Bluestone Dam Safety Assurance Phase 5 Federal contract opportunity
Solicitation number
W9123719B0001
Issued by
Department of the Army Corps of Engineers Engineering District Huntington

About this file

This is a solicitation for a firm-fixed price construction contract to complete Phase 5 of the Bluestone Dam Safety Assurance Project in West Virginia. Work includes dewatering, excavation, demolition, anchor installation, tunneling, and construction of a permanent divider wall to modify the stilling basin in two halves. The estimated value is between $250,000 and $500,000. Interested offerors must register in SAM and check registration status prior to submitting a bid in response to this unrestricted solicitation. The deadline for questions is in mid-September 2019 and bids are due in early October. The contract will be awarded to the responsive and responsible bidder offering the lowest price. The procuring agency is the US Army Corps of Engineers Huntington District.

View the file

Other files for this federal contract opportunity

Other files attached to Bluestone Dam Safety Assurance Phase 5, newest first.
File Type Posted
Abstract of Offers.pdf PDF
W9123719B0001 0004.pdf PDF
A.03.09 Drawing B-701 (Amendment 0004).pdf PDF
Plans (Volume 2, Amendment 0003).pdf PDF
Plans (Volume 3, Amendment 0003).pdf PDF
Questions and Answers.pdf PDF
Plans (Volume 1, Amendment 0003).pdf PDF
W9123719B0001_0002.pdf PDF
Presentation_Slides.pdf PDF
Preliminary_Materials_and_Concrete_Mixture_Proportioning_Report.pdf PDF
Sign-In_Sheet.pdf PDF
W9123719B0001_0001.pdf PDF
Brand_Name_Justification.pdf PDF
W9123719B0001.pdf PDF
Plans_(Volume_2).pdf PDF
Plans_(Volume_3).pdf PDF
Directions_for_Pre-Bid_Site_Visit.pdf PDF
Plans_(Volume_1).pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above referenced solicitation for the Bluestone Dam Safety Assurance Project, Phase V, Stilling Basin Repairs, Hinton, WV is hereby amended as follow s:

Enclosures:

1. Revised Bid Schedule; 2. Revised Section 00 21 00; 3. Revised Section 00 70 00 (FAR Clause 52.236-4); 4. Boring Logs; 5. New Section 00 01 16; 6. Revised Section 31 68 12; 7. Revised Section 31 68 13; 8. Volume 1 Amended Draw ings; 9. Volume 2 Amended Draw ings; 10.

Volume 3 Amended Draw ings

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 14

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Nov-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123719B0001

X 9B. DATED (SEE ITEM 11)

16-Sep-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Nov-2019

CODE

USACE, CONTRACTING DIVISION

LEAH MORGAN, 502 8TH STREET

HUNTINGTON WV 25701

W91237 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123719B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been modified:

BID SCHEDULE

ITEM

NO.

DESCRIPTION QTY UNIT UNIT

PRICE

ESTIMATED

AMOUNT

1 Reimbursement of Actual Cost of Performance and Payment Bonds for Bids in Excess of $250,000

1 Job Sum (not to exceed)

2 Mobilization and Demobilization 1 Job Sum $

3 Stilling Basin Evacuation 3 Ea. $ $

4 Stilling Basin Delay 30 Day $ $

5 Stilling Basin Instrumentation Personnel Evacuation

15 Ea.

6 Stilling Basin Instrumentation Personnel Delay

30 Day

7 Stilling Basin Floating Plant Evacuation 1 Ea. $ $

8 Stilling Basin Floating Plant Evacuation Delay

15 Day

9 Installing Project Identification and Safety Performance Signs

1 Job Sum $

10 Reimbursable Costs for Government Furnished Cofferdam

1 Job Sum $3,000,000.00

11 Work Limits Mowing 108 Ea. $ $

12 Contractor-Furnished Government Office

108 Month

13 Contractor-Furnished Janitorial Services 108 Month $ $

14 Environmental Protection 1 Job Sum $ 15 Flow Diversion System 1 Ea. $ $

16 Working "As-built" Documents (Price shall not be less than $200,000)

1 Job Sum $

17 Final "As-built" Documents (Price shall not be less than $250,000)

1 Job Sum $

18 Demolition - Structures 1 Job Sum $

19 Demolition - Miscellaneous Features 1 Job Sum $ 20 Milling - Miller Avenue 1 Job Sum $

21 Spillway Apron Concrete Demolition 13,402 Cu.Yd. $ $

22 Training Wall Concrete Demolition 1,546 Cu.Yd. $ $

Enclosure No. 1

23 Toe of Monolith M34 Concrete Demolition

965 Cu.Yd.

24 Stilling Weir and Apron Concrete Demolition

1,692 Cu.Yd.

25 Fishing Pier Demolition 1 Job Sum $

26 Cofferdam Demolition 1 Job Sum $

27 Waterstop, Type 'Y' 13,145 Ln.Ft $ $

28 Waterstop, Type 'Y' Retrofit 5,560 Ln.Ft $ $

29 Deformed Steel Bars for Concrete Reinforcement

8,611,000 lbs.

30 General Concrete 692 Cu.Yd. $ $

31 Concrete Pavement 1,780 Cu.Yd. $ $

32 Parking Block 91 Ea. $ $

33 Precast Concrete Cap 343 Ln.Ft $ $ 34 Baseball Diamond Retaining Wall 155 Cu.Yd. $ $

35 Class 591 Mass Concrete 18,000 Cu.Yd. $ $

36 Class 493 Mass Concrete 25,200 Cu.Yd. $ $ 37 Class 492 Mass Concrete 35,620 Cu.Yd. $ $

38 Class 492 Infill Concrete 6,600 Cu.Yd. $ $

39 Class 491 Mass Concrete 60 Cu.Yd. $ $

40 Class 322T Tremie Concrete 3,200 Cu.Yd. $ $

41 Portland Cement 11,230 Ton $ $

42 Pozzolan 5,060 Ton $ $ 43 Ground Granulated Blast-Furnace Slag 7,110 Ton $ $

44 Silica Fume 6,120 cwt. $ $ 45 Bollards/Pipe Guards 69 Ea. $ $

46 Aluminum Handrail, Type 1 1 Job Sum $ 47 Aluminum Handrail, Type 2 1 Job Sum $ 48 ADIT Door #2 Replacement 1 Job Sum $

