Amendment 6 - W91238-10-R-0026

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY11 General Instruction Building, Presidio of Monterey, California

The purpose of this amendment is to:

1. Revise the specifications and draw ings.

The proposal due date has been extended to Wednesday, 8 December 2010 at 3 pm Pacific Daylight Time (PDT).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Nov-2010

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-10-R-0026

X 9B. DATED (SEE ITEM 11)

07-Oct-2010

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Nov-2010

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET-ROOM 878

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91238-10-R-0026

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 01-Dec-2010 03:00 PM to 08-Dec-2010 03:00 PM.

TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications 2102 07-OCT-2010 Attachment 2 Drawings - Volume 1 of 7 17 30-SEP-2010 Attachment 3 Drawings - Volume 2 of 7 49 30-SEP-2010 Attachment 4 Drawings - Volume 3 of 7 64 30-SEP-2010 Attachment 5 Drawings - Volume 4 of 7 62 30-SEP-2010 Attachment 6 Drawings - Volume 5 of 7 58 30-SEP-2010 Attachment 7 Drawings - Volume 6 of 7 101 30-SEP-2010 Attachment 8 Drawings - Volume 7 of 7 49 30-SEP-2010 Attachment 9 Davis Bacon Wage

Determination

52 10-SEP-2010

Attachment 10 Specifications - Amendment 1

175 21-OCT-2010

Attachment 11 Drawings - Amendment 1 55 21-OCT-2010 Attachment 12 Drawings, Specification -

Amendment 2

6 29-OCT-2010

Attachment 13 Davis-Bacon Wage Determination - 29 Oct

52 29-OCT-2010

Attachment 14 Specs, Drawings - Amendment 5

38 10-NOV-2010

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications 2102 07-OCT-2010 Attachment 2 Drawings - Volume 1 of 7 17 30-SEP-2010 Attachment 3 Drawings - Volume 2 of 7 49 30-SEP-2010 Attachment 4 Drawings - Volume 3 of 7 64 30-SEP-2010 Attachment 5 Drawings - Volume 4 of 7 62 30-SEP-2010 Attachment 6 Drawings - Volume 5 of 7 58 30-SEP-2010 Attachment 7 Drawings - Volume 6 of 7 101 30-SEP-2010 Attachment 8 Drawings - Volume 7 of 7 49 30-SEP-2010 Attachment 9 Davis Bacon Wage

Determination

52 10-SEP-2010

Attachment 10 Specifications - Amendment 1

175 21-OCT-2010

Attachment 11 Drawings - Amendment 1 55 21-OCT-2010 Attachment 12 Drawings, Specification -

Amendment 2

6 29-OCT-2010

Attachment 13 Davis-Bacon Wage Determination - 29 Oct

52 29-OCT-2010

Attachment 14 Specs, Drawings - Amendment 5

38 10-NOV-2010

Attachment 15 Specification - Amendment 6

9 23-NOV-2010

Attachment 16 Drawings - Amendment 6 31 23-NOV-2010

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

SECTION 00100 LOCAL PROVISIONS

SECTION 00100

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

AND EVALUATION CRITERIA FOR AWARD

The following documents must be returned with your quote, bid, or offer.

--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.

--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.

Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your quote, bid, or offer.

--The completed Pricing Schedule with your proposed contract line item prices inserted in the appropriate spaces. Prices must be proposed for all contract line items and priced sub-line items. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

--Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00600).

--Your Bid Guarantee (e.g., Standard Form 24, “Bid Bond”)

--Any other documents required by the solicitation (see Attachments and/or Section 00111 for competitive RFPs).

INQUIRIES:

Prospective offerors should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fbo.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Number is: W91238-10-R-0026

The Bidder Inquiry Key is: Q4W7YO-O6DCRY

c. The Bidder Inquiry System will be unavailable for new inquiries on 19 November 2010 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Samantha Plank Telephone: (916) 557-5193

E-MAIL:

Samantha.E.Plank@usace.army.mil AND Gregory.L.Tom@usace.army.mil

DIRECTIONS FOR SUBMITTING OFFERS:

Envelopes/packages containing offers must be sealed, marked and addressed as follows:

MARK ENVELOPES/PACKAGES:

Solicitation No.: W91238-10-R-0026

Closing Date: 08 December 2010 Closing Time: 3:00 PM Local Time

ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTION PERTAINING TO HAND-CARRIED OFFERS:

Hand-carried offers must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, Offerors may no longer hand-carry their offers directly to Contracting Division. Offers may NOT be turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no longer public parking in the Building.

