1. CCTV - Headend: Com Switch Location:
Cameras Labeled Y N
Camera picture quality (Day & Night) Y N
Camera Alarm Points Set Y N
Camera angle and view as designed w/ no obstructions Y N
Camera mounts anchored tight (Not impacted by wind or other means) Y N
2. CCTV - Location: Com Switch Location:
Hardware and components securely fastened and tight Y N
Outdoor applications – Equipment & Fittings weather tight Y N
Camera components function correctly (Locally) Y N
Camera angle and view as designed w/ no obstructions Y N
Camera mount sufficient and anchored correctly Y N
Housing/Enclosure has heater Y N
For PTZ, dome tint is clear / smoked
W911S8-19-R-0002 Attachment 14, TE13-CCTV Acceptance(PVT) Mstr
Conduit and fittings secured and anchored Y N
Camera location is sufficient to prevent tampering Y N
Other Y N
3. CCTV Submittals:
Project narrative page Y N
Recommended spare parts list Y N
Equipment in place (location, component description, mod/ser#) Y N
Equipment suppliers contact information Y N
Contractor contact information Y N
Camera naming scheme & Settings Updated Y N
Camera and software pre-sets Y N
Alarm pre-sets Y N
W911S8-19-R-0002
DVR recording storage capacity (Note Size and storage retrieval Time) Y N
Software user level/restriction set Y N
Password protection (if required) Y N
Drawings & Block Diagrams Y N
4. Training:
Facility manager trained on the system operation & maintenance Y N
Comments/Problems:______________________________________________________________________
PS Inspector:___________Print(PSS)_________________________Sign________________________________
Sub Contractor:_________Print(Sub)_________ ______________Sign_________________________________
Project Manager:_______ Print (USACE)______________________Sign_____________________________________
Contractor Rep:_________ Print(PrimeContractor)_______________Sign________________________________
W911S8-19-R-0002