This document appears to be a Question Submission Form related to the JBLM Stormwater Inspection solicitation, Solicitation Number W911S823R0007. The key details are:

The solicitation is for stormwater pipe inspection services at Joint Base Lewis-McChord (JBLM). The work is to be performed Monday through Friday, 0800-1700 hours. Contractors are not required to obtain a plumbing license in Washington State to conduct emergency repairs, as repairs are not a requirement of this service. The Performance Work Statement references several technical documents that are to be provided as attachments, including the Army Geospatial Data Layer Quality Assurance Plan, Stormwater Utility Segment data standards, and SDSFIE. The solicitation states that the North American Datum 1983 shall be used for coordinate collection, despite an apparent inconsistency in the PWS. The government intends to evaluate offers and award a contract without discussions, but reserves the right to conduct discussions if necessary.

View the file

Other files

File Type Posted
L2 Questions_ Responses - 5.10.24.pdf PDF
Amendment W911S823R0007 00003.pdf PDF
Amendment W911S823R0007 00002.pdf PDF
TE 5a IGIS Stormwater Utility Node QAP Version 4.0.pdf PDF
TE 5c Utility Feature SW Junction QAP Version 4.0.pdf PDF
Copy of L2 - Questions Submitted 3.19.2024.pdf PDF
Performance Work Statement v12.pdf PDF
Amendment W911S823R0007 00001.pdf PDF
TE 5b IGIS Stormwater Utility Segment QAP Version 4.0.pdf PDF
Performance Work Statement v11.pdf PDF
TE 10 - JBLM MS4 Permit Appendix A - Street Waste Disposal 2022.12.20.pdf PDF
TE 08 - Utility Feature SW Junction QAP Version 4.0 2018.10.19.pdf PDF
TE 04 - UFGS 33 01 30.16 Nov. 2021.pdf PDF
TE 01- Wage Determination No. 15-5539 (rev 24) 2023.12.26.pdf PDF
TE 05 - Location Data 2022.12.20.xlsx XLSX spreadsheet
L2 - Question Submission Form.xlsx XLSX spreadsheet
TE 09 - Pipe Segment Identification v2 2022.12.20.pptx PPTX presentation
TE 02 - Parking 2022.12.20.pptx PPTX presentation
L1 Technical Experience Proposal Form.docx DOCX document
TE 03 - Map_Atlas_Grid 2022.1.25.pdf PDF
TE 07 - IGIS Stormwater Utility Segment QAP Version 4.0 2018.10.19.pdf PDF
W911S823R0007.pdf PDF
TE 06 - IGIS Stormwater Utility Node QAP Version 4.0 2018.10.19.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment L2

1 PWS 1.3

Is Contractor to make contact with facility managers within secure areas, or will KO/COR facilitate communication based on Contractor schedule?

Best to work with COR during scheduleing.A minimum week prior to contact facility manager or units needed.

2 PWS 2.3.1.2

Are working hours limited to Monday through Friday 0800-1700 or are these days and hours flexible? Work will be done Monday through Friday, 0800-1700.

3 PWS 2.5.1

Will Contractor be required to obtain a plumbing license in the State of Washington in order to conduct emergency repairs on JBLM? Repairs is not a requirement of this service.

4 PWS 5.9

Please provide referenced documents not included in TE5 - Army Geospatial Data Layer Quality Assurance Plan (QAP), Stormwater Utility Segment, SDSFIE 4.0 Gold: StormwaterUtilitySegment and SDSFIE Army Adaptation: StormwaterUtilitySegment, Document Version 4.3 see attachments

5 PWS 5.9.1 & 5.9.7

Which datum should be used to collect coordinates? Section 5.9.1 requires WGS84 and 5.9.7 requires NAD83. North American Datum 1983 shall be used, paragraph 5.9.7