The contract specialist will be in the Building Lobby 20 minutes prior to the closing time to accept hand-carried offers. After announcing that no further offers will be received, the contract specialist will have the hand-carried offers x-rayed as a security precaution.

Offerors who desire to hand-deliver their offers at an earlier time must notify the contract specialist in advance in order to arrange to be met in the Building Lobby by Contracting Division personnel. In the event the contract specialist cannot be reached, please call the main Contracting Division telephone number, (916) 557-5201, in order to request assistance.

Please ensure that all courier and delivery personnel are aware of these procedures.

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Section 00111, Preaward Survey). All offerors will complete and return the Preaward Survey as part of the Price/Cost proposal. Failure to submit the Preaward Survey in conjunction with the price proposal will not of itself render the offer unacceptable.

In order to be determined to be responsible a prospective contractor must:

a. Have adequate financial resources to perform the contract or the ability to obtain them.

b. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments.

c. Have a satisfactory performance record. In making the determination of responsibility, the Government Contracting Officer shall consider relevant past performance information. A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history except when there are special standards set forth in the solicitation which applies to all bidders that must be met in order to receive the award. These special standards may be necessary when unusual expertise or specialized facilities are necessary in the performance of the contract; therefore, in order to be determined to be responsible for that particular contract, the offeror must be able to meet those special standards. A prospective contractor that is or recently has been seriously deficient in contract performance shall be presumed to be nonresponsible unless the Contracting Officer determines that the circumstances were beyond the contractor's control or that the contractor has taken appropriate corrective action. Other responsibility considerations by the Contracting Officer will include past efforts by the contractor to apply sufficient tenacity and perseverance to perform acceptably, to meet quality requirements of contracts, and the contractor's past compliance with subcontracting plans (if required) under recent contracts.

d. Have a satisfactory record of integrity and business ethics.

e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).

f. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.

g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in subparagraphs a, e, and f above) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.

The Preaward Survey as a tool used by the Government in determining responsibility of the offeror is submitted as part of the Price/Cost proposal and is separate from the technical proposal's response to the technical evaluation criteria found later in this Section. Some of the information required from the offeror for completion of the Preaward Survey and the technical proposal may be duplicative but it is necessary that the information be provided in full in both places and that the Price/Cost proposal and the Technical proposal be separate documents.

DO NOT state, for example, in the technical proposal, "See Price/Cost proposal for past performance information".

AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

a. The internet URL for Corps of Engineers publications is:

http://140.194.76.129/publications/

b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications.

Information about the CCB can be obtained from:

http://www.wbdg.org/ccb/ccb.php

c. The Corps of Engineers manual, EM 385-1-1, Safety and Health Requirements Manual, is available on the Internet at the following location:

https://kme.usace.army.mil/CoPs/Contracting/USACE%20Safety%20Manual%20%20EM%2038511%202008/For ms/AllItems.aspx or an alternate URL is http://www.usace.army.mil/CESO/Pages/EM385-1-1,2008NEW!.aspx.

TELEGRAPHIC OFFERS:

TELEGRAPHIC OFFERS ARE NOT ACCEPTABLE.

However, offers may be modified or withdrawn by telegraphic notice. Any telegram to modify an offer sent to this office must be received in the office designated in the solicitation for receipt of offers not later than the exact date and time set for receipt of offers. A telegraphic modification of an offer received in such office by telephone from the receiving telegraph office not later than the exact date and time set for receipt of offers shall be considered.

However, the telephone message shall be confirmed by the telegraph company by sending a copy of the written telegram that formed the basis for the telephone call. The written telegram shall be sealed in an envelope by a proper official and sent to the office designated in the solicitation for receipt of offers. The official shall write on the envelope (1) the date and time of receipt and by whom, and (2) the solicitation number, and shall sign the envelope.

The offeror is responsible to inform the telegraph company of these requirements. No one from this office will be dispatched to the local telegraph office to pick up any telegram for any reason. An offer may be withdrawn by telegraphic notice received at any time prior to contract award.

FACSIMILE BIDS/OFFERS:

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

PREPARATION OF SUBCONTRACTING PLAN:

(a) See FAR 52.219-9, Section 00700, of this solicitation. Located in Section 00111 of this solicitation is a sample Subcontracting Plan which will aid the Contractor in preparing a Subcontracting Plan in accordance with FAR 52.219-9(d)(1) through (d)(11). Subcontracting Plans will be developed considering only the subcontracts actually to be awarded. Subcontracting Plans are required from other than small businesses if the contract price is over $1.5 million; they are not required from small business firms regardless of the contract price.

