This document is Amendment 0006 to Solicitation W9123626BA006, issued by the U.S. Army Corps of Engineers (USACE) W2SD ENDIST Norfolk on September 14, 2026. The amendment incorporates ProJNet bidder inquiries with corresponding government responses, revised plans and specifications, and does not extend the bid due date or bid opening date.

The project involves Fort G-A Recovery Range construction work at a military installation in Virginia, structured as a 100% competitive 8(a) small business set-aside with three phased contract line items (CLINs) anticipated to be funded and executed within a 365-day period of performance. Key work includes construction of concrete turning pads (approximately 24 turning pads with new concrete pavement), gravel road redressing and maintenance, culvert cleaning and replacement, wet pond maintenance and dredging, erosion and sediment control, drainage improvements, and site restoration. The project requires contractor-furnished testing, quality control with certified personnel (NRMCA and ACI certified installers), concrete placement with specified mix designs, and environmental compliance. Notable clarifications address QC manager qualifications (10 years experience, removal of professional engineer registration requirement), site utility coordination via Dig Safe 811, contractor responsibility for permits and material import/export, tree removal restrictions (April 1 to September 30), no hazardous materials anticipated, and final acceptance criteria requiring government inspection and punch list correction. Revised drawings and specifications address survey data sources, wet pond elevation corrections (80 feet instead of 90 feet), silt fence clarification, and aggregate specifications. The controlling issued-for-bid drawing set was issued in Amendment 0005.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section 00 01 15 - List of Drawing Sheets

The attachments table has changed from:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0007 Category_Desi gnation_Memo _Ordnance_VR A_Turn_Pads

Environmental and Site Category Memorandum

27 Oct 2023 Attach ment

No

To:

Identifie r

Document Name

Document Description Reference Identifier

Date Line Item Page N umbers

Docum ent Type

Provide d Under Separat e Cover

0007 Category_Desi gnation_Memo _Ordnance_VR A_Turn_Pads

Environmental and Site Category Memorandum

27 Oct 2023 1 Attach ment

No

The following contract documents were added:

1188_FORT_G-A_RECOVERY_RANGE_REV1_SPECS

1188_FORT_G-A_RECOVERY_RANGE_Rev1_PLANS_signed Category_Designation_Memo_Ordnance_VRA_Turn_Pads

The following contract documents were deleted:

1188_FORT_G-A_RECOVERY_RANGE_100pct_PLANS_signed

1188_FORT_G-A_RECOVERY_RANGE_SPECS

The following contract documents Page Counts were changed:

W9123626BA0060006

DOCUMENT PAGE COUNTS

DOCUMENT NAME FROM TO

Category_Designation_Memo_Ordnance_VRA_Turn_Pads none 1

Section 00 22 13 - Supplementary Instructions to Bidders

Miscellaneous text in this section has been added to:

ProjNet Bidder Inquiries and Corresponding Government Responses:

1. Inquiry ID: 11888601

Section 00 21 00 - Instruction of the RFP (page 6 of 85) provides no specific information for the Site Visit and the fields in this section are blank. Also, we are not able to locate the information elsewhere in the RFP. We request specific instructions how and when we may attend a site visit, please.

Government Response:

See Section 00 21 00 in amendment 0001 of the solicitation.

2. Inquiry ID: 11889672

Since the project is solicited as 100% competitive 8(a) small business set-aside, is the pool of offerors limited to those located within the jurisdiction of the Virginia Richmond District of the Small Business Administration?

Government Response:

Eligibility to submit a bid is not restricted to firms located within the jurisdiction of the SBA Richmond District. Any SBA certified 8(a) participant that meets the solicitation requirements is eligible to compete.

3. Inquiry ID: 11891970

Spec calls a Quality Control Manager to hold a current professional engineer registration with State of Virginia. It's not a common situation that a Prime Contractor employs such individuals, and they can meet other requirements. Please consider to waive this request and clarify how many years of experience QCM needs to have (spec provides conflicting 5 or 10 years requirements).

Government Response:

Reference 1.6.2.2 Qualifications. The requirement for PE or architect license is removed and change pages for 01 45 00 will be provided via an upcoming amendment of the solicitation. The 10 years' experience will remain.

For clarity, the 2nd subparagraph beginning with 'The QC Manager must be a graduate engineer,..." will be removed. The first subparagraph beginning with "The QC Manager must be an individual with..." will remain.

4. Inquiry ID: 11891995

Spec calls a QC Specialist to hold a current professional engineer registration with State of Virginia. It's not a common situation that a Prime Contractor employs such individuals. Please consider waiving this request and alternate requirements for this role. Alos, advise if this individual needs to be on site all the time during the project.

Government Response:

The requirement for registered professional engineer in the state of Virginia is removed for QC Specialist.