49 Watertight Doors 1 Job Sum $

50 Basin End Wall Piles 1 Job Sum $ 51 Supercavitating Baffle Armor 40 Ea. $ $

52 ADAS Instrumentation Contractor Delay

30 Day

53 Left Recreation Playground 1 Job Sum $ 54 Right Recreation Playground 1 Job Sum $

55 Baseball Diamond 1 Job Sum $

56 Bleachers 2 Ea. $ $ 57 Park Bench 21 Ea. $ $ 58 Trash Receptacles 11 Ea. $ $

59 Picnic Table 7 Ea. $ $

60 Picnic Shelter, Large 1 Ea. $ $ 61 Picnic Shelter, Small 1 Ea. $ $ 62 Grills 2 Ea. $ $

63 Retaining Wall Pads 223 Ln.Ft $ $

64 Right Recreation Fishing Pier 1 Job Sum $

65 Accessible Parking Sign 12 Ea. $ $

66 Instrumentation 1 Job Sum $

67 Uplift Cell 28 Ea. $ $

68 Conduit for Uplift Cells 6,400 Ln.Ft $ $

69 Tubing for Uplift Cell System 13,460 Ln.Ft $ $

70 Maintenance Building 1 Job Sum $

71 Concession Stand/Press Box 1 Job Sum $

72 Dugouts 1 Job Sum $ 73 Left Side Comfort Station 1 Job Sum $

74 Right Side Comfort Station 1 Job Sum $

75 Interpretive Center 1 Job Sum $

76 Recreation Area Electrical Building 1 Job Sum $

77 Overlook Electrical Building Modification

1 Job Sum $

78 Compressed Air System 1 Job Sum $

79 Oil-Water Separator 1 Job Sum $

80 Mechanical Work - Dam 1 Job Sum $

81 Divider Wall Ventilation 1 Job Sum $

82 Power Distribution Wiring System (Left Side)

1 Job Sum $

83 Power Distribution Wiring System (Right Side)

1 Job Sum $

84 Baseball Field Audio System 1 Job Sum $

85 Baseball Field Scoreboard System 1 Job Sum $

86 Maintenance Building Backup Generator

1 Job Sum $

87 Baseball Field Lighting System 1 Job Sum $

88 High Mast Lights 1 Job Sum $

89 Area Lighting (Left Side) 1 Job Sum $

90 Area Lighting (Right Side) 1 Job Sum $

91 Dewatering System 1 Ea. $ $

92 Excavation, Common 64,300 Cu.Yd. $ $

93 Exploratory Drilling, 4-inch Coring of Planned Borings

1250 Ln.Ft

94 Exploratory Drilling, 4-inch Coring of Supplementary Borings

350 Ln.Ft

95 Line Drilling 2,500 Sq.Yd. $ $

96 Excavation, Rock – Stilling Basin and Stone Confinement Wall

57,000 Cu.Yd.

97 Preliminary Cleanup 18,000 Sq.Yd. $ $ 98 Final Cleanup and Foundation

Preparation 17,000 Sq.Yd.

99 Dental Treatment - First 50 Cubic Yards 50 Cu.Yd. $ $ 100 Dental Treatment - All Over 50 Cubic

Yards 130 Cu.Yd.

101 Protective Earth Cover 2,500 Sq.Yd. $ $

102 Excavation, Rock - Penstock Basin Exit Channel

4,800 Cu.Yd.

103 Clearing and Grubbing 2 Acre $ $

104 Select Rockfill 101,000 Cu.Yd. $ $

105 Rockfill 19,000 Cu.Yd. $ $

106 Rockfill Cofferdams Removal 20,800 Cu.Yd. $ $

107 Excess Disposal Material 16,000 Cu.Yd. $ $

108 Disposal Embankment 57,900 Cu.Yd. $ $

109 Additional Fill 16,000 Cu.Yd. $ $

110 Topsoil (for Seeding) 11,200 Cu.Yd. $ $

111 Geomembrane and Protective Geotextile 3,200 Sq.Yd. $ $

112 Slush Grout 14 Sq.Yd. $ $

113 Underdrain System, 3-inch Drain and Instrumentation Drilling

6,100 Ln.Ft

114 Gallery Drain and Grout Hole Drilling 2,150 Ln.Ft $ $

115 Pressure Testing 3 Hr. $ $ 116 Portland Cement in Grout 900 Bag $ $

117 Admixtures in Grout 400 Gal. $ $

118 Bentonite in Grout 2,300 lbs. $ $ 119 Sand in Grout 1,500 Cu.Ft. $ $ 120 Placing Grout 60 Hr. $ $

121 Reconnections for Additional Downstaging

3 Ea.

122 Stand-by Time for Grouting 5 Hr. $ $

123 Foundation Drilling and Grouting Final Report

1 Ea.

124 Foundation Strip Drains 3,020 Ln.Ft $ $

125 Drain Riser Assembly 124 Ea. $ $

126 Lateral Piping for Drilled Drains 4,500 Ln.Ft $ $ 127 Lateral Piping for Existing Half Tile

Drain System 880 Ln.Ft

128 Receiver Pans 9 Ea. $ $

129 Isolation Casing 4 Ea. $ $

130 Foundation Drain Reaming 35,100 Ln.Ft $ $

131 Alternate Foundation Drain Cleaning 1,400 Ln.Ft $ $

132 Stone Slope Protection 24,100 Cu.Yd. $ $

133 Filter Fabric 5,800 Sq.Yd. $ $ 134 Derrick Stone 4,000 Cu.Yd. $ $

135 Steel Sheet Piling, Type PS 27.5 4,864 Ln.Ft $ $

136 90 Degree T-Pile Connection 128 Ln.Ft $ $ 137 In-Place Cellular Fill 2,118 Cu.Yd. $ $

138 Drilled Shafts 925 Ln.Ft $ $ 139 Anchor Liftoff Testing, 5 Strand 2 Ea. $ $

140 Anchor Liftoff Testing, 29 to 35 Strand 5 Ea. $ $

141 Anchor Liftoff Testing, 41 to 47 Strand 4 Ea. $ $

142 Anchor Liftoff Testing, 54 to 61 Strand 17 Ea. $ $ 143 Fabrication of Bearing Plate 1 Ea. $ $ 144 Strain Gauge Readings 2 Ea. $ $