(b) The sample Subcontracting Plan is attached to this solicitation for information purposes. Review of the Subcontracting Plan by the Government will be in accordance with FAR 19.705-4. For Invitation for Bids a Subcontracting Plan will be required only from the low bidder if the low bidder is a large business and the low bid is over $1.5 million. The Subcontracting Plan is not required from the low bidder until after the Bid Opening; it is not required as part of the bid package. After the Bid Opening, if the selected bidder fails to submit an acceptable plan within the time prescribed by the Contracting Officer, the bidder will be ineligible for award. For Request for Proposals, a Subcontracting Plan is required with submission of the price proposal package.

(c) A Subcontracting Plan which proposes goals less than the recommended goals below must contain support, in writing, for the lesser goals and discuss the Contractor's good faith effort to meet the recommended floors.

(d) In accordance with FAR 19.704 if the contract contains options, the cumulative value of the basic contract and all options is considered in determining whether a subcontracting plan is necessary. If a plan is necessary, the subcontracting plan shall contain separate parts, one for the basic contract period and one for each option period. It is necessary to address planned subcontracting dollars and percentages of total to be awarded to small businesses, small disadvantaged businesses, HUBZone small businesses, women-owned small businesses, veteran-owned small businesses, service-disabled veteran- owned small businesses, Hispanic Servicing Institutions and Tribal Council Universities, HBCU/MIs, and qualified nonprofit agencies for the blind and other severely disabled for the basic contract period and each option period. All other parts of the subcontracting plan only need to be addressed once.

(e) Subcontracts awarded to HUBZone small businesses, small disadvantaged businesses, women-owned small businesses, veteran-owned small businesses, service-disabled veteran-owned small businesses, Hispanic Servicing Institutions and Tribal Council Universities, HBCU/MIs, and qualified nonprofit agencies for the blind and other severely disabled count toward the overall small business goal. HBCU/MIs are counted as a subset of the small disadvantaged business goal. The Corps of Engineers has not been assigned separate goals for qualified nonprofit agencies for the blind and other severely disabled, HBCU/MIs, Hispanic Servicing Institutions and Tribal Council Universities, or for HUBZone small business concerns.

(f) Qualified nonprofit agencies for the blind and other severely disabled, that have been approved by the Committee for Purchase from People Who Are Blind or Severely Disabled under the Javits-Wagner-O’Day Act (41 U.S.C. 46-48), are eligible to participate in the program as a result of 10 U.S.C. 2410d and Section 9077 of Pub. L.

102-396 and similar sections in subsequent Defense appropriations acts. Under this authority, subcontracts awarded to such entities may be counted toward the prime contractor’s small business subcontracting goal.

(g) Contact Ms. Michelle Stratton (916)557-7641, Deputy for Small Business, with questions on the Subcontracting Plan requirements and further instructions on submission of Electronic Subcontracting Reporting System (eSRS) as required by FAR 52.219-9.

(h) The accepted Subcontracting Plan will be incorporated into and made a material part of the contract.

(i) The Corps of Engineers highly encourages all bidders/offerors to meet the recommended subcontracting goals as follows:

Small Businesses 70.0%

Small Disadvantaged Businesses 6.2%

Women-Owned Small Businesses 7.0%

HUBZone Small Business 9.8%

Veteran-Owned Small Business 3.5%

Service Disabled Veteran Owned Small Business 2.0%

The goals are calculated as a percentage of the TOTAL SUBCONTRACTING DOLLARS, NOT THE TOTAL

CONTRACT AMOUNT.

PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15 located in Section 00700.

INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate. If this is an IFB, failure to provide pledges of acceptable assets, with the bid, in the specified form, accompanied by a properly executed SF 24 and SF 28, will render the bidder nonresponsible and thus ineligible for award. If this is an RFP, failure to provide required documentation described herein may cause the offeror to be deemed "unacceptable".

BID GUARANTEE FORM AND AMOUNT:

The offeror shall furnish a separate bid guarantee in accordance with the solicitation provision titled "Bid Guarantee", FAR 52.228-1. In accordance with FAR 28.101-2 the bid guarantee amount shall be at least 20 percent of the "bid price" but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. If there are option line items on the Pricing Schedule (Section 00010), the term "bid price" is hereby defined as the total bid not to include any amount for line items designated as "options". In bids/proposals that contain "additives", the "bid price" is defined as the total of all bid items including additive line items. FAR 28.106-1 states that a Standard Form (SF) 24 shall be used for the bid bond. In accordance with FAR 28.202(a)(1), corporate sureties utilized must appear on the list contained in the Department of Treasury Circular

570 titled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies."

ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .