (if needed), and Annual Fee. All PRDs must be completed and properly electronically filed by the LRP in order to obtain a Waste Discharge Identification (WDID) number from SMARTS. The WDID number shall be obtained from SMARTS and included it in the SWPPP prior to construction commencement.

Annual Reports shall be submitted in both electronic and paper form to the government for information only no later than August 1st of each year, and electronically submitted to the SWRCB in SMARTS no later than Semptember 1 of each year. Each annual report shall be in accordance with the special provisions within the CSWRCB GO 2009-0009-DWQ requirements. Each annual report shall provide training information documenting all training for:

individuals responsible for any activity associated with compliance with the CSWRCB GO 2009-0009-DWQ requirements; individuals responsible for BMP installation, inspection, maintenance and repair; and individuals responsible for overseeing, revising, and amending the SWPPP. Each annual report shall consist of, but is not limited to, the following:

a. a summary and evaluation of all sampling and analysis results, including copies of laboratory reports;

b. the analytical method(s), method reporting unit(s), and method detection limit(s) of each analytical parameter (analytical results that are less than the method detection limit shall be reported as "less than the method detection limit");

01 57 23.00 41- 14 AM-01

c. a summary of all corrective actions taken during the compliance year;

d. identification of any compliance activities or corrective actions that were not implemented;

e. a summary of all violations of the General Permit, CSWRCB GO 2009-0009-DWQ;

f. the names of individual(s) who performed the facility inspections, sampling, visual observation (inspections), and/or measurements;

g. the date, place, time of facility inspections, sampling, visual observation (inspections), and/or measurements, including precipitation (rain gauge); and

h. the visual observation and sample collection exception records and reports specified in Attachments C: Risk Level 2 Requirements.

The Contractor shall be responsible for the electronic filing of all storm event sampling results, and NAL exceedance reports (see paragraph NAL Exceedance Report). NAL Exceedance Reports shall be submitted to the USACE representative within the timeframe specified for review and feedback prior to electronically filing in SMARTS. If the contractor has not received a government response by the time the exceedance reports are required to be submitted in SMARTS, the intent of the permit shall be followed and the contractor shall not wait for government approval to file in SMARTS. NAL exceedance reports must be submitted to the USACE representative no later than 1 business day after the conclusion of the storm event, and electronically filed in SMARTS no later than 10 days after the conclusion of the storm event.

PART 2 PRODUCTS

Temporary storm water pollution control products include the site's SWPPPs (general and temporary batch plant specific). Each SWPPP shall include a CSMP, SAP, and specific BMPs. SWPPP, CSMP, and SAP development details are provided in Part 1 of these specifications. This section defined which BMPs are required to be utilized and included in the SWPPP, as well as a list of additional BMPs which are available for use. All BMPs shall follow their specified CASQA CABMPHB BMP fact sheet except where more stringent requirements are stated in these specifications or in the BMPs' manufacturer's recommendations. Additional design requirements for particular BMPs are stated in Part 1: GENERAL of this specification, which shall be adhered to. Additional mobilization/demobilization, maintenance, and inspection requirements are stated in Part 3: EXECUTION of this specification, which shall be adhered to.

2.1 REQUIRED BEST MANAGEMENT PRACTICES

2.1.1 Erosion Control BMPs

Install and maintain all of the following required erosion control BMPs. A combination of two or more of the following five erosion control BMPs shall be used for soil protection in each area: hydraulic mulch, hydroseeding, soil binders, straw mulch, or geotextile and mats. Follow the additional recommendations as provided in Section 32 92 33.00 41 NATIVE PLANT SEEDING AND EROSION CONTROL to be in compliance for seeding or other permanent BMPs. Choose the following BMPs with minimum longevity to meet the

01 57 23.00 41- 15 AM-01

duration of the project, and those which offer habitat sensitive, weed free, biodegradable or photodegradable features, when allowed by site conditions.