145 Drilling Hole, 10-inch Diameter for Rock Anchors – Conventionally Drilled Type

33,936 Ln.Ft

146 Drilling Hole, 13-Inch Diameter for Rock Anchors – Conventionally Drilled Type

31,435 Ln.Ft

147 Drilling Hole, 15-Inch Diameter for Rock Anchors – Conventionally Drilled Type

7,422 Ln.Ft

148 Rock Anchors, 1-24 Strand, Conventionally Drilled Type

33,132 Ln.Ft

149 Rock Anchors, 25 to 48 Strand, Conventionally Drilled Type

31,888 Ln.Ft

150 Rock Anchors, 49-61 Strand, Conventionally Drilled Type

7,902 Ln.Ft

151 Anchor Tests for Rock Anchors - Conventionally Drilled Type

948 Ea.

152 Watertightness Testing for Rock Anchors - Conventionally Drilled Type

1,896 Ea.

153 Pregrouting Holes for Rock Anchors - Conventionally Drilled Type

97,875 Bag

154 Redrilling Pregrouted Holes for Rock Anchors - Conventionally Drilled Type

116,675 Ln.Ft

155 Watertightness Testing of Encapsulation for Rock Anchors - Conventionally Drilled Type

948 Ea.

156 Borehole Camera Logging for Rock Anchors - Conventionally Drilled Type

50 Ea.

157 Drilling Hole, 10-inch Diameter for Rock Anchors - Directionally Drilled Type

4,160 Ln.Ft

158 Drilling Hole, 13-Inch Diameter for Rock Anchors - Directionally Drilled Type

4,691 Ln.Ft

159 Drilling Hole, 15-Inch Diameter for Rock Anchors - Directionally Drilled Type

22,685 Ln.Ft

160 Rock Anchors, 1-24 Strand, Directionally Drilled Type

4,105 Ln.Ft

161 Rock Anchors, 25 to 48 Strand, Directionally Drilled Type

4,780 Ln.Ft

162 Rock Anchors, 49-61 Strand, Directionally Drilled Type

22,801 Ln.Ft

163 Anchor Tests for Rock Anchors - Directionally Drilled Type

200 Ea.

164 Watertightness Testing for Rock Anchors - Directionally Drilled Type

400 Ea.

165 Pregrouting Holes for Rock Anchors - Directionally Drilled Type

60,069 Bag

166 Redrilling Pregrouted Holes for Rock Anchors - Directionally Drilled Type

50,698 Ln.Ft

167 Grouting of Intercepted Foundation Drains for Rock Anchors - Directionally Drilled Type

12 Ea.

168 Watertightness Testing of Encapsulation for Rock Anchors - Directionally Drilled Type

200 Ea.

169 Borehole Camera Logging for Rock Anchors - Directionally Drilled Type

7 Ea.

170 Interception Borehole Camera Logging for Rock Anchors - Directionally Drilled Type

200 Ea.

171 Drilling Holes in Rock and Concrete - Bar Anchors

248 Ln.Ft

172 Rock Anchors - 3-Inch Threaded Bar 232 Ln.Ft $ $

173 Performance Tests - Bar Anchors 2 Ea. $ $ 174 Watertightness Testing - Bar Anchors 7 Ea. $ $

175 Pregrouting Holes - Bar Anchors 245 Bag $ $

176 Redrilling Pregrouted Holes - Bar Anchors

705 Ln.Ft

177 Watertightness Testing of Encapsulation

- Bar Anchors

2 Ea.

178 Excavation, Tunnel Concrete 203 Cu.Yd. $ $ 179 Final Concrete Tunnel Surface Cleanup and Preparation 366 Sq.Yd.

180 Subgrade Preparation 30,500 Sq.Yd. $ $ 181 Engineering Fabric 30,500 Sq.Yd. $ $ 182 Aggregate Base Course, Class 1 9,300 Cu.Yd. $ $