A QC specialist needs to be on site at all times during any part of the concrete pad construction including form installation, steel reinforcement installation, and placing and finishing concrete.

01 45 00, Paragraph 1.6.5 will be revised via an upcoming amendment to incorporate the above response.

5. Inquiry ID: 11898392

Has the site been cleared of UXO?

Government Response:

Range Control has indicated that no UXO survey is required.

6. Inquiry ID: 11908233

In the Specifications provided, under section 32 13 13.06 (1.3.2.2) it calls for a combination of certain numbers of NRMCA and ACI certified crew members working on/overseeing the placement crew.

Please clarify that this is intended for QC, QA and Superintendents/Foremen, and not the normal labor force placing and finishing the concrete.

Government Response:

These certifications may be held by Concrete Subcontractor QC or Superintendent/Foreman.

7. Inquiry ID: 11908237

At the site visit, documents with aerial photos and phasing details were passed out. There are conflicts between these documents and the phasing details shown on plan sheet G-005. Turning Pads 7, 9, and 24 all have conflicts. Please confirm the correct phasing of the turning pads.

Government Response:

Refer to Sheet G-005 for phasing of turning pads.

8. Inquiry ID: 11914924

Pages 3 and 85 of 85 of the SF1442 Description of the Project refers to 24 CTPs, however Sheet G-005 of the project drawings identifies 28 CTPs (numbered TP1-TP31 with numbers 11,25, and 30 omitted). Please clarify.

Government Response:

Refer to sheets C-507 through C-512 for exact number and size of turning pads. Please note that four turning pads have two turning pad numbers on the base's numbering convention despite being one concrete pad. These are as follows: TP 3 and TP 4 (sheet C-507 detail A2), TP 2 and TP 20 (sheet C-507 detail D9), TP 13 and TP 14 (sheet C-509 detail E13), and TP 22 and TP 23 (sheet C-511 detail A9).

9. Inquiry ID: 11914925

Pages 3 and 85 of 85 of the SF1442 Description of the Project refers to 24 CTPs, however Sheet G-005 of the project drawings identifies 28 CTPs (numbered TP1-TP31 with numbers 11,25, and 30 omitted). Please clarify.

Government Response:

Duplicated question. See Inquiry 11914924 response.

10. Inquiry ID: 11914938

Note 1 for 'Laydown Notes' on G-004 reefers to being responsible for permits for the laydown areas. What permits will be required?

Government Response:

Per the specifications, testing is contractor-furnished.

11. Inquiry ID: 11914953

Do the three CLINS represent the three phased work areas?

The CLINs listed represent all work required.

12. Inquiry ID: 11914958

Are all three CLINs expected to be funded and executed within the 365-day period of performance?

Government Response:

All CLINs are anticipated to be funded and all work is expected to be executed within the 365-day period of performance.

13. Inquiry ID: 11914959

Are all three CLINs expected to be funded and executed within the 365-day period of performance?

Government Response:

All CLINs are anticipated to funded and all work is expected to be executed within the 365-day period of performance.

14. Inquiry ID: 11914964

Are there any hazardous materials expected to be encountered?

Government Response:

No hazardous materials are expected to be encountered during this project.

15. Inquiry ID: 11914965

Are there any hazardous materials expected to be encountered?

Government Response:

No hazardous materials are expected to be encountered during this project.

16. Inquiry ID: 11916189

Are there CADD drawings available?

Government Response:

The CADD drawings will be provided to the awardee of the contract and after the award.

17. Inquiry ID: 11916192

Notes #5 and #8 imply we should fill the existing BMP up to elevation 90 ft. Elevation 90 would almost completely fill the BMP and be over the inverts of the pipes going into it. Should the notes state to restore to Elevation 80?

Government Response:

Correct, both notes should say Elevation 80.

The drawings will be updated in an upcoming amendment to the solicitation.

18. Inquiry ID: 11916297

Will a drawing for the underground utilities be provided? Will electricity and water be provided for an onsite trailer at no cost to the contractor?

Government Response:

The contractor will coordinate with the individual privatized utility providers to acquire the utility services.

19. Inquiry ID: 11916329

Once the CCTV inspection Report has been completed will pipe replacement if necessary be considered a modification/change order or does the government have an estimated quantity of pipe replacement they would like us to consider for the proposal?

Government Response:

There is no direction provided to conduct a comprehensive, initial CCTV. Direction for replacement of specific pipes has been provided on the plan sheets. Regarding the outfall pipes from the BMPs, a note to clean the pipe and repair the inlet will be added to Sheets CG108 & CG111. This will be published via an upcoming amendment to the solicitation.

20. Inquiry ID: 11922682

The specifications require the contractor to locate utilities using GPR and verify elevations. Can the Government provide any existing utility as-built drawings, utility surveys, or previous GPR investigations to supplement the contract documents?