2.1.1.1 SCHEDULING

Utilize scheduling as an erosion control BMP in accordance with the CASQA CABMPHB "Scheduling, EC-1" fact sheet. The Scheduling BMP involves developing a schedule that includes sequencing construction activities with the implementation of construction site BMPs. The purpose is to reduce the amount and duration of soil exposed to erosion by wind, rain, runoff and vehicle tracking, and to perform the construction activities and control practices in accordance with the planned schedule. Schedule work to eliminate soil disturbance activities during rain events. If work is to be done when rainfall is predicted, adjust the construction schedule to allow the implementation of erosion and sedimentation controls on all disturbed area prior to rainfall.

2.1.1.2 PRESERVATION OF EXISTING VEGETATION

Utilize this BMP as an erosion control BMP in accordance with the CASQA CABMPHB "Preservation of Existing Vegetation, EC-2" fact sheet.

Preservation of existing vegetation consists of identifying and protecting of desirable vegetation that provides erosion and sedimentation control benefits. Temporary fencing shall be provided prior to the commencement of soil disturbing activities to protect existing vegetation, especially on areas designated as Environmentally Sensitive Areas (ESAs) as described in Section 01 57 20.00 41 ENVIRONMENTAL PROTECTION.

2.1.1.3 HYDRAULIC MULCH

Hydraulic Mulch consists of applying a mixture of shredded wood fiber or a hydraulic matrix and a stabilizing emulsion or tackifier with hydroseeding equipment, which temporarily protects exposed soil from erosion by raindrop impact or wind. This BMP shall be utilized to meet the CASQA CABMPHB "Hydraulic Mulch, EC-3" fact sheet standards.

2.1.1.4 HYDROSEEDIMG

Hydroseeding typically consists of applying a mixture of wood fiber, seed, fertilizer, and stabilizing emulsion with hydro-mulch equipment, which temporarily protects exposed soils from erosion by water or wind.

Hydroseeding requires sufficient time in the season to ensure adequate vegetation establishment and erosion control prior to rainfall. This BMP shall be utilized to meet the CASQA CABMPHB "Hydroseeding, EC-4" fact sheet standards.

2.1.1.5 SOIL BINDERS

Soil Binders consist of applying and maintaining soils stabilizers to exposed soil surfaces. Soil binders are materials applied to the soil surface to temporarily protect soil from erosion by water. Soil binders also provide temporary dust, wind and erosion control benefits. Soil binder types and application rates are detailed in the CASQA CABMPHB fact sheet. This BMP shall be utilized to meet the CASQA CABMPHB "Soil Binders, EC-5" fact sheet standards.

01 57 23.00 41- 16 AM-01

2.1.1.6 STRAW MULCH

Straw mulch consists of placing a uniform layer of straw and incorporating it into the soil with a studded roller or anchoring it with a stabilizing emulsion. This BMP shall be utilized to meet the CASQA CABMPHB "Straw Mulch, EC-6" fact sheet standards.

2.1.1.7 GEOTEXTILES AND MATS

This BMP involves the placement of geotextiles, mats, plastic covers, or erosion control blankets to stabilize disturbed soil area and protect soils from erosion by wind or water. Material selection, site preparation, seeding, anchoring, and installation requirements are detailed in the CASQA CABMPHB fact sheet. This BMP shall be utilized to meet the CASQA CABMPHB "Geotextiles and Mats, EC-7" fact sheet standards.

2.1.2 Sediment Control BMPs

Install and maintain the following sediment control BMPs.

2.1.2.1 SILT FENCE

Install and maintain silt fences as a sediment control BMP in accordance with the CASQA CABMPHB "Silt Fence, SE-1" fact sheet. Secondary to fiber rolls, silt fences are temporary linear sediment barriers of permeable fabric designed to intercept and slow the flow of sediment-laden sheet flow runoff. Silt fences allow sediment to settle from runoff before water leaves the construction site. Silt fences must be properly trenched and keyed in for full effectiveness. Design and layout, materials and installation requirements are detailed in the CASQA CABMPHB fact sheets, which must be adhered to.