183 Prime Coat 7,750 Gallon $ $ 184 Bituminous Concrete Base Course, Type I 4,600 Ton

185 Bituminous Concrete Wearing Course, Type I

2,150 Ton

186 Miller Avenue Final Repave 840 Ton $ $

187 Combination Curb and Gutter, Type I 770 Ln.Ft $ $ 188 Plain Curb, Type I 2,803 Ln.Ft $ $

189 Shoulders 300 Cu.Yd. $ $ 190 Pavement Marking, Type I 23,200 Ln.Ft $ $

191 Parking Marking 7,350 Ln.Ft $ $

192 Accessible Parking Symbol 15 Ea. $ $

193 Guardrail, Type 1, Class 2 9,865 Ln.Ft $ $

194 Guardrail Glove End Treatment 34 Ea. $ $

195 No. 1 Aggregate 500 Cu.Yd. $ $ 196 Detectable Warning Surface 7 Ea. $ $

197 42-inch Fence 99 Ln.Ft $ $

198 8-foot Baseball Diamond Fence 700 Ln.Ft $ $

199 15-foot Backstop Fence 74 Ln.Ft $ $

200 6-Foot Security Fence 1,347 Ln.Ft $ $

201 Seeding 8.5 Acre $ $ 202 Landscape Planting 1 Job Sum $

203 Waterline, Ductile Iron Pipe, 6-Inch 1,285 Ln.Ft $ $

204 Waterline, HDPE SDR 9, 3/4-Inch 284 Ln.Ft $ $

205 Waterline, HDPE SDR 9, 1-Inch 145 Ln.Ft $ $

206 Waterline, HDPE SDR 9, 2-Inch 1,165 Ln.Ft $ $

207 Curb Valve, 3/4-Inch 1 Ea. $ $

208 Gate Valve, 2-Inch 3 Ea. $ $

209 Gate Valve, 6-Inch 2 Ea. $ $

210 Yard Hydrant 3 Ea. $ $ 211 Fire Hydrant 1 Ea. $ $

212 Water Fountain 2 Ea. $ $

213 RPZ Assembly 1 Ea. $ $

214 Sanitary Sewer Line, PVC SDR 35, Size 4-Inch

738 Ln.Ft

215 Sanitary Sewer Line, PVC SDR 35, Size 8-Inch

1,161 Ln.Ft

216 Sanitary Sewer Line, HDPE SDR 9, Size 2-Inch

644 Ln.Ft

217 Sanitary Sewer Line, DIP, Size 8-Inch 294 Ln.Ft $ $

218 Precast Concrete Manhole 6 Ea. $ $ 219 Cleanout 3 Ea. $ $

220 Left Side Sewage Lift Station 1 Ea. $ $

221 Box Culvert, 5 foot by 5 foot 284 Ln.Ft $ $

222 Box Culvert, 5 foot by 3 foot 434 Ln.Ft $ $

223 HDPE Corrugated Pipe, 24-Inch 1,480 Ln.Ft $ $

224 Storm Sewer, Reinforced Concrete Pipe, 18-Inch

345 Ln.Ft

225 Storm Sewer, Reinforced Concrete Pipe, 24-Inch

156 Ln.Ft

226 Storm Sewer, Reinforced Concrete Pipe, 12-Inch

138 Ln.Ft

227 Storm Sewer WVDOH Type B Inlet 8 Ea. $ $

228 Storm Sewer WVDOH Type G Inlet 12 Ea. $ $

229 Wingwall, 24-Inch 8 Ea. $ $

230 Trench Drain 1 Job Sum $

231 Power Distribution Wiring System (Left Side)

1 Job Sum $

232 Power Distribution Wiring System (Right Side)

1 Job Sum $

233 Remote Shelter Power Modifications 1 Job Sum $

234 Remote Shelter Fiber Modifications 1 Job Sum $

235 Maintenance Building Fiber Optic Feeder Modification

1 Job Sum $

Total (Items 1 thru 235) $

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

INSTRUCTIONS TO BIDDERS

BID OPENING

The bid opening will be held at the U.S. Army Corps of Engineers, Room 125, 502 8th Street, Huntington, WV 25701. For date and time of bid opening, see Block 13 on Standard Form 1442. Upon arrival, attendees must check in with the security desk to have the guards contact Leah Morgan at ext. 5548 to submit your bid and be escorted to Room 125 for the bid opening.

PRICE BASIS

Bidders are advised that only bids submitted on a firm-fixed price basis will be considered, and that bids submitted on any other than firm-fixed price basis will be rejected.

Bid price alterations, i.e., crossed-out or white-out changes on the bid will not be accepted unless the change(s) is/are initialed.

BID QUANTITIES

Bids for less than specified quantities of each item in the Schedule will not be considered. Failure to submit a unit price for each item where required in the bid schedule will be considered as a material deviation from the requirements of the solicitation, and the bid will be rejected. (FAR 14.404-2)

ARITHMETIC DISCREPANCIES

(a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the bidding schedule as submitted by the bidders:

(1) Obviously misplaced decimal points will be corrected;

(2) In case of discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of job and extended price will be corrected; and

(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends their bid to be evaluated on the basis of unit prices, extensions, and totals arrived at by resolution of arithmetic discrepancies as provided above and bid will be so reflected on the abstract of bids.

ADDITIONAL INSTRUCTIONS

I. BIDS MUST SET FORTH FULL, ACCURATE, AND COMPLETE INFORMATION AS REQUIRED BY

THIS INVITATION FOR BID (INCLUDING ATTACHMENTS). THE PENALTY FOR MAKING

FALSE STATEMENTS IN BIDS IS PRESCRIBED IN 18 U.S.C. 1001.

Enclosure No. 2

II. THE HUNTINGTON DISTRICT CORPS OF ENGINEERS DOES NOT ACCEPT BIDS BY

FACSIMILE TRANSMISSIONS AND/OR EMAIL.

III. NOTE THE AFFIRMATIVE ACTION REQUIREMENTS OF THE EQUAL EMPLOYMENT

OPPORTUNITY CLAUSE (FAR 52.222-23) WHICH WILL APPLY TO THE CONTRACT

RESULTING FROM THIS SOLICITATION.

IV. ONE SEALED PAPER ORIGINAL AND ONE PAPER COPY OF BIDS ARE DUE AT THE

PLACE SPECIFIED ON THE STANDARD FORM 1442, ITEM 8. IN ADDITION TO THE HARD

COPIES, IT IS PREFERRED THAT BIDDERS SUBMIT A SEARCHABLE PDF DOCUMENT ON

A CD OR DVD. SUBMISSIONS RECEIVED SOLELY VIA ELECTRONIC MEDIA SUCH AS

CD, DVD, THUMBDRIVE, EMAIL, OR FACSIMILE WILL NOT BE CONSIDERED.

V. IF THE APPARENT LOW BIDDER IS OTHER THAN SMALL BUSINESS, A

SUBCONTRACTING PLAN MAY BE REQUIRED IN ACCORDANCE WITH FAR CLAUSE

52.219-9 ALTERNATE I (DEVIATION), SMALL BUSINESS SUBCONTRACTING PLAN.

VI. EFFECTIVE SEPTEMBER 26, 2018 AND IN ACCORDANCE WITH FAR CLAUSE 52.204-7, “AN

OFFEROR IS REQUIRED TO BE REGISTERED IN SAM WHEN SUBMITTING AN OFFER OR

QUOTATION, AND SHALL CONTINUE TO BE REGISTERED UNTIL TIME OF AWARD, DURING

PERFORMANCE, AND THROUGH FINAL PAYMENT OF ANY CONTRACT, BASIC AGREEMENT,

BASIC ORDERING AGREEMENT, OR BLANKET PURCHASING AGREEMENT RESULTING FROM

THIS SOLICITATION.” VENDORS ARE HIGHLY ENCOURAGED TO CHECK THEIR

REGISTRATION STATUS AND PLAN ACCORDINGLY PRIOR TO SUBMITTING A BID.

DETERMINATION OF RESPONSIBILITY

To ensure award is made to a responsible bidder, a determination of responsibility will be conducted. The apparent low bidder will be contacted by the Contracting Officer and will be required to provide the requested responsibility information within 4 calendar days. As part of this responsibility determination, the Contracting Officer will utilize the guidance contained in FAR 9.104-1. To be determined responsible, a prospective contractor must:

a. Have adequate financial resources to perform the contract or the ability to obtain them.

b. Be able to comply with the required or proposed delivery or performance schedule.

c. Have a satisfactory performance record.

d. Have a satisfactory record of integrity and business ethics.

e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them.

f. Has the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.

g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

DEFINITIVE RESPONSIBILITY CRITERIA

In addition to examining the criteria in FAR 9.104-1, the Contracting Officer will also examine whether the apparent low bidder can meet the requirements of the following two definitive responsibility criteria. After bid opening, but prior to award, the apparent low bidder will be required to furnish documentation showing that the prime contractor or subcontractor(s) has/have completed:

a. No more than a total of eight (8) projects showing experience with placing at least a cumulative total of 75,000 cubic yards of mass concrete with 1.5 inch (or greater) aggregate and setting up and operating a batch plant in support of the project(s). Note that the quantity of concrete is the cumulative total of all submitted projects.

b. Two (2) projects showing experience directionally drilling through concrete and rock on a 1:150 tolerance as measured against a specified center line with real time survey and directional correction capabilities.

Firms may use prime or subcontractor (to be used on this project) experience to demonstrate experience with the definitive responsibility criteria, but the work performed by each entity on projects demonstrating that entity’s experience with the definitive responsibility criteria shall be the same as the work to be performed by that entity under this procurement. In order for experience to qualify under either of these criteria, the documentation must show that the experience was direct and not by-standing. By-standing means that the entity participated in a construction project but did not directly execute the features of work identified above. Personnel experience may be submitted as documentation to meet criterion (b) only. Should an entity intend to satisfy criterion (b) with personnel experience alone, the documentation must show that the entity is able to provide the necessary equipment to support the personnel in that role.

The apparent low bidder will have ten (10) calendar days after the Government’s request to submit the documentation demonstrating that it meets the above definitive responsibility criteria, and will receive award of the contract if otherwise eligible and responsible. If the apparent low bidder cannot provide this documentation, or if the documentation it submits does not show that it meets these criteria, the apparent next low bidder will be requested to provide this documentation. If this apparent next low bidder timely provides the documentation within ten (10) calendar days after the Government’s request, it will receive award of the contract if otherwise eligible and responsible. This process will be followed until the apparent low bidder who meets the requirement can document that it meets the definitive responsibility criteria or the Government cancels the solicitation.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

52.236-4 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys, core borings, etc., and previous construction at the site. Records consisting of drive sampling and core boring data gathered to determine the characteristics of the materials at the site have been compiled by the Government. Locations of borings and associated graphic logs are shown on the drawings.

Corresponding typed logs are included in Section 00 01 15 BORING LOGS. Subsurface exploration samples that were not consumed during testing, Borehole Image Processing Surveys, and foundation reports are available for examination by prospective bidders. Prospective bidders are encouraged to contact the Government to arrange for examination of all available data. Because of its nature and quantity, this material must be examined at the Huntington District Warehouse located at #9 27th Street, Huntington, WV 25702. The Contractor shall contact the Contracting Officer to make arrangements to view the core and referenced information.

(b) Weather conditions. The Contractor shall make his own investigations as to weather conditions at the site. The Charleston, WV, Weather Forecast Office is responsible for forecasts for the town of Hinton. The Blacksburg, VA, Weather Forecast Office is responsible for forecast for the town of Bellepoint and Bluestone Dam. The NOAA Weather Radio is transmitted on station WXM72 out of Hinton, WV.

(c) Transportation facilities. West Virginia State Routes 20 and 3 provide access to the project site.

(d) Location of Project. Bluestone Lake is located within Hinton, Summers County, West Virginia.

(e) Contractor's Responsibility. The Contractor will be held responsible for any and all damages attributable to the actions of the Contractor or its subcontractors outside the limits of construction, shown on the drawings or designated by the Contracting Officer. This shall include damage to existing roads, drainage structures, electrical or telephone facilities, pavement, and other structures and facilities. All such damage shall be repaired to the satisfaction of the proper municipal or state authorities by the Contractor and at his expense.

(f) Jurisdictions. All hauling over roads to and from the project will be subject to the approval of the proper municipal or state authorities; and the Contractor shall make the necessary arrangements, at its expense, with such authorities for the use of such roads, and shall comply with their requirements in connection with such use.

(g) Field Information. Contractors who desire an escort at the site or who require field information should contact:

Resident Engineer, HC78 Box 6C, Hinton, WV 25951, Telephone 304-466-6950.

(h) Floods. Attention is invited to the fact that the site of the work is subject to flooding at any time.

(i) Working Area and Times. The dam is operational 24 hours a day, 7 days a week. Government Operations personnel's normal work hours are Monday through Friday from 7:30 a.m. to 4:00 p.m. The Contractor's activity shall not impact the operations of the dam for the duration of the contract. The Contractor shall have access to the inside of the dam during the specified normal work hours. Access to the interior of the dam outside normal work hours will require specific arrangements to be made with the Contracting Officer and Operations personnel.

Enclosure No. 3

(j) Work Site Clean-up. No separate payment will be made for clean-up of the construction site following flood events.

(k) A video of lessons learned from a full scale anchor study conducted in 2002 entitled "Field Anchor Study Video Documentation and Directional Drilling Report" will be made available for viewing for the Contractor’s information. Also, a survey of potential directional drilling and borehole measurement technology was conducted by Fuller Mossbarger Scott & May, dated February 2005, which will also be made available for review. Prospective bidders are encouraged to contact the Government to arrange for examination of all available data. This material may be examined at the Huntington District Warehouse located at #9 27th Street, Huntington, WV 25702. The Contractor shall contact the Contracting Officer to make arrangements to view the core and referenced information.

(End of clause)

(End of Summary of Changes)

Amendment No. 0003 IFB No. W9123719B0001 Page 15 of 64 Pages

SECTION 00 01 00 - SOLICITATION

1. BIDDING SCHEDULE. Bidding Schedule is deleted in its entirety and a new revised Bidding Schedule is substituted therefore as Enclosure No. 1.

SECTION 00 01 15 - BORING LOGS

2. Append the new boring logs to the end of this section.

These new boring logs are enclosed as Enclosure No. 4.