Government Response:

Any available as-builts will be provided to the awarded contractor and after award.

21. Inquiry ID: 11922684

If unsuitable or unstable soils are encountered beneath the turning pads or roadways beyond those anticipated by the plans, will undercutting and replacement be handled by contract modification?

Government Response:

If unsuitable soils are encountered, notification will be made to the Government and resolution may involve a contract modification. If soils are deemed unstable due to moisture, specification requirements shall be followed.

22. Inquiry ID: 11922686

Existing culverts are to be maintained, repaired, or replaced as required. Will the Government provide CCTV inspections or condition assessments identifying which culverts are expected to require replacement versus cleaning?

Government Response:

Refer to plan sheets identifying which culverts are to be replaced versus repaired versus cleaned.

23. Inquiry ID: 11922687

Will Phase 2 and Phase 3 proceed immediately following Phase 1 if options are exercised, or could there be significant delays between phases?

Government Response:

Please refer to solicitation section 00 00 00.

24. Inquiry ID: 11922689

Please provide the acceptable finished grading tolerances for training roads and turning pads, including allowable deviations from design elevations.

Government Response:

See Spec section 32 13 13.06 Table 1 for concrete, for gravel +/- 0.1 ft or as directed by the contracting officer in the field.

25. Inquiry ID: 11922690

During Army training operations adjacent to active construction, what work restrictions, or temporary work stoppages should contractors anticipate?

Government Response:

No work stoppages should be encountered in active construction phase.

26. Inquiry ID: 11922691

The plans reference road "redressing" and maintenance. Please clarify the required depth of repair and whether scarification, additional aggregate, or complete regrading is anticipated in areas not specifically detailed.

Government Response:

See detail A2 on sheet C-504.

27. Inquiry ID: 11922693

Are the haul routes identified on Drawing G-001 mandatory, and what weight restrictions or seasonal restrictions apply?

Government Response:

Yes, unless otherwise directed by the Contracting Officer in the field. No weight or seasonal restrictions.

28. Inquiry ID: 11922695

Please confirm whether all concrete testing, density testing, aggregate testing, and other quality control testing are contractor-furnished or will the government will provide testing?

Government Response:

Per the specifications, testing is contractor-furnished.

29. Inquiry ID: 11922696

Will the Government designate borrow or waste areas on the installation, or is the contractor responsible for importing/exporting all material?

Government Response:

The contractor is responsible for import/export of all material.

30. Inquiry ID: 11922697

Are locally available concrete mix designs acceptable provided they meet specification requirements, or are there installation-specific mix requirements?

Government Response:

See Spec section 32 13 13.06 Paragraph 2.1

31. Inquiry ID: 11922698

Will the Government establish horizontal and vertical control points, or is the contractor responsible for establishing all project control?

Government Response:

Use control points as established on survey (see sheet V-001).

32. Inquiry ID: 11922700

Should cleaning of all existing systems receiving new drainage be considered as part of our bid?

Government Response:

Cleaning of the culverts affected by construction is typical and expected.

33. Inquiry ID: 11922715

Could the bid due date be extended two additional weeks to allow for the incorporation of all RFI answers into the pricing?

Government Response:

The Bid Due Date and Bid Opening Date has been extended. Please see Amendment 0004 of the solicitation via SAM.gov and PIEE.

34. Inquiry ID: 11922868

Is the project Tax Exempt?

Government Response:

Refer to FAR Clause 52.229-3 listed in the Solicitation.

35. Inquiry ID: 11923175

DFARS 252.204 7012 applies only when Covered Defense Information (including CUI) will be transmitted, stored, or generated as part of contract performance. After reviewing the solicitation documents, amendments, and pre bid materials, we are unable to find any CUI or CDI content included or required. Could you please confirm whether DFARS 252.204 7012 is intended to apply to this solicitation? If the Government does not anticipate any CUI/CDI being provided or created during performance, we respectfully request removal of the DFARS 7012 clause to avoid unnecessary restrictions on competition and subcontractor participation.

Although the Government does not anticipate providing Covered Defense Information (CDI) or Controlled Unclassified Information (CUI) as part of this procurement action, the awardee will be required to comply with the requirements of DFARS 252.204-7012 if any such information is shared with the contractor. DFARS 252.204-7012 will remain in the solicitation.

36. Inquiry ID: 11923579

Will the government grant a 10-day extension in anticipation of many requests for information so that offerors have time to respond appropriately?

Government Response:

Yes. The Bid Due Date and Bid Opening Date has been extended. Please see Amendment 0004 of the solicitation via SAM.gov and PIEE.

37. Inquiry ID: 11923581

Is the "Definitive Responsibility Critieria Information" section the same as "Responsibility Documents, optional (See Instructions Section 3)," referred to in "Documents to be submitted prior to the Bid Closing Date?" Is this section truly optional, and will offerors who do not provide this be viewed as weaker?