2.1.2.1.1 SEDIMENT BASIN

Install and maintain sediment basins as a sediment control BMP in accordance with the CASQA CABMPHB "Sediment Basin, SE-2" fact sheet.

Sediment basins, at a minimum, shall be used where sediment-laden water may enter the drainage system or watercourse. They shall be used in association with dikes, temporary channels, and pipes used to convey runoff from disturbed areas. Use sediment basins in conjunction with erosion control practices to reduce the amount of sediment flowing into the basin.

The QSP shall inspect the sediment basin prior to any likely forecasted rain event (as defined in the paragraph titled "Rain Event Action Plans (REAPs)"), daily during rain events, after rain events, and a minimum of once per week when a rain event is not likely. Accumulated sediment must be periodically removed in order to maintain BMP effectiveness. The QSP shall ensure the sediment is removed when sediment accumulation reaches one-half the designated sediment storage volume. The QSP shall ensure all standing storm water from the basins is removed within 72 hours after accumulation.

2.1.2.2 FIBER ROLLS

Install and maintain fiber rolls as a sediment control BMP in accordance with the CASQA CABMPHB "Fiber Rolls, SE-5" fact sheet. Preferred over silt fences, fiber rolls (or straw wattles) consists of straw, flax, or other similar materials bound into a tight tubular roll. Straw fill material shall be from locally grown (California) rice, certified weed free. Use fiber rolls containing biodegradable materials with natural jute casing

01 57 23.00 41- 17 AM-01

/netting. Fiber rolls must be properly trenched and staked for full effectiveness. When fiber rolls are placed at the toe and on the face of slopes, they intercept runoff, reduce its flow velocity, release the runoff as sheet flow, and provide removal of sediment from the runoff. By interrupting the length of a slope, fiber rolls can also reduce erosion.

Fiber rolls may also be used for inlet protection and as check dams under certain situations. When installing on a slope, the slope inclination controls the required spacing as detailed in the CASQA CABMPHB fact sheet, and the Risk Level 2 requirements in the General Permit (see paragraph MAINTENANCE, MONITORING AND INSPECTIONS), both of which must be adhered to.

2.1.2.3 STREET SWEEPING AND VACUUMING

Utilize this BMP as a sediment control BMP in accordance with the CASQA CABMPHB "Street Sweeping and Vacuuming, SE-7" fact sheet. This BMP consists of removing tracked sediment to prevent the sediment from entering a storm drain or watercourse. It is to be implemented anywhere sediment is tracked from the project site onto public or private paved roads, especially at points of ingress/egress. Self-propelled or walk-behind equipment shall be used to remove sediment and clean paved areas. Kick brooms or sweeper attachments shall not be allowed. Visible sediment tracking shall be swept and/or vacuumed in such a manner as to eliminate unauthorized non-storm water discharge from reaching surface water or drainage systems. When tracked or spilled sediment is observed outside the construction limits, it must be removed immediately; continuous removal may be required. A mechanical street sweeper shall be kept onsite and available at all times the contractor is on site. If sediment is wet or when tracked soil is caked, the soil shall be scraped loose. The discharge of any debris (litter, rubble, discarded refuse, and remains of destroyed inorganic anthropogenic waste) is prohibited. After sweeping is finished, properly dispose of sweeper wastes at an approved dumpsite.

2.1.2.4 STORM DRAIN INLET PROTECTION

Install and maintain this BMP as a sediment control BMP in accordance with the CASQA CABMPHB "Storm Drain Inlet Protection, SE-10" fact sheet. Every storm drain inlet potentially receiving sediment-laden runoff from any construction related areas must be protected against permitting the transmission of turbid waters. Storm drain inlet protection consists of a sediment filter or an impounding area around or upstream of a storm drain, drop inlet, or curb inlet. Storm drain inlet protection measures temporarily pond runoff before it enters the storm drain, allowing sediment to settle. One of the three following types of storm drain inlet protection devices shall be chosen by the contractor based on site conditions and specified in the SWPPP detailing maintenance and installation, and locations shown on the WPCDs:

a. Excavated Drop Inlet Sediment Trap: An excavated area around the inlet to trap sediment.

b. Gravel bag barrier: Used to create small sediment trap upstream of inlets on sloped paved streets. Appropriate for sheet flow or when concentrated flow may exceed 0.5 cfs, and where overtopping is required to prevent flooding.

c. Block and Gravel Filter: Appropriate for flows greater than 0.5 cfs.

01 57 23.00 41- 18 AM-01

2.1.3 Wind Erosion Control BMP

The wind erosion control BMP shall be utilized as a minimum BMP requirement. Utilize the wind erosion control BMP in accordance with the CASQA CABMPHB "Wind Erosion Control, WE-1" fact sheet. Wind erosion control consists of applying water or other dust palliatives as necessary to prevent or alleviate dust nuisance. Provide covers for haul trucks transporting materials. It is the Contractor's responsibility to provide rapid clean up of sediments deposited on paved roads.

2.1.4 Tracking Control BMPs

Tracking control BMPs consists of preventing or reducing vehicle tracking from entering a storm drain or watercourse. Tracking control BMPs include:

stabilized construction entrance/exit, stabilized construction roadway, and entrance/outlet tire wash. Utilize these BMPS to preclude dirt or mud from being tracked onto public roads or to adjacent water bodies. Tracking Control BMPs shall be utilized in accordance with the CASQA CABMPHB Tracking Control, TC-1 through TC-3, fact sheets, as detailed below.

2.1.4.1 STABILIZED CONSTRUCTION ENTRANCE/EXIT

Utilize this BMP in accordance with the CASQA CABMPHB "Stabilized Construction Entrance/Exit, TC-1" fact sheet. This BMP is defined by a point of entrance/exit to a construction site that is stabilized to reduce the tracking of mud and dirt onto public roads by construction vehicles.

Design the stabilized entrance/exit to support the heaviest vehicles and equipment that will use it. Use of constructed/manufactured steel plates with ribs must be detailed in the SWPPP for approval. If the aggregate method is selected, it must follow the size and depth as detailed in the fact sheet and shall be detailed in the SWPPP for approval.

2.1.5 Non-Stormwater Management BMPs

Non-storm water management BMPs are source control BMPs that prevent pollution by limiting or reducing potential pollutants at their source before they come in contact with storm water. These BMPs are also referred to as "good housekeeping practices" which involve keeping a clean, orderly construction site. The discharge of any debris (litter, rubble, discarded refuse, and remains of destroyed inorganic anthropogenic waste) is prohibited.

2.1.5.1 ILLICIT CONNECTION/ILLEGAL DISCHARGE DETECTION AND REPORTING

Utilize this BMP in accordance with the CASQA CABMPHB "Illicit Connection/Discharge, NS-6" fact sheet. This BMP consists of procedures and practices designed to recognize illicit connections or illegally dumped or discharged materials on a construction site. Illicit connection/illegal discharge detection and reporting is applicable anytime an illicit connection or discharge is discovered or illegally dumped material is found on the construction site. Notify the Resident Engineer of any illicit connections and illegal dumping or discharge incidents at the time of discovery. The Resident Engineer will notify the appropriate organizations for reporting.

2.1.5.2 VEHICLE AND EQUIPMENT CLEANING

Utilize this BMP in accordance with the CASQA CABMPHB "Vehicle and Equipment Cleaning, NS-8" fact sheet. Vehicle and equipment cleaning

01 57 23.00 41- 19 AM-01

procedures and practices are used to minimize or eliminate the discharge of pollutants from vehicle and equipment cleaning operations to storm drain systems or to watercourses.