SECTION 00 01 16 - DEVIATION TO THE WATER CONTROL MANUAL

3. Append the new Section 00 01 16 after Section 00 01 15.

This new section is enclosed as Enclosure No. 5.

SECTION 00 80 00 – SPECIAL CONTRACT REQUIREMENTS

4. Page 6, Para. 1.6. Delete “e-mail Sandra.M.Hardwick@usace.army.mil” and replace with “e-mail Sandra.L.Hardwick@usace.army.mil.”

5. Pages 18, 19 and 20, Para. 1.24.1. Delete this paragraph in its entirety and replace with the following:

“The Contractor shall adhere to the following Construction Restrictions.

(a) The Contractor shall perform the work in accordance with Section 01 00 00 CONTRACT CONSIDERATION, Paragraph CONSTRUCTION SEQUENCE.

(b) All components of the flow diversion system shall be installed, operational and approved by the Contracting Officer prior to stopping flow through dam sluice gates 1 through 8 for construction activities on the right side of the stilling basin. The Contractor can request right side flow stoppage when the diverter system is installed and other requirements of the specifications for dewatering of the basin have been met. Unless alternate limits are proposed by the Contractor and approved by the Contracting Officer, work requiring penstocks to be free of water such as manhole cover removal, debris removal, and siphon pipe installation must occur during the time interval between 1 December and 1 April when the lake is at a winter pool of Elevation 1406.

(c) Restrictions for construction of the right side of the stilling basin:

o All existing anchors of the right training wall shall be de-tensioned prior to dewatering of and

Page 16 of 64 Pages working in the right side of the stilling basin upstream of the stilling basin weir.

o Downstream cofferdam cells, transition, and granular cofferdam shall be constructed before the following can occur:

(1) Dewatering of and working in the stilling basin upstream of the stilling basin weir (the exception to this restriction is if the Contractor chooses to install cover plates at the downstream end of the stilling weir sluices in accordance with these plan and specifications)

(2) Notching of the stilling basin weir

(3) Dewatering downstream of the stilling basin weir o When the right side of the stilling basin is dewatered, the Contractor shall monitor the water level elevation on the outside of the right training wall. Should this water level elevation exceed Elevation 1381.0, the Contractor shall evacuate the right side of the stilling basin.

o At no time shall soil be placed against or retained by the right training wall.

(d) Restrictions for construction of the left side of the stilling basin:

o The first two anchors to be stressed in each of left training wall monoliths M94 through M100 shall be installed, tensioned and locked-off prior to dewatering of and working in the left side of the stilling basin upstream of the stilling basin weir.

o Downstream granular cofferdam and basin end wall shall be constructed before the following can occur:

(1) Dewatering of and working in the stilling basin upstream of the stilling basin weir (the exception to this restriction is if the Contractor chooses to install cover plates at the downstream end of the stilling weir sluices in accordance with these plan and specifications)

(2) Notching of the stilling basin weir

(3) Dewatering downstream of the stilling basin weir

Page 17 of 64 Pages o When the left side of the stilling basin is dewatered, the Contractor shall monitor the water level elevation on the outside of the left training wall. Should this water level elevation exceed Elevation 1381.0, the Contractor shall evacuate the left side of the stilling basin.

o For the left training wall, in addition to installing the required anchors prior to dewatering, the Contractor may choose to perform other work associated with this wall prior to dewatering. The Contractor shall be allowed to perform the other work while the left side of the basin is operational provided the following are met:

(1) At no time shall concrete demolition of the left training wall exceed the limits provided in the plans.

(2) At no time shall the soil elevation on the outside of the left training wall upstream of the stilling weir be lower than Elevation 1394.0.

(3) At no time shall the soil elevation on the outside of the left training wall be higher than the original wall height unless all anchors are installed, tensioned and locked-off in the wall including all anchors through the outside face and all anchors through the wall raise.

o The Contractor shall be responsible for the stability of the wall raise of the left training wall during construction and shall provide a work plan ensuring its stability for approval prior to initiating work on raising the left training wall.

(e) For construction of the right side of the stilling basin upstream of the stilling basin weir, the upstream transition of the cofferdam shall be anchored and the most upstream toe block of the cofferdam shall be constructed and anchored prior to initiating demolition of the existing apron and construction of the apron overlay and M34T2 base to Elevation 1368.0. For construction of the right side of the stilling basin upstream of the stilling basin weir, the apron overlay shall be constructed and anchored, M34T2 shall be constructed to Elevation 1368.0, and all toe blocks of the cofferdam shall be constructed and anchored prior to initiating concrete demolition of the existing apron below elevation 1363.0 (elevation 1358.0 at M34T2) and excavation of rock in the stilling basin. For construction of the left side of the stilling

Page 18 of 64 Pages basin upstream of the stilling basin weir, the apron overlay shall be constructed and anchored prior to initiating concrete demolition of the existing apron below elevation 1363.0 and excavation of rock in the stilling basin.

(f) The Contractor shall construct any necessary platforms for and install anchors in spillway monoliths M24 and M33 when the right side of the stilling basin is dewatered. The Contractor shall construct any necessary platforms for and install anchors in spillway monoliths M37 and M38 when the left side of the stilling basin is dewatered.

(g) No rock excavation will be performed within the basin until all planned and supplementary exploratory borings have been completed and final founding elevations and locations of line drilled faces have been confirmed for the side of the basin where work is being performed.

(h) Curtain grouting for the spillway monoliths will be completed prior to the placement of concrete for any new monoliths within the stilling basin.

(i) The Contractor shall perform drain reaming and cleaning as required in Section 31 32 25

REAMING AND CLEANING OF EXISTING INSPECTION

GALLERY DRAINS twice during the contract. The initial drain reaming and cleaning shall occur prior to the placement of concrete for any new monoliths within the stilling basin. The final drain reaming/cleaning shall be performed within the last year of construction and after all dam anchors have been installed.

(j) Anchor liftoff testing shall be completed no later than 31 December 2023.

(k) Contractor shall construct M34T1 prior to constructing M34T2 above Elevation 1368.0. The Contractor shall construct M77T1 prior to removing baffles in the stilling weir apron and constructing M77T2.

(l) Any structure used for dewatering, including but not limited to, the Government furnished cofferdam, the Contractor constructed cofferdam, the left training wall, the right training wall, the stilling weir, the divider wall, the basin end wall, and the granular cofferdam, shall have to meet the following requirements prior to mobilizing personnel or equipment into the dewatered area:

Page 19 of 64 Pages

(1) All instrumentation shall be installed in the structure.

(2) The ADAS must be fully functional to monitor life safety.

(3) The work area must be dewatered for 14 calendar days to establish baseline readings for the instrumentation prior to mobilizing personnel or equipment. The 14 calendar days is in addition to the time estimates for ADAS installation and automation provided in Section 13 05 00 INSTRUMENTATION, Paragraph AUTOMATED

DATA ACQUISTION SYSTEM (ADAS) UNDER SEPARATE

CONTRACT.”

6. Page 20, Para. 1.24.2.1. Delete this paragraph in its entirety and replace with the following:

“The Contractor shall submit for approval by the Contracting Officer a plan designed and stamped by a professional engineer registered in the state of West Virginia, for a mooring system for all floating plant placed in the stilling basin. Tether lines shall be maintained on the floating plant to provide stability and to prevent uncontrolled movements that would threaten the safety of personnel and could damage equipment. The Government shall require the Contractor to evacuate personnel and floating plant from the stilling basin if crest flow is predicted, see Paragraphs STILLING BASIN FLOATING PLANT

EVACUATION AND STILLING BASIN FLOATING PLANT

EVACUATION DELAY, below. The Contractor shall evacuate personnel and floating plant prior to exceeding the Contractor mooring system design. This evacuation and delay shall occur at no cost to the Government.”

7. Page 21, Para. 1.25. Delete this paragraph in its entirety and replace with the following:

“Personnel and equipment will need to be removed during the following events:

During Construction of Right Side Stilling Basin

(a) The pool is forecast to be greater than Elevation 1515.0.

(b) Crest Flow Left Side

(c) Sluice or Crest Flow Right Side.

Page 20 of 64 Pages

(d) Water elevation on the outside of the right training wall exceeds Elevation 1381.0.

Based on rainfall on the ground forecast the Government will give the Contractor 12-24 hour notice.

During Construction of Left Side Stilling Basin

(a) The pool is forecast to be greater than Elevation 1515.0.

(b) Crest Flow Right Side

(c) Sluice or Crest Flow Left Side.

(d) Water elevation on the outside of the left training wall exceeds Elevation 1381.0.

Based on rainfall on the ground forecast the Government will give the Contractor 12-24 hour notice.”

8. Page 22, Para. 1.27.2. Delete this paragraph in its entirety and replace with the following:

“Payment will be made at the applicable contract line item price per day for "Stilling Basin Delay", which price will include all costs associated with having the Contractor delayed from performing work in the stilling basin after evacuation. Once flow returns to acceptable levels and upon approval of the Contracting Officer the delay ends.”

9. Page 22. Add the following new paragraphs after Paragraph 1.27.4:

“1.27.5 Stilling Basin Floating Plant Evacuation

Payment will be made at the applicable contract line item price per each for "Stilling Basin Floating Plant Evacuation", which price shall include all costs associated with the Contractor removing floating plant, equipment and personnel from the basin, and remobilizing the floating plant, equipment and personnel to the basin.

Page 21 of 64 Pages

1.27.6 Stilling Basin Floating Plant

Evacuation Delay

Payment will be made at the applicable contract line item price per day for "Stilling Basin Floating Plant Evacuation Delay", which price shall include all costs associated with having the Contractor delayed from performing work in the stilling basin after stilling basin floating plant evacuation. Once crest flow ends, the delay ends.”

SECTION 01 00 00 – CONTRACT CONSIDERATIONS

10. Pages 4 and 5, Para. 1.4.4. Delete this paragraph in its entirety and replace with the following:

“Except as indicated for the left training wall in Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS, Paragraph CONSTRUCTION RESTRICTIONS, the right side of the stilling basin including the divider wall and right overtopping protection shall be constructed before beginning construction on the left side of the basin. The Contractor may choose to perform work on the left training wall prior to completion of the right side of the stilling basin in accordance with Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS, Paragraph CONSTRUCTION RESTRICTIONS. For the right side of the stilling basin, the Contractor shall receive final acceptance of the right side basin from the Contracting Officer prior to initiating construction of the left side. The right side will be considered acceptable when the divider wall is complete, is connected to the existing inspection gallery, all sumps pumps are installed and functional, both watertight doors are installed and functional, and the divider wall has passed the water leakage test. For the water leakage test, the Contractor shall fill the space between divider wall and cofferdam to Elevation 1391.0 for a continuous period of 7 days. If the combined leakage into the gallery of the divider wall and the dry side of the divider wall exceeds more than 10 gallons per minute or if the leakage in any joint exceeds 3 gallons per minute, the divider wall will not be accepted. In addition, all work within the cofferdam is to be complete except placement of scour protection material between main basin right and penstock left training walls and construction of the M24 sump collector.

However, work to place scour protection material and construct the sump collector

Page 22 of 64 Pages shall be conducted in the dry. Acceptance will not include electrical, mechanical, or instrumentation equipment in the interior of the divider wall gallery; this equipment will remain the responsibility of the Contractor until final acceptance of the stilling basin.

The Contractor shall repair any damage to equipment within the divider wall gallery caused by construction activities prior to final acceptance at no cost to the Government.

The new maintenance building and all appurtenant features to include security fencing, utilities, area lighting, etc., shall be constructed prior to initiating demolition of the existing maintenance building and appurtenant features, as shown on the drawings. The Contractor cannot demolish existing Maintenance Building until 30 calendar days after acceptance of the new Maintenance Building.”

11. Page 5, Para. 1.4.5. Delete this paragraph in its entirety and replace with the following:

“Operations will exercise the sluice gates twice a year. During this testing, it is anticipated that water from the sluice gates will be discharged into the main basin, approximately 450 cubic feet of water per sluice with a minimum discharge rate of 150-1000 gallons per minute per sluice. The Contractor can anticipate one day per event for exercising the sluice gates. No personnel will be allowed in the basin during this event. The Contracting Officer will notify and coordinate with the Contractor 30 calendar days in advance of exercising the sluice gates. The cost for this shall be incidental to the dewatering.”

SECTION 01 31 19.00 40 – PROJECT CONFERENCES

12. Page 3, Para. 3.2.3.a and Para. 3.2.3.h. Delete these paragraphs in their entirety and renumber the remaining paragraphs accordingly.

SECTION 01 32 01.00 10 – PROJECT SCHEDULE

13. Page 15, Para. 3.10.2. Delete the last sentence in its entirety and replace with the following:

“Days lost due to high water will be considered adverse weather days.”

Page 23 of 64 Pages

SECTION 01 38 10 – PROGRESS PHOTOGRAPHS

14. Page 4, Para. 3.1. Delete the eighth sentence in its entirety.

SECTION 01 50 00 – TEMPORARY CONSTRUCTION FACILITIES

15. Page 10, Para. 1.16.1. Delete the first sentence in its entirety and replace with the following:

“The Contractor shall provide temporary office space for the Corps of Engineers use that will be separate office space from the Contractor during the period of construction within three miles of the Bluestone Resident Office.”

SECTION 01 57 20.00 10 – ENVIRONMENTAL PROTECTION

16. Page 9, Para. 3.7.5. Delete this paragraph in its entirety and replace with the following:

“A flow diverter system shall be developed by the Contractor in accordance with the contract drawings. The purpose of this system is to divert water from the lake, through the penstocks and penstock gates, to the penstock stilling basin, returning it to the river on the right side (east) near the mouth of Packs Branch. The intent of this system is to lessen the impact of flow alteration in the river as a result of construction on the right side of the main dam stilling basin. Unless alternate limits are proposed by the Contractor and approved by the Contracting Officer, this system must be installed and operating prior to stopping flow from the right side stilling basin for construction. Past this point, the system shall remain in operation at all times when dam sluice gates 1 through 8 are closed and no flow is present on the right side of the cofferdam. It is the Contractor's responsibility to ensure the system remains operational until such time flow can be reestablished from dam sluice gates 1 through 8. The Contractor is also responsible for removal of the flow diversion system when no longer needed and restoration to pre-construction condition of any areas impacted by installation of the flow diversion system. Submit designs, materials, equipment, installation and operations plans to the Contracting Officer

Page 24 of 64 Pages for approval. Construction of the flow diverter system will require removal of debris from within the penstocks; this material shall be disposed of in accordance with these specifications. Note that some portions of work associated with the flow diverter system must be completed with the lake elevation at winter pool (El. 1406) between 1 December and 1 April unless permitted otherwise by the Contracting Officer. Some portions of the penstocks are coated with paint containing lead; the Contractor shall take any steps necessary to comply with applicable Federal, State, local, laws and regulations and these specifications.”

SECTION 01 60 00.00 40 – MATERIAL AND EQUIPMENT

17. Page 8, Para. 3.9.1. Delete this paragraph in its entirety and replace with the following:

“An existing cofferdam to dewater the right half of Bluestone stilling basin is Government furnished for use by the Contractor. Upon award, the Government furnished cofferdam becomes the property of the Contractor. The cofferdam consists of five circular cells, four arcs, two transitions, a platform suitable for use only as a pedestrian walkway from the left training wall to the cofferdam, and is provided "AS IS." No warranty is provided for the cofferdam.

Dimensions and details of the cofferdam can be found in the For Information Only drawings, and no warranty shall be attached thereto or be implied by such drawings or other related documents. Upon completion of use of the Government furnished cofferdam, the Contractor shall remove the cofferdam in accordance with the drawings and specifications. Concrete and aggregate removed may be disposed of on-site in accordance with the drawings and specifications.

All other items shall be removed from the site.

The Contractor shall inspect the cofferdam, verify the condition of the cofferdam and acknowledge receipt, in writing, to the Contracting Officer prior to using the cofferdam.”

18. Page 9, Para. 3.9.3. Under the heading “Material Inventory – For Information Only” add the following to the end of the inventory list:

“3000 square feet of grating has been removed from the inventory.”

Page 25 of 64 Pages

19. Page 10, Para. 3.10.2. Delete this paragraph in its entirety and replace with the following:

“The Contractor will be reimbursed in an amount not to exceed $3,000,000.00, for costs, provided that prior written approval for the cost was received from the Contracting Officer, if any, necessary to bring the Government furnished cofferdam up to current engineering standards only once from the time of acceptance until acceptance of right side of the stilling basin by the Contracting Officer. Any additional costs will be the Contractor's expense. Any amount not expended to bring the Government furnished cofferdam up to current engineering standards only once from the time of acceptance by the Contractor until 6 months after dewatering and inspection of the right side of the stilling basin shall revert to the Government. The purpose of the reimbursable cost is to bring the cofferdam up to current engineering standards once, if necessary, not to maintain current engineering standards.”

SECTION 01 78 00 – CLOSEOUT SUBMITTALS

20. Page 2, Para. 1.1. Under the heading “SD-02 Shop Drawings”, delete the paragraph in its entirety and replace with the following:

"As-Built" Drawings; G|DC Working “As-Built" Drawings; G|DC

Drawings showing final "as-built" conditions of the project. The manually prepared drawings shall consist of the approved marked working "as-built" prints and two color copies. Working “as-builts” shall be submitted in accordance with the specifications and final “as-builts” shall be submitted after all work is complete.”

21. Page 3, Para. 1.2.1.1. Delete the paragraph in its

“The Contractor shall revise digital PDF versions of working "as-built" drawings by red-line process to show the "as-built" conditions during the prosecution of the project. These working "as-built" marked drawings shall be kept current on a weekly basis, submitted to the Government every six months, and at least one set shall be available on the jobsite at all times. Changes from the contract drawings, which are made in the work or additional information which might

Page 26 of 64 Pages be uncovered in the course of construction, shall be accurately and neatly recorded as they occur by means of details and notes.

Final "as-built" drawings shall be prepared, in a digital PDF format, after all construction activities have been completed.

The working "as-built" marked drawings and final "as-built" drawings will be jointly reviewed for accuracy and completeness by the Contracting Officer and the Contractor prior to submission of each monthly pay estimate. If the Contractor fails to maintain the working and final "as-built" drawings as specified herein, the Contracting Officer will deduct from the monthly progress payment an amount representing the estimated cost of maintaining the "as-built" drawings.