Government Response:

As stated in Instructions to Bidders Section 3, the Responsibility Documents, which include Definitive Responsibility Criteria Information, are not required to submit a bid.

If the information is not submitted with the bid, the apparent low bidder will be required to provide it within three (3) working days of the Government's request as part of the responsibility determination conducted prior to award.

38. Inquiry ID: 11923584

Should offerors submit all required documents in one proposal volume?

Government Response:

Offerors should submit all required documents in one proposal volume.

39. Inquiry ID: 11923587

"How are we to break-out the Priority Phasing concerning the greenbelt items? (e.g.: E&S, Demo, Storm/channels, & grading) The Phasing mark-ups at Pre-Bid visit, overlap & show non-scope highlights on roading. Please clarify Phase boundaries."

Refer to Sheet G-005 and read notes on that sheet for phasing of the project.

40. Inquiry ID: 11923595

Assumingly, the Construction Sequence applies to each Priority

Phase (as progressive); or are the C-501 Notes 9.1 - 9.6 universal then the project Phases begin?

Please clarify on how the project is to progress.

Government Response:

The construction sequence described in Note 9 on sheet C-501 applies to every bid option (aka "phase"). If there is an instance where it makes more sense to do otherwise (e.g., leaving up sediment controls in certain areas between Bid Options), obtain Contracting Officer approval before proceeding.

41. Inquiry ID: 11923605

There appears to be variations between the existing conditions contouring represented on the "V" sheets, as to the "CD" demo sheets, while Sheet V-001 Note #4 states to utilize the "CD" sheets for construction information.

Please clarify, as the greenbelt area takeoffs would be affected.

Government Response:

Both the V and CD sheets reference the exact same survey file. Please note that while the V sheets represent purely existing conditions, the CD sheets also incorporate planned demolition work, which may account for some differences in appearance. Ultimately, the contractor is responsible for field verifying all existing site conditions as the site may have changed since the 2024 survey.

42. Inquiry ID: 11923615

"Grading sheets CG108,110, & 111 each have notes on repairing basin side slopes and/or restoring the basin back to original design (10' depth/elevation 90 (528,000 cubic ft)) without design /proposed grade or further instruction. Please clarify the required scope."

Government Response:

The objective of the work on Wet Ponds #2 and #3 is to perform maintenance to restore their design functionality and ensure the basins are prepared to handle the additional stormwater load from the new development.

For Wet Pond #3 (located southeast, outside of the fence line), the scope requires the removal of all woody vegetation growing on the earthen berm and around the outlet structure. The contractor must locate, inspect, clean, and repair the outlet structure as necessary to restore it to fully functional condition.

For Wet Pond #2 (located south-center), the scope requires dredging accumulated sediment to restore the original design volume of 528,000 cubic feet and a working depth of 10 feet. As-Builts of the wet pond will be provided to the contractor upon award. Please note that the keynote on sheets CG110 and CG111 contains an elevation typo; the correct bottom elevation is 80 feet, not 90 feet. Additionally, the contractor must clear all woody vegetation within 25 feet of the outfall.

The outlet structure must be located, inspected, cleaned, and either repaired or replaced as necessary to ensure proper operation. Original outfall details are located on sheet C-514, and the complete set of original wet pond construction documents will be provided to the contractor after the contract is awarded.

43. Inquiry ID: 11923629

Concerning contaminated stone/soils; it was mentioned at the site visit that the intent to handle such is an "on-site"/'on-base" location to rid of these and/or that the material would stay within the control of the base to avoid complicated processing to haul off-site. Is there confirmation to this: as to avoid fees for haul-off and disposal?

Government Response:

The Contractor should base proposal on offsite disposal.

44. Inquiry ID: 11923636

"The statement is to place 6"" inches of 21Bs but the plan detail callouts are for (4) four. Please confirm."

Government Response:

4" of 21B is correct.

45. Inquiry ID: 11923648

During the site visit with the Army Corp & US Army facility sergeant, it was stated that there is not a requirement for "special badging" and/or clearance (as a FOR), however, that every contractor is responsible for the "legal working and clearance status" of each employee on-site. It was further stated that the gates will be "posted" for access during operations to ensure fluid access to/from the site with little delay, and that during critical concrete deliveries especially. We would like a confirmation please, as complications with access could hinder/delay the operation and scheduling.

Government Response:

It is the Contractor's responsibility to verify and maintain legal working and clearance status for each of their employees. Access gates to the site will remain closed at all times. However, a strategy for Contractor access will be established at the Pre-Construction meeting.

46. Inquiry ID: 11923661

Please confirm that the drawing set titled '100% Submittal - Not for Construction,' dated November 3, 2025, is the controlling issued-for-bid contract drawing set for solicitation W9123626BA006.

Government Response:

The controlling issued-for-bid drawing set was issued in solicitation amendment 0005.

47. Inquiry ID: 11923669

Please confirm that the only turning pads to receive new concrete pavement under this contract are TP1, TP2, TP3, TP4, TP5, TP6, TP7, TP8, TP9, TP10, TP12, TP15, TP16, TP17, TP18, TP19, TP20, TP21, TP22, TP23, TP24, TP26, TP28, and TP29.

Government Response:

Refer to sheets C-507 through C-512 for exact number and size of turning pads.

48. Inquiry ID: 11923674

Please identify whether any road, drainage, grading, erosion-control, or transition work is required at TP13, TP14, TP27, or TP31.

Government Response:

See sheets CS101 - CG112 for work done on all turning pads. Grading, erosion-control, and transition work is required on all turning pads. Drainage is required where specified on the plans.

49. Inquiry ID: 11923681

Please define the Government acceptance criteria that must be satisfied before the contractor will be released from one priority phase to begin the next priority phase.

Government Response:

Prior to release to the next priority phase, the Government will conduct a final inspection, and all punch list items for the current phase must be corrected and accepted by the Government.

50. Inquiry ID: 11923686

Please provide the planned Government inspection and acceptance duration between completion of one priority phase and authorization to commence the next priority phase.

Prior to release to the next priority phase, the Government will conduct a final inspection, and all punch list items for the current phase must be corrected and accepted by the Government.

51. Inquiry ID: 11923692

Please identify the anticipated date or contract milestone by which the Government intends to exercise CLIN 0002.

Government Response:

All CLINs are anticipated to be funded and all work is expected to be executed within the 365-day period of performance.

52. Inquiry ID: 11923699

Please identify the anticipated date or contract milestone by which the Government intends to exercise CLIN 0003.

Government Response:

In the solicitation, refer to clause 52.217-7.

53. Inquiry ID: 11923703

Please confirm whether the 365-calendar-day contract duration applies to CLIN 0001 alone if CLINs 0002 and 0003 are not exercised.

Government Response:

All CLINs are anticipated to be funded and all work is expected to be executed within the 365-day period of performance.

54. Inquiry ID: 11923709

Please confirm whether the Government has established required interim completion dates or maximum durations for Priority One, Priority Two, or Priority Three.

Government Response:

All CLINs are anticipated to be funded and all work is expected to be executed within the 365-day period of performance.

55. Inquiry ID: 11923716

Please provide the date, time, meeting location, registration procedure, and Government point of contact for the organized site visit.

Government Response:

The site visit was completed on 7 July 2026.

Post contract award, the required registration procedure and Government point of contact will be provided to the awardee.

56. Inquiry ID: 11923718

Please provide all available utility record drawings, installation utility maps, and utility-owner information applicable to the limits of construction.

Government Response:

Utility owners will be provided after the award. The contractor will be responsible for contacting Dig Safe 811 for marking designated areas as required. See Drawing Sheet C-001.

57. Inquiry ID: 11923721

Please confirm whether test pits and hand-excavated utility verification required before construction are incidental to the applicable CLINs.

Government Response:

The contractor will be responsible for contacting Dig Safe 811 for marking designated areas as required. See Drawing Sheet C-001.

58. Inquiry ID: 11923723

Please confirm that relocation or redesign required because of an existing utility not shown in the contract documents will be addressed as a differing site condition or contract change.

Government Response:

This will be addressed on a case by case basis in accordance with the terms and conditions under FAR 52.236-2 Differing Site Conditions.

59. Inquiry ID: 11923726

Please provide all available geotechnical reports, boring logs, laboratory test data, pavement evaluations, and subsurface investigations for the project site.

Government Response:

A 2007 geotechnical report will be provided to the awardee and after contract award.

Other documents such as the 2024 survey, original drawing as builts, and other existing data about the site will be provided to the contractor after the contract is awarded.

60. Inquiry ID: 11923730

Please confirm how removal and replacement of unsuitable material encountered below the indicated excavation limits will be measured and compensated.

Government Response:

Contractor will provide Geotech and notify the USACE COR. This will be addressed on a case by case basis.

61. Inquiry ID: 11923743

Please confirm whether rock excavation is anticipated within the project limits.

Government Response:

The excavation of large rocks is not anticipated.

62. Inquiry ID: 11923745

Please provide available information concerning seasonal groundwater, perched water, or known dewatering conditions along the proposed culvert and drainage work.

Government Response:

A 2007 geotechnical report will be provided to the awardee and after contract award.

Other documents such as the 2024 survey, original drawing as builts, and other existing data about the site will be provided to the contractor after the contract is awarded.

63. Inquiry ID: 11923751

Please identify the exact culvert designations and lengths requiring cleaning or unclogging under each CLIN.

Government Response:

All work not specified as being in a bid option (see G-005) is in "Base Bid" phase. As such, culverts called out as requiring cleaning or unclogging are considered Base Bid, see plan sheets for lengths.

64. Inquiry ID: 11923756

Please define the work included under 'minor repairs' to existing culverts.

See sheets CD101 - CG112 for work done on culverts. Most culvert work involves cleaning (see CG101-CG112), removal (CD101-CD112), or replacement (CD101-CG112). Two locations involve locating, inspecting, and cleaning/repairing/replacing a drop inlet as needed depending on their current conditions (CG108 & CG111).

65. Inquiry ID: 11923760

Please confirm whether all drainage components shown as damaged, broken, or destroyed on existing-condition drawings are required to be replaced under the applicable CLIN.

Government Response:

All drainage components shown as damaged, broken, or destroyed on existing-condition drawings are required to be replaced under the applicable CLIN.

66. Inquiry ID: 11923763

Please provide any Government-prepared quantity takeoff, design quantity report, engineer's quantity estimate, or earthwork summary available for bidder use.

Government Response:

The Government will not provide the requested quantity or estimates. Bidders are responsible for developing their own quantities based on the solicitation documents using a construction estimator or applicable method.

67. Inquiry ID: 11923766

Please provide the native civil CAD files, surfaces, alignments, and pipe-network files used to prepare the contract drawings.

Government Response:

The CAD files including the Civil 3D surfaces of existing and proposed conditions, and pipe networks will be available at project award.

68. Inquiry ID: 11923770

Please provide the existing-ground digital terrain model or survey point file used to prepare the grading drawings.

Government Response:

The CAD files including the Civil 3D surfaces of existing and proposed conditions will be available at project award.

69. Inquiry ID: 11923774

Please provide the proposed-finish-grade digital terrain model used to prepare the contract grading plans.

Government Response:

The CAD files including the Civil 3D surfaces of existing and proposed conditions will be available at project award.

70. Inquiry ID: 11923779

Please confirm that the concrete pavement limits shown on the CS drawings include all thickened edges, transitions, and approach aprons required under each turning-pad quantity.

Government Response:

Concrete pavement limits on the CS sheets include the thickened edges.

Transitions and Approach Aprons are gravel.

71. Inquiry ID: 11923783

Please confirm whether the existing 12-inch VDOT No. 3 aggregate subbase is to remain in place beneath every new turning pad unless specifically shown for removal.

Government Response:

The existing VDOT No. 3 aggregate subbase is to remain in place.

72. Inquiry ID: 11923787

Please confirm how deficient or contaminated existing VDOT No. 3 aggregate discovered below the turning-pad excavation will be handled for compensation purposes.

Government Response:

The existing VDOT No. 3 aggregate subbase is to remain in place with no deficient No. 3 aggregate expected.

73. Inquiry ID: 11923791

Please identify the required corrosion-resistant reinforcing steel material and applicable ASTM designation for the No. 4 bars.

Government Response:

Refer to specifications: SECTION 32 13 13.06, 2.1.5.3 - REINFORCEMENT

"Bar reinforcement conforming to ASTM A615/A615M, Grade 60. Epoxy coat in accordance with

ASTM A775/A775M."

74. Inquiry ID: 11923796

Please identify the required corrosion-resistant material and coating system for the one-inch pavement dowels.

Government Response:

Dowels: 1" diameter plain billet-steel bars. Paint and oil on one end. ASTM A615 (2020) and ASTM A775 (2017) should be used.

Refer to specifications: SECTION 32 13 13.06, 2.1.5.1 - DOWEL BARS

"Dowel bars conforming to ASTM A615/A615M, Grade 60 for plain billet-steel bars of the size and length indicated. Remove all burrs and projections from the bars. Epoxy coat in accordance with

ASTM A775/A775M."

75. Inquiry ID: 11923801

Please confirm whether a previously approved USACE or VDOT concrete pavement mix may be submitted in lieu of project-specific trial batching.

Government Response:

Sec 32 13 13. 06 Para 2.2.3 that states an existing mix design may be submitted if developed within the previous 12 months.

76. Inquiry ID: 11923805

Please identify whether concrete truck deliveries or placements will be restricted during scheduled Army training periods.

Government Response:

Deliveries will not be restricted during construction. Placements can be coordinated as required with the COR.

77. Inquiry ID: 11923807

Please identify any Government-imposed maximum concrete haul time or batch-plant distance beyond the specification's general placement requirements.

Government Response:

Spec Section 32 13 13.06, para 1.4 provides guidance through ASTM C94.

78. Inquiry ID: 11923808

Please provide station limits and widths for all gravel-road redressing and maintenance required under CLIN 0001.

Government Response:

Stations and widths are per plan. Critical to Gravel Road Maintenance is to reestablish a crown and cross slope and to smooth and compact the roadway.

79. Inquiry ID: 11923811

Please confirm the exact station limits, width, and required section for Road A maintenance between TP12 and TP13.

Government Response:

Stations and widths are per plan. Critical to Gravel Road Maintenance is to reestablish a crown and cross slope and to smooth and compact the roadway.

80. Inquiry ID: 11923815

Please confirm the required compacted aggregate depth for gravel-road redressing where the drawings do not identify a specific undercut or new aggregate depth.

Government Response:

The reshaping of the road will include grading of the existing roadway to reestablish the crown and the cross slope and then compacting the surface.

81. Inquiry ID: 11923826

Please confirm whether the contractor must furnish sufficient aggregate to achieve the finished roadway section regardless of the amount of reusable existing aggregate.

Government Response:

The expectation is that new aggregate will be used adjacent to the concrete turning pads.

82. Inquiry ID: 11923831

Please define the contractor's restoration responsibility for damage to Government roads outside the limits of construction caused by normal construction traffic.

Government Response:

Roadway conditions will be evaluated at the end of the project and compared to the pre-existing survey to determine the extent of the Contractor's responsibility for repairs

83. Inquiry ID: 11923835

Please confirm whether the Government and contractor will conduct a joint preconstruction condition survey of all haul routes before construction traffic begins.

Government Response:

A pre-existing condition survey will be conducted with Contractor prior to commencement of work.

84. Inquiry ID: 11923839

Please provide the allowable limits, usable acreage, surface condition, and load restrictions for Laydown/Stockpile Area No. 1.

Government Response:

The limits are per plan and reflect the existing area being used for staging of vehicles.

There are no load restrictions on Laydown/Stockpile Area No. 1.

85. Inquiry ID: 11923846

Please confirm that Laydown/Stockpile Area No. 2 will become available upon Government release of Priority Three without separate rental or permit cost.

Government Response:

Laydown / Stockpile area #2 will be available for Laydown and Stockpile during the construction of bid option 3. Rent is not charged for the use of government designated laydown areas. See specs for contractor permit requirements.

86. Inquiry ID: 11923849

Please define the required final restoration standard for the laydown and stockpile areas.

Government Response:

G-004 provides direction to return their condition prior to construction.

87. Inquiry ID: 11923853

Please identify whether Government-furnished construction water will be available and the location of the authorized connection point.

Government Response:

Contractor shall coordinate with water company for service and payment.

88. Inquiry ID: 11923856

Please identify whether Government-furnished temporary electrical service will be available at the project site.

Government Response:

Contractor shall coordinate with power company for service and payment.

89. Inquiry ID: 11923860

Please confirm whether the contractor must provide portable sanitary facilities within the training range.

Government Response:

Yes the contractor must provide portable sanitary facilities within the training range for contractor use.

90. Inquiry ID: 11923862

Please confirm that all independent material testing and laboratory services are contractor-furnished and included in the applicable CLINs.

Government Response:

All required testing and laboratory services are contractor-furnished and included in the applicable CLINs

91. Inquiry ID: 11923866

Please identify whether the Government intends to perform separate acceptance or verification testing in addition to contractor quality-control testing.

Government Response:

The specifications alone provide guidance on acceptance and verification testing. Specifically, see the following Specification Locations:

1. Sec 01 32 01.00 10 Para 3.3.19 Cost Loading and Closeout Activities

2. Sec 01 45 00 Para 1.9.3 Final Acceptance Inspection

2. Sec 31 05 19.13, Para 2.2 Inspections, Verifications, and Testing

3. Sec 32 13 13.06 para 1.5 Acceptance & 2.2.3, Mix Verification Tests

92. Inquiry ID: 11923867

Please identify all environmental, land-disturbance, stormwater, wetland, or installation permits already obtained by the Government for this project.

Government Response:

See Spec Section 01 57 19. The government will not be obtaining any permits.

93. Inquiry ID: 11923869

Please identify all environmental or land-disturbance permits that must be obtained and paid for by the contractor.

Government Response:

See Spec Section 01 57 19

94. Inquiry ID: 11923871

Please identify any seasonal environmental restrictions, protected-species limitations, archaeological restrictions, or tree-clearing windows applicable to the work area.

Government Response:

The time of year restriction involves tree removal. No Trees can be felled from 1APR to 30SEP.

This applies to trees with stem 3+ inches in diameter at 4 feet above ground.

95. Inquiry ID: 11923874

Please provide any available information concerning contaminated soil, unexploded ordnance, petroleum-impacted material, asbestos-containing drainage materials, or other hazardous material within the work limits.

Government Response:

In preparation for this project, the Installation Environmental Officer performed an Environmental Survey and Site Category determination. The site was categorized as Category II: There is no known contamination; there remains some potential that contamination may be encountered during construction. If this occurs, it will be treated as a change and handled per the Differing Site Conditions clause.

The memorandum detailing this information will be provided in an upcoming amendment to the solicitation.

96. Inquiry ID: 11923926

Please clarify if both Section 00 10 00 and Attachment 1 need to be filled out and submitted or just Attachment 1.

Government Response:

Submit the Bid Schedule per the Instructions to Bidders listed in the solicitation.

97. Inquiry ID: 11923933

Will the Government accept a validity period less than 120 calendar days, such as 60 calendar days.

Government Response:

The validity period listed will remain as stated on the solicitation.

98. Inquiry ID: 11924064

Is silt fencing supposed to be around the LOD or only on this section?

In addition, is construction wire fencing supposed to be considered only as indicated on page 22 of the drawings or around the entire project area?

Could you please confirm where the new storm culvert that we are supposed to provide in Drawing CG 111 is located?

Government Response:

1. Silt fencing for erosion and sediment controls are per plan or per direction of the contracting officer. The expectation is that adjustments can made in the field to accommodate the phasing of any grading.

2. Culverts 9 & 10 are per plan on Sheet

99. Inquiry ID: 11924113

Please provide clarification for Section 1: "Documents to be submitted prior to the Bid Closing Date:" item number 5 "Responsibility Documents, optional" (See Instructions Section 3)".

QUESTION: Are the items a) through g) considered "OPTIONAL" to be submitted once the firm is selected for award - or are items a) through g) required within our proposal, prior to the Bid Closing Date?

Government Response:

Responsibility Documents and Definitive Responsibility Criteria Information are optional for submitting with the bid.

100. Inquiry ID: 11993052

Per Section 32 13 13.06 Subsection 1.3.2.2 Field Technicians, the concrete contractor is to have no less that 3 NRMCA certified installers and at least 2 American Concrete Institute Flatwork Finisher Certified Installers on site working during all concrete placement. Please confirm that this requirement is true.

Government Response:

The specification is correct.

101. Inquiry ID:11993053

Per Section 31 00 00 Subsection 3.9 Testing, Laboratory Testing of the gradation and maximum density for imported material must be completed at a rate of one test per every 20 cubic yards.

This would amount to testing every truckload for crushed aggregate. Please confirm that this amount of testing is required.

Government Response:

This requirement has been changed in Amendment 0005. See Sec. 31 00 00 paragraph 3.8 Table

1. It now says:

"For prepared subgrade, structure fill, porous fill and backfill; one test shall be performed per lift for every 2000 sq ft of placed and compacted material. For any distinct and separate work area (ex.

overturn areas) a minimum of one test per lift shall be performed, regardless of the areas size. The number of tests will be determined by whichever of the above options results in the greater number of tests for a given lift."

Amendments to the Technical Specifications and Solicitation are as follows:

1. PLANS Sheets G-004, V-107, V-108, V-112, CD107, CD108, CD112, CG107, CG108, & CG112 updated -Clarification of survey notes and the source of existing topographical data.

2. PLANS Sheet G-005 updated - Clarification of work not specified in a bid option.

3. PLANS Sheet CS107 updated - label for TP 16 added.

4. PLANS Sheets CG110 & CG111 updated - Design depth elevation updated to 80 FT.

5. PLANS Sheets CG108 & CG111 updated - Clarification of scope of work regarding the repair /replacement of the BMP drop inlets, including the fact that the attached pipe is to be cleaned (not relaced) and noting the length of the pipe.

6. PLANS Sheet C-501 updated - Clarification of silt fence header.

7. PLANS Sheet C-503 updated - Removal of a silt fence note.

8. PLANS Sheet C-504 updated - Clarification of aggregate note.

9. SPECS section 01 45 00 - Updating the Experience Matrix table.

IDCode: J
Page: 1
Pages: 27
AmendNo: 0006
EffDate: 14 SEP 2026
ReqNo:
ProjNo: W9123626B1AUI
IssCode: W91236
AdmCode:
IssuedBy: W2SD ENDIST NORFOLK

KO CONTRACTING OFFICE, 803 FRONT STREET

NORFOLK, VA 23510-1096

UNITED STATES

MICHAEL STEVENSON, EMAIL: MICHAEL.L.STEVENSON@USACE.ARMY.MIL TELEPHONE: 757-201-2133 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W9123626BA006
SolDate: 18 JUN 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Solicitation W9123626BA006 is hereby amended as follows:

1. This amendment incorporates ProJNet Inquiries and the corresponding Government responses.

2. The revised Plans and Specifications are attached to this amendment.

3. This amendment does not extend the Bid Due date and Bid Opening Date.

ContNameTitle:
CoNameTitle: MICHAEL HAGERTY
ContDate:
CODate: 14 SEP